Loading...
HomeMy WebLinkAbout[05-b] North Corridor, Scoping Document'`'~~d: c~° uz~ sT JcxsH ~~H MEETING DATE: AGENDA ITEM: Council Agenda Item) b March 5, 2009 Engineer Reports North east/west Corridor Study -Scoping Document SUBMITTED BY: Engineering/Administration BOARD/COMMISSION/COMMITTEE RECOMMENDATION: The North east/west study includes Stearns County and the APO. To help facility the study a TAC and PMT were utilized. During discussions with the TAC it was determined that a four lane road section would be needed and from that a purpose and need was developed and the Scoping document was submitted for review by Fed Hwy Administration. PREVIOUS COUNCIL ACTION: Last year Brian Shorten of SRF presented the Council with the information included in the document. The same presentation was made before Stearns County. The City is the agent for the segment of road included in the Scoping document as it is a City road. The County was the agent for the EAW regarding the CR 2 bypass. BACKGROUND INFORMATION: Brett Danner of SRF highlighted the changes from the last document: 1) Purpose and need: the purpose and need has been updated to include travel demand forecasts and modeling provided by the St. Cloud APO. 2) Alternatives: discussion of how the build alternatives address the purpose and need 3) Project costs: the project cost discussion has been updated to reflect planning-level estimates used by the APO. A future project cost is also included using the APO's inflation factor. Copies of the Scoping Document will also be provided to Mn/DOT and FHWA for review. It is anticipated that FHWA will publish the EIS notice of intent in the near future. Following PMT, Mn/DOT, and FHWA review, there will bean agency review period and public comment period. BUDGET/FISCAL IMPACT: ATTACHMENTS Scoping document REQUESTED COUNCIL ACTION: Authorize execution of the Scoping document so that it can be forwarded for publication and review. SCOPING DOCUMENT AND DRAFT SCOPING DECISION DOCUMENT ST. JOSEPH NORTH CORRIDOR Stearns County, Minnesota February 2009 S.P.233-020-03 SLOPING DOCUMENT ST. JOSEPH NORTH CORRIDOR STEARNS COUNTY, MINNESOTA State Project Number: 233-020-03 Future construction of a new minor arterial roadway connection from CSAH 3 to CSAH 133 north of St. Joseph, Minnesota. Ms. Judy Weyrens City Administrator City of St. Joseph 25 College Avenue North St. Joseph, MN 56374-0668 (320) 363-7201 ~weyrens(a~cityofstjose h.com CERTIFICATION BY RESPONSIBLE GOVERNMENTAL UNIT Date Approved St. Joseph City Administrator TABLE OF CONTENTS Page No: 1.0 INTRODUCTION ...................:.......................:.....:........................................... 1.1 PURPOSE OF SLOPING DOCUMENT ......................................................:...............:......................:.............1 1.2 PROJECT DESCRIPTION ...................................................................:........................................................2 1.3 PROJECT HISTORY ...................................................................................................................................3 1.4 RELATIONSHIP OF ST. JOSEPH NORTH CORRIDOR SLOPING TO OTHER CSAH 2/ NORTH CORRIDOR PROJECTS ..................:.................:...:......................................................................... 3 1.5 PROJECT SCHEDULE ................................................................................................................................4 1.6 RESPONSIBLE GOVERNMENTAL UNIT AND PROJECT MANAGER ...................................:.:....:...................4 2.0 PURPOSE OF AND NEED FOR THE PROJECT ..............................................................:........................5 2.1 INTRODUCTION ........................................................................................................................................ $ 2.2 PREVIOUSLY-IDENTIFIED TRANSPORTATION ISSUES .:............................................................................. S 2.3 BACKGROUND INFORMATION ON PLANNED GROWTH AND ST. JOSEPH LAND USE PLANS .......................:.........................................................................................6 2.3.1 Population and Household Growth Trends ..................................................................:..............6 2.3.2 St. Joseph Land Use and Growth Plans ......................................................................................8 2.3.3 St. Joseph Orderly Annexation Areas ..................................................................,......................9 2.4. PURPOSE AND NEED FOR THE PROJECT .........................................:.............:........................................10 2.4.1 Purpose of the Project ................................................................................:..............................10 2.4.2 Need for the Project ........................................................................:.........................................10 2.4.3 Other Transportation Goals and Objectives ..............................................:..............................16 3.0 DEVELOPMENT OF SLOPING ALTERNATIVES ..............................:..................................................21 3.1 ALTERNATIVES DEVELOPED DURING CORRIDOR STUDY (PRE-NEPA PROCESS .............................:....21 3.1.1 Corridor Study Alternatives Dismissed ....................................................................................22 3.1.2 Corridor Study Alternatives Retained ...................:..................................................................22 3.1.3 Corridor Study Organization ........................................................................:...........................24 3.1.4 North Corridor Identification in Corridor Study ....................................:.....:............................26 3.1.5 Final Corridor Study Alternatives ........: .:.................................................................................27 3.1.6 Tiered EIS Decision ........................:........................................................................................27 3.2 POST-CORRIDOR STUDY ALTERNATIVE CHANGES ................................................................................28 3.3 DESCRIPTION OF SLOPING ALTERNATIVES ..............................................:..:..........................................28 3.3.1 No-Build Alternative ............................:...................................................................................28 3.3.2 Build Alternatives .....:...............................................................................................................28 3.4 BUILD ALTERNATIVES FOR STUDY IN EIS ............................................................................................29 3.4.1 Build Alternative Alignments ...............................................:...................................................29 3.4.2 Build Alternative Typical Section ............................................................................................29 4.0 COST AND FUNDING SOURCE .....................................................................................................29 -i- TABLE OF CONTENTS CONTINUED 5.0 SOCIAL, ECONOMIC AND ENVIRONMENTAL ISSUES ....................................................................30 5.1 ISSUES IDENTIFICATION PROCESS ..........................................................................................................30 5.2 ISSUES TO BE ADDRESSED IN TIERED EIS .............................................................................................31 5.2.1 Issues Requiring Separate Study ..............................................................................................33 5.2.2 Issues of Major Concern Requiring Detailed Analysis .........................,..................................34 5.2.3 Issues of Moderate Concern Requiring Less Detailed Analysis ...............................................41 5.2.4 Issues Not to be Addressed in Tiered EIS ................................................................................46 6.0 PUBLIC AND AGENCY INVOLVEMENT ...............................................................................................46 6.1 COOPERATING AND PARTICIPATING AGENCIES .....................................................................................48 7.0 PERMITS AND APPROVALS .....................................................................................................................49 7.1 PERMITS AND APPROVALS REQUIRED ...................................................................................................49 7.2 LEVEL OF ACTION ................................................................................................................................. SO APPENDICES: APPENDIX A: Scoping Document Figures APPENDIX B: Public And Agency Coordination Plan APPENDIX C: Draft Scoping Decision Document -ii- TABLE OF CONTENTS CONTINUED LIST OF TABLES Page No. TABLE 1 HISTORIC POPULATION COMPARISON (1970-2006) WITHIN THE STUDY AREA .........6 TABLE 2 FUTURE POPULATION GROWTH WITHIN THE STUDY AREA .......................................... ..7 TABLE 3 CITY OF ST. JOSEPH HOUSEHOLD PROJECTIONS .............................................................. ..8 TABLE 4 NORTH ST. JOSEPH GROWTH AREA LAND USE FORECAST GROWTH ......................... 11 TABLE 5 TRIP DISTRIBUTION FOR NORTH ST. JOSEPH GROWTH AREA ...................................... 12 TABLE 6 CRITICAL LANE THRESHOLDS AND CAPACITY RELATIONSHIPS ................................ 14 TABLE 7 CRITCAL LANE ANALYSIS RESULTS: EXISTING AND NO BUILD (CSAH 75 INTERSECTIONS) ............................................................................................................................ 14 TABLE 8 SUMMARY OF EXISTING ACCESS ON CSAH 75 THROUGH ST. JOSEPH FROM CSAH 3 TO CSAH 133 ......................................................................................................... 15 TABLE 9 CSAH 75 AVERAGE DAILY TRAFFIC VOLUMES: 2006 AND 2030 NO BUILD .................. 15 TABLE 10 ST. CLOUD APO SYSTEM SPACING GUIDELINES: URBANIZING AREAS ...................... 18 TABLE 11 CRITCAL LANE ANALYSIS RESULTS: FUTURE BUILD CONDITIONS (CSAH 75 INTERSECTIONS) ......................................................................................................... 23 TABLE 12 TRAFFIC VOLUME FORECASTS: CSAH 75 AND NORTH CORRIDOR ............................. 23 TABLE 13 CORRIDOR VISION AND DESIGN STANDARDS ...................................................................... 29 TABLE 14 ANTICIPATED PERMITS AND APPROVALS REQUIRED ...................................................... 49 LIST OF FIGURES FIGURE 1: AREA LOCATION MAP FIGURE 2: NORTH CORRIDOR SLOPING ALTERNATIVES FIGURE 3: CITY OF ST. JOSEPH -FUTURE LAND USE FIGURE 4: TIER I EIS ALTERNATIVES H:\Projects\5533\EP\Scoping\Reports\Scoping Document\Draft\FHWA MnDOT Review\North Corridor Scoping_02 09.doc - iii - 1.0 INTRODUCTION 1.1 PURPOSE OF SLOPING DOCUMENT The proposed action is the construction of a new minor arterial roadway connection from County State Aid Highway (CSAH) 3 to CSAH 133 in St. Joseph Township, north of the City of St. Joseph in Stearns County, Minnesota (see Figures 1 and 2). The environmental review process for the St. Joseph North Corridor Project assumes that construction would likely use some combination of local, state and/or federal funding sources. As such, the project planning and environmental review are being conducted in conformance with state and federal environmental review requirements. The National Environmental Policy Act (NEPA) of 1969 requires that social, economic, and environmental considerations be included in the planning of projects that receive federal funding and involve other federal actions. Similarly, the Minnesota Environmental Policy Act (MEPA) requires review of potential environmental impacts for proposed projects that exceed state regulatory thresholds. The proposed action meets the state requirements for the preparation of an EIS under Minnesota Rules Chapter 4410.4400 Subp. 16 (construction of a road on a new location which is four or more lanes in width and two or more miles in length). Scoping is the first step in the EIS process. This Scoping Document and Draft Scoping Decision Document (SD/DSDD) has been prepared as part of the federal NEPA process and state environmental review process to fulfill requirements of 42 USC 4321 et. seq., 23 USC § 139, and Minnesota Rules Chapter 4410.2000. The SD/DSDD is distributed to federal, state and local agencies and the public to provide an opportunity for review and comment prior to the preparation of a Final Scoping Decision Document (SDD). A 30-day comment period will begin when the availability notice for the SD/DSDD is published in the Minnesota Environmental Quality Board (EQB) Monitor. A public Scoping meeting will be held during the 30-day comment period (as required by Minnesota Rules Chapter 4410.2100 Subpart 3) which will provide an opportunity for the public to comment on the SD/DSDD. Per Council on Environmental Quality (CEQ) regulations for implementing NEPA (40 CFR 1508.28), environmental documentation may occur through a "tiered" two-step review process. The tiered EIS process has been determined to be appropriate for the proposed action because, while the construction of the project may not occur for 20 or more years, the project area is rapidly developing and future development will likely encroach on potential corridor locations, resulting in greater potential for social and economic impacts at the time the project is funded if an alignment location is not protected in the near future. A Tier I Environmental Impact Statement (EIS) will be prepared that identifies and evaluates the social, economic and environmental issues associated with the Corridor Alternatives, as the basis for identifying a preferred corridor alternative that can be preserved for future use. The Tier I EIS will consist of a Tier I Draft EIS (DEIS), a Tier I Final EIS (FEIS), and a Tier I Record of Decision (ROD). In general, the Tier I DEIS will provide analysis of the potential social, economic, and environmental impacts of all Corridor Alternatives, whereas the Tier I FEIS will provide more detailed analysis of the impacts associated with the alignment identified as the Preferred Corridor Alternative following the DEIS comment period. A Tier II EIS process will St. Joseph North Corridor - 1- February 2009 Scoping Document be initiated in the future, as the project moves forward for implementation. The Tier II process will focus on Preferred Corridor Alternative design details, an updated assessment of environmental impacts, and identification of mitigation. Specific content for the Tier II DEIS and FEIS documents will not be known until they are initiated. This SD provides a discussion of: • The purpose of and need for the proposed project; • Alternatives considered; • Potential social, economic and environmental impacts and discussion regarding to what extent each issue will need to be addressed in the Tier I EIS and how the issue will likely be addressed in the Tier II process; • Permits and approvals likely to be needed prior to construction of the proposed project; • Public and agency coordination plan; and • Agencies and other stakeholders consulted during project development and environmental review process. The scoping process is used to reduce the scope and size of the EIS by selecting a reasonable range of alternatives for detailed study and by identifying the appropriate level of detail for studying issues and impacts. The scoping process is also used to solicit participating and cooperating agency input into the development of the purpose and need for the project and in identifying a reasonable range of alternatives to be studied in the EIS. The DSDD provides a summary of the SD findings and documents the proposed scope and focus of the EIS. The combined SD/DSDD documents are distributed to federal, state, regional and local agencies and the public to provide an opportunity for review of the proposed project and comment on project issues and alternatives prior to the preparation of the final SDD. A final Scoping Decision will be made by the City of St. Joseph, in consultation with the Minnesota Department of Transportation (Mn/DOT) and Federal Highway Administration (FHWA), after the public scoping meeting and at the end of the 30-day comment period. Following completion of the scoping process, a Tier I EIS will be prepared in accordance with the findings of the SD and SDD. 1.2 PROJECT DESCRIPTLON The North Corridor Project study area is located north of the City of St. Joseph, Stearns County, Minnesota (see Figure 1, Appendix A). While the study area is located outside of St. Joseph City limits, it is located within the area of St. Joseph Township programmed for annexation by the City. The study area boundaries extend north from CSAH 75, along CSAH 3 and then east, north of the City of St. Joseph to CSAH 133. The study area currently lacks continuous east-west roadways, other than CSAH 75. CSAH 75 is a principal arterial roadway that bisects St. Joseph, connecting the St. Cloud Metropolitan Area St. Joseph North Corridor - 2 - February 2009 Scoping Document to Interstate 94 (I-94) west of St. Joseph. Existing land uses in the project area are primarily agricultural; however, lands north of St. Joseph are experiencing development pressure as the City expands to the north of its existing boundaries. Aerial photography and parcel boundaries in Figure 3 (Appendix A) illustrate the expansion of residential development to the north of downtown St. Joseph. 1.3 PROJECT HISTORY The North Corridor project is part of a larger arterial concept that connects the greater St. Cloud Metropolitan Area to St. Joseph. For the City of St. Joseph, the North Corridor project is part of a circumferential road system concept that will allow for more effective north-south and east-west travel through and around the city. The North Corridor project has been proposed in order to fulfill the need for enhanced east-west travel in the area. The North Corridor concept has been in St. Cloud Area Planning Organization's (APO) transportation plans dating back to the St. Cloud Area Planning Organization (APO) 2010 Transportation Plan (adopted 1991). This minor arterial is identified as a long-range (20+ years) improvement in the 2010 Transportation Plan. An arterial facility is identified in successive St. Cloud APO Transportation Plans, including the St. Cloud APO 2015 Transportation Plan (adopted 1995), the St. Cloud APO 2020 Transportation Plan (adopted 1998), the St. Cloud Metropolitan Area 2025 Transportation Plan (adopted 2001), and the St. Cloud APO 2030 Transportation Plan (adopted 2005). Most recently, this arterial facility is identified as an illustrative project for purposes of the St. Cloud APO 2030 Transportation Plan. In support of that larger arterial concept, a St. Joseph North Corridor and CSAH 2 Realignment Study (hereafter "2006 Corridor Study") was conducted by the City of St. Joseph, Stearns County, St. Joseph Township, and the St. Cloud Area Planning Organization (APO) in 2005-2006 in an effort to define new primary transportation corridors before the area develops. The purpose of the Corridor Study was to identify corridor alignments that would provide safe, reliable, and efficient mobility for both motorized and non-motorized travel in and around the St. Joseph's area. The Corridor Study included a study area extending north from I-94 across CSAH 75, along CSAH 3 and then east, north of the City of St. Joseph to Westwood Parkway in St. Cloud. The Corridor Study considered project elements beyond what will be studied in the North Corridor's environmental review process (i.e., the realignment of CSAH 2, and the continuation ofeast-west access in the area north of St. Joseph further to the east). Toward the conclusion of the Corridor Study, the study partners, in consultation with FHWA and Mn/DOT, concluded that the original study area consists of three, independent projects for which different environmental documentation should be prepared-the CSAH 2 South Realignment project, .the CSAH 2 North/North Corridor West project, and the North Corridor East project. The "CSAH 2 North/North Corridor West" project identified in the Corridor Study has become the North Corridor project that is the subject of this SD and subsequent Tiered EIS. 1.4 RELATIONSHIP OF ST. JOSEPH NORTH CORRIDOR SCOPiNG TO OTHER CSAH 2/NORTH CORRIDOR PROJECTS St. Joseph North Corridor - 3 - February 2009 Scoping Document The CSAH 2 South Realignment project connects I-94 to CSAH 75 and CSAH 3 west of St. Joseph and was evaluated in a separate Environmental Assessment Worksheet (EAW). This EAW was published by Stearns County in September 2007, and a Negative Declaration was issued in November 2007. Construction of the proposed CSAH 2 South Realignment is planned to occur in two phases. The first phase is construction of a two-lane rural section roadway. The construction of the two-lane roadway is included in the Stearns County Five-Year Highway Work Plan for year 2009. The second phase of the proposed project is construction of CSAH 2 from I-94 to CSAH 3 as four-lane urban section roadway. Timing for construction of the four-lane roadway is currently unknown, but is planned to occur when warranted by development of the surrounding area. The North Corridor East project is the proposed right of way preservation and construction for a new east-west minor arterial roadway between CSAH 133 and the St. Cloud city limit to the east (Rolling Ridge Road). The North Corridor East project is currently under study as part of a combined Environmental Assessment/Environmental Assessment Worksheet (EA/EAW). North Corridor East is not funded or programmed, and is identified as an illustrative project in the St. Cloud APO 2030 Transportation Plan. The environmental review process for North Corridor East is anticipated to be complete in 2009. It is anticipated that an EA re-evaluation, at a minimum, will be required for North Corridor East when construction funding is identified. The location the North Corridor project, in relation to the CSAH 2-South and North Corridor- East projects is illustrated in Figure 2, Appendix A. The North Corridor project described in this document represents a separate action from other projects currently being implemented or planned for the future. There are no immediate project or construction funds programmed for the North Corridor project. Preservation of a corridor for future use at this time is a proactive planning tool that would facilitate orderly development within the St. Joseph area and avoid future social, environmental, and economic impacts that could result when constructing a roadway through an area that has already been developed. 1.5 PROJECT SCHEDULE The following lists the anticipated schedule for completion of project activities: Federal Notice of Intent Scoping Document/Draft Scoping Decision Document Public Scoping Meeting Scoping Decision Document Tier I Draft Environmental Impact Statement Identification of Preferred Alternative Tier I Final Environmental Impact Statement Tier I Adequacy Determination Tier I Record of Decision (ROD) Corridor PreservationlOfficial Mapping Initiation of Tier II EIS Process Winter 2009 Summer 2009 Summer 2009 Fa112009 2010-2011 2012 2013 2013 2013 To Be Determined 3 Years Prior to Construction 1.6 RESPONSIBLE GOVERNMENTAL UNIT AND PROJECT MANAGER St. Joseph North Corridor - 4 - February 2009 Scoping Document The FHWA is the lead federal agency under NEPA. Mn/DOT, as the direct recipient of federal funds for the project, is a joint lead agency under NEPA. The City of St. Joseph, as project sponsor ultimately responsible for design and construction of the proposed project, and as the sub-recipient of federal funds, is also a joint lead agency under NEPA. The City of St. Joseph is the project proposer and Responsible Governmental Unit (RGU) under Minnesota Rules Chapter 4410.0500 for the purposes of this SD/DSDD, and for the EIS, with respect to state environmental review requirements. The contact person for St. Joseph is listed below. Ms. Judy Weyrens City Administrator City of St. Joseph 25 College Avenue North St. Joseph, MN 56374-0668 (320) 363-7201 jweyrens(a,cityofstj oseph. com 2.0 PURPOSE OF AND NEED FOR THE PROJECT 2.1 INTRODUCTION The following sections describe the purpose and need for the St. Joseph North Corridor Project. This discussion includes a summary of previously-identified transportation issues, background information on planned growth and land use plans, and the currently-identified transportation purpose and need for the project. 2.2 PREVIOUSLY-IDENTIFIED TRANSPORTATION ISSUES As described in Section 1.3, the 2006 North Corridor and CSAH 2 Realignment Corridor Study was undertaken to define opportunities for new, primary transportation corridors around the north side of St. Joseph before development could limit or preclude options for a new transportation corridor. The 2006 Corridor Study identified transportation issues in the project area in St. Joseph. These issues, as identified in the 2006 Corridor Study, are summarized below. • Intersection Capacit~perations: CSAH 75 is a four-lane divided expressway that carries regional traffic from I-94, through St. Joseph, to the downtown St. Cloud urban core. CSAH 75 is the only continuous, east-west roadway currently serving the St. Joseph area. Year 2030 traffic forecasts under the St. Cloud APO's financially constrained network show that the CSAH 75/College Avenue and CSAH 75/2nd Avenue intersections would be over capacity. • System Linkage: The project area lacks a network of continuous east-west roadways. The purpose of the 2006 Corridor Study was to work towards developing an arterial network in St. Joseph that provides connections between key corridors and activity centers, and a strong connection between St. Joseph and the St. Cloud Metropolitan Area. To enhance and St. Joseph North Corridor - S - February 2009 Scoping Document maintain the project area's transportation network, the Corridor Study identified a goal of providing supporting arterial roadways every'/z to 1 mile. Consistency with Local Highway Plans: Three transportation plans include an arterial corridor north of St. Joseph. These plans include the St. Cloud APO 2030 Transportation Plan, the City of St. Joseph Comprehensive Plan (2002), and the Stearns County Transportation Plan (1999). ~ Social Demands and Economic Development: Local partners involved with the 2006 Corridor Study acknowledged a desire to identify transportation corridors early, even if the roadways would not be constructed for many years, to make efficient use of public funds for right of way acquisition. Early corridor identification provides local officials with greater opportunities to avoid or minimize impacts and supports organized, thoughtful development of the project area. 2.3 BACKGROUND INFORMATION ON PLANNED GROWTH AND ST. JQSEPH LAND USE PLANS The City of St. Joseph is expanding in all directions. Evidence of these growth patterns is illustrated in demographic statistics {e.g., population growth, household growth), the St. Cloud Area Joint Planning Project District Plan, recent developments within the project area, and City of St. Joseph annexation plans. These items are described below. 2.3.1 Population and Household Growth Trends The City of St. Joseph and Stearns County have both continued to grow in population aver the last four decades; St. Joseph Township experienced rapid growth between 1970 and 1980, but has been losing population since 1980 (Table 1). The City of St. Joseph experienced its highest growth between 1980 and 1990 and again from 2000 to 2006. TABLE 1 HISTORIC POPULATION COMPARISON (1970-2006) WITHIN THE STUDY AREA Year City of St. Jose h % Chan a St. Joseph Townshi % Chan a Stearns Count % Chan e 1970 1,786 -- 1,922 -- 95,400 18.7% 1980 2,994 67.6% .2,916 51.7% 108,161 13.4% 1990 3,294 10.0% 2,567 -12.0% 118,791 9.8% 2000 4,681 42.1 % 2,449 -4.8% 133,166 12.0% 2006 5,873 25.4% 2,139 -14.5% 144,443 8.5% Source: U.S. Census; Minnesota State Demographic Center data as presented in Table 3-1 of the 2008 City of St. Joseph Comprehensive Plan (October 2008 draft). ~ Since completion of the 2006 Corridor Study, the City of St. Joseph Comprehensive Plan and the Stearns County Transportation Plan have been updated. This Scoping Document will reference the 2008 City of St. Joseph Comprehensive Plan and the 2008 Stearns County Transportation Plan. St. Joseph North Corridor - 6 - February 2009 Scoping Document The State Demographer, the St. Cloud APO, and local agencies project continued population and employment growth with the St. Cloud Metropolitan Area and St. Joseph (Table 2). Although the St. Cloud Metropolitan Area consists of communities from Stearns, Benton and Sherburne counties, a majority of land in the metropolitan area is located within Stearns County. As such, a majority of the population growth that is anticipated for the St. Cloud Metropolitan Area is accounted for by growth anticipated in Stearns County. TABLE 2 FUTURE POPULATION GROWTH WITHIN THE STUDY AREA Percent Percent Growth Growth 2000 2006 2020 (2000- 2030 (2000- Jurisdiction Po ulation (1) Po ulation (1) Po ulation~2~ 2020 Po ulation~2~ 2030 St. Cloud Metropolitan Area (3> 113,292 117,574 152,255 34% 173,161 53% Stearns County (portion in St. Cloud Metropolitan Area) g1,238 85,364 107,118 32% 120,208 28% City of St. Joseph ~ 4,681 5,873 12,808 174% 15,753 237% ~'~ Source (2000 and 2006 population data): Minnesota State Demographic Center. c2~ Source (2020 and 2030 population data for St. Cloud Metropolitan Area and Stearns County): St. Cloud APO 2030 Transportation Plan. (3) Includes portions of Stearns County, Benton County, and Sherburne County. (4) St. Joseph Comprehensive Plan (Draft Plan Update). 2008. Projections developed for St. Cloud Area Wastewater Treatment Plant Facilities Plan. As shown, St. Joseph's Comprehensive Plan (October 2008 draft) projects the city's population to more than double, reaching over 12,000 by 2020, a 174 percent growth rate over its year 2000 population. The same source projects St. Joseph's population to grow to greater than 15,000 persons by year 2030, reflecting a 237 percent growth rate over its year 2000 population. These projections were based on those developed for the St. Cloud Area Wastewater Treatment Plant Facilities Plan, and are not intended as an exact prediction of future population. They do, however, provide an indication of potential growth that may be anticipated for facilities planning. Based on various data sources identified in the City's Comprehensive Plan (State Demographer's Office, 1990 Census, 2000 Census) the number of households within the city increased 47 percent for the 10-year period from 1990 to 2000. While the number of building permits approved by the city has declined within the past few years, consistent with regional, statewide, and national trends, moderate household growth is projected within the city through year 2030. The City of St. Joseph expects the number of households within the city to increase nearly six-fold by year 2030 (see Table 3).Z 2 City of St. Joseph Comprehensive Plan. October 2008 draft. Chapter 3. Demographic Trends and Assumptions. Section N. Household Growth. St. Joseph North Corridor - 7 - February 2009 Scoping Document TABLE 3 CITY OF ST. JOSEPH HOUSEHOLD PROJECTIONS Year Households (existing) and Household Forecasts ~1~ 2000 .1,120 2006 1,661 2010 2,171 2015 4,991 2020 5,003 2025 5,433 2030 6,154 Source: Table 3-7 (St. Joseph Population and Household Projections) from City of St. Joseph Comprehensive Plan (October 2008 draft). Household projections for year 2010 and 2015 have been adjusted to account for expected delay in annexation from St. Wendel Township and build out of other residential developments within the city. ~i~ Household forecasts based on populations forecasts for the St. Cloud Wastewater Treatment Facilities Plan and the Minnesota State Demographer's estimate of 2.56 persons/household. 2.3.2 St. Joseph Land Use and Growth Plans As noted above, the city's 2002 Comprehensive Plan (adopted in 2002) and 2008 Comprehensive Plan Update (October 2008 draft) both recognize anticipated growth in the city over the next 20 years. Existing and planned development within the city and planned land uses within the project area are summarized below. Existing_and Planned Development Residential development has continued to push northward in St. Joseph, with the platting of the Northland Heights development and its build-out since 2006. This development is primarily accessed via Northland Drive, and by residential streets that connect to CSAH 2. It is anticipated that Northland Drive would ultimately connect to a roadway at the north end of the subdivision (thereby providing both another outlet for the development and a new north-south community collector in St. Joseph). Along CSAH 133 at the eastern end of the North Corridor study area is the planned Feld Development site. The Feld Development is a 300-acre tract, currently in agricultural uses, that was annexed by the City of St. Joseph in 2006. The Feld site is planned for future mixed used development, with commercial and industrial uses on the southern half and residential land uses on the northern half of the site. The western 55 acres of the Feld site, along CSAH 133, is referred to as the Parkway Business Center, a light-industrial/commercial planned unit development. An EAW was completed for the Parkway Business Center in March 2007. The preliminary plat for the Parkway Business Center has been approved and work is underway on the final plat approval. Municipal services have been extended along CSAH 133 and will serve the Parkway Business Center, ultimately serving the entire 300-acre Feld site. A future Alternative Urban Areawide Review (AUAR) for the Feld site is planned by the City of St. Joseph to address issues associated with land use changes as a result of development of the site. St. Joseph North Corridor - 8 - February 2009 Scoping Document Although not in the North Corridor study area, a large mixed-density residential development being built outside the city's southern limits will add to traffic traveling through St. Joseph. The 464-acre ARCON Development site is bounded by the Sauk River on the south, I-94 on the west, and CR 121 on the east. Municipal services (water, sanitary sewer) have been extended to serve the development area, which was annexed by the City. St. Cloud Area School District 742 (ISD 742) recently constructed a new elementary school on a 71-acre site within the ARCON Development AUAR area at the intersection of Jade Road and CR 121. City of St. Joseph Transportation Plan The city's 2007 Transportation Plan acknowledges the ongoing study being conducted in support of the North Corridor project, and includes the three Build Alternatives that came out of the Corridor Study in its Future Transportation Network mapping. It is anticipated that the city's Transportation Plan will be updated at some point following completion of the North Corridor environmental review. City of St. Joseph Land Use Plans (north St. Joseph growth areal The City of St. Joseph is currently updating its comprehensive plan. The Comprehensive Plan identifies a series of planning districts within the city and in the city's annexation areas. The North Corridor project area is located within a Planning District 3 (north of existing corporate limits) and Planning District 10 (north-central portion of city). Planning Districts 3 and 10 are bound, for the most part, by CSAH 75 to the south and west, St. Wendel Township to the north, and CSAH 133 to the east. Collectively, these areas are referred to as the north St. Joseph growth area throughout this SD. The City of St. Joseph future land use map indicates that the planned future land uses within the north St. Joseph growth area north of CSAH 75 are primarily residential (low- and medium- density), as well as community-oriented mixed use. The area adjacent to the Watab River near the western project limits are identified for open space preservation/wildlife corridor uses. With the exception of the new Northland Heights residential development, the area currently is devoted primarily to agricultural and rural residential uses (see Figure 3, Appendix A). It should be noted that, according to the City's Comprehensive Plan, the future land use map illustrates more acreage than the City will be capable of consuming by year 2030 based on population and household forecasts. The future land use map is consistent with the City's orderly annexation agreement boundaries. 2.3.3 St. Joseph Orderly Annexation Areas The. North Corridor study area is located within the City of St. Joseph's planned annexations into St. Joseph Township. An annexation agreement provides a timeframe for when city services would be made available to township residents. These timeframes act as a planning guide and do not necessarily represent specific dates. The City's annexation areas are divided into two phases: a zone scheduled for annexation between 2003-2007, and outlying areas planned for orderly annexation between 2008 and 2017. A majority of the annexation areas are in agricultural uses. The bulk of the area being studied for the North Corridor is planned for annexation between 2003-2007 (although this area has not yet St. Joseph North Corridor - 9 - February 2009 Scoping Document been annexed). A small portion of the North Corridor area, from CSAH 3 and the Lake Woebegon Trail and curving northeast toward the Watab River, is located in the 2008-2017 annexation zone. Since the year 2000, a total of 2.21 square miles (1,416 acres) have been annexed from St. Joseph Township to the City of St. Joseph. In year 2000, the land area of the City of St. Joseph was 1.86 square miles. The current (year 2006) land area is 4.07 square miles, an increase of 118 percent.3 2.4 PURPOSE AND NEED FOR THE PROJECT 2.4.1 Purpose of the Project The purpose of the North Corridor study is to identify a minor arterial roadway corridor that can be preserved for future roadway development in the growth area of north St. Joseph. The proposed future roadway would be part of a minor arterial network intended to improve mobility in the St. Joseph area by providing an alternative route to CSAH 75, and providing connections to other minor arterial roadways that also serve this growing area. 2.4.2 Need for the Project The St. Cloud Metropolitan Area has continued to expand to the west, and as it does, many surrounding areas like St. Joseph have also experienced population growth. St. Joseph's population has increased three-fold since 1970, and population projections indicate that its growth will continue, increasing by another 237 percent between 2000 and 2030. As population grows, the transportation needs of the area will also increase. The transportation needs for the proposed project include forecast increases in travel demand and traffic operations. In addition, the City of St. Joseph, with support from Stearns County and the St. Cloud APO, has identified a series of transportation-related goals that should be address by the proposed project. These goals include: system connectivity, future planned land uses, system spacing, and corridor preservation in support of future, planned land uses. 2.4.2.1 Forecast Increases in Travel Demand Travel demand forecasts were completed for existing conditions (year 2000), year 2030 conditions, and future conditions beyond year 2030 to evaluate the future travel demand within the north St. Joseph growth area. Year 2000 was identified as existing conditions because this is the base year currently in use as part of the St. Cloud APO's 2030 Transportation Plan.4 Year 2030 conditions represent land use and socioeconomic forecasts based on the APO's 2030 Transportation Plan. Land uses in the APO's 2030 Transportation Plan are tied to local comprehensive land use plans, as well as other factors, and distributed throughout the AFO's s City of St. Joseph Comprehensive Plan. October 2008 Draft. Chapter 2: Physical Setting and Table 2-2 (St. Joseph Annexations from 2000-Present). a The St. Cloud APO is currently in the process of completing their 2035 Transportation Plan. The base year utilized in the 2035 Plan is year 2005. Future documentation for the North Corridor project will be updated with information from the 2035 Plan as it becomes available. St. Joseph North Corridor - 10 - February 2009 Scoping Document planning area based on year 2030 demographic forecasts. Future conditions beyond year 2030 assume full build-out of the City of St. Joseph planned land uses as identified in the City's comprehensive plan, contiguous with the orderly annexation area boundaries with St. Joseph Township. The travel demand forecasts were completed using the travel demand model developed and approved by the St. Cloud Area Planning Organization (APO) for use in the St. Cloud Metropolitan Area. Land use forecasts (type of land use and measurement unit) from the APO's travel demand model were identified for existing, year 2030, and future conditions based on St. Joseph land use plans. Forecast trip generation was also identified for the north St. Joseph growth area for existing and future conditions. The results of this analysis are described below. Land Use Forecast Growth The amount of residential, commercial/retail, office, and industrial land uses was identified for the north St. Joseph growth area using data from the St. Cloud APO. Using existing land use patterns, knowledge of the planning area, and the land use comprehensive plans for participating cities, the APO projects future lands uses. for the St. Cloud Planning Area (including the City of St. Joseph) for use in their travel demand model. Land uses are organized into 10 different categories, including residential (single and multi-family), commercial/retail, office, industrial, school, park, college/university, etc. Residential uses are measured in number of dwelling units. Commercial/retail, office and industrial land uses are measured in square feet. Existing residential units and planned growth in residential units included in the St. Cloud APO travel demand model for the north St. Joseph growth area .are tabulated in Table 4. From existing conditions to year 2030, the north St. Joseph growth area is forecast to accommodate more than 400 additional residential dwelling units. Based on planned future land uses beyond year 2030, the north St. Joseph growth area is forecast to accommodate an additional 2,400 residential dwelling units compared to existing conditions. TABLE 4 NORTH ST. JOSEPH GROWTH AREA LAND USE FORECAST GROWTH Future Conditions Existing Future (Comprehensive Plan Land Uses Conditions Land Uses) Measure (Year 2000 ear 2030 (Be and Year 2030) Residential ~'~ Dwellin Units 164 574 2,636 Commercial/ Office/ Square Feet 161,000 271,000 660,000 Industrial Source: St. Cloud Area Planning Organization land use forecasts and travel demand model. (i) Includes single-family and multi-family dwelling units. Table 4 also tabulates the amount of commerciaUretail, office, and industrial land uses included in the St. Cloud APO travel demand model forecast for the north St. Joseph growth area. The amount of commercial, office, and industrial uses are forecast to increase from 161,000 square St. Joseph North Corridor -11 - February 2009 Scoping Document feet under existing conditions to 271,000 square feet under year 2030 conditions. The north St. Joseph growth area is forecast to accommodate 660,000 square feet of commercial/industrial space for conditions beyond year 2030. Trip Origin/Destination Patterns Increases in population and planned changes in land uses in the north St. Joseph growth area are forecast to result in additional vehicle trips (i.e., travel demand). Vehicle trip ends5 within the north St. Joseph growth area are tabulated for existing, year 2030, and future land use conditions beyond year 2030 in Table 5. Results of this analysis show that vehicles within the north St. Joseph growth area have trip origins and destinations that are predominately to or from points outside of the north St. Joseph growth area. TABLE 5 TRIP DISTRIBUTION FOR NORTH ST. JOSEPH GROWTH AREA Num ber and Percent of Tri Ends tll Future No-Build Future No-Build Existing Conditions Conditions Conditions (Year 2000) (Year 2030) (Be and Year 2030) tZ~ Within the north 15% (1,200) 13% (2,000) 21°l0 (10,900) St. Jose h owth area To/From Other Locations within St. Cloud APO 85% (6,900) 87% (13,400) 79% (41,500) Plannin Area TOTAL 100% 8,100 100% 15,400 100% (52,400 ~'~ Number in parentheses represents number of trip ends (beginning or ending in northeast St. Joseph growth area). (z) Full build out of City of St. Joseph, contiguous with orderly annexation boundaries; based on planned land uses identified in the City's comprehensive plan. The rate and timing for these conditions is unknown, and is determined by several factors including market forces or other factors under municipal control to varying degrees. Under existing conditions, 1,200 .vehicle trips ends are focused within the north St. Joseph growth area (i.e., internal trips originating from and destined to points within the north St. Joseph growth area). However, most of the vehicle trip ends (85 percent) in the north St. Joseph growth area are originating from or destined to other points within the St. Cloud APO planning area. Under year 2030 No-Build conditions, 2,000 vehicle trip ends are forecast to come from and are destined to points within the north St. Joseph growth area. This is approximately 800 additional vehicle trip ends (67 percent increase) originating from and destined to points within the north St. Joseph growth area compared to existing conditions. However, similar to existing conditions, most of the vehicle trips ends in the north St. Joseph growth area are forecast to originate from or are destined to other locations within the St. Cloud APO planning area under 2030 No-Build conditions. Under future conditions beyond 2030, a total of approximately 52,400 daily vehicle trip ends are forecast for the north St. Joseph growth area. Under future conditions beyond 2030, nearly one- fifth of the trip ends, or approximately 10,900 daily vehicle trip ends, are forecast to originate 5 Trips are produced by or attracted to a particular travel analysis zone, depending upon the type of trip (e.g., home/work trip). Each trip has two ends. A trip end is the beginning or end point of a particular trip. St. Joseph North Corridor -12 - February 2009 Scoping Document and are destined for points within the north St. Joseph growth area. Similar to existing and year 2030 No-Build conditions, a majority of trips ends generated by the north St. Joseph growth area are forecast to and from .other locations within the St. Cloud APO planning area under future conditions beyond year 2030. Summary of Forecast Increases in Travel Demand As population grows in the City of St. Joseph, the transportation needs of the City will also grow. Based on results from the St. Cloud APO travel demand model, the north St. Joseph growth area is forecast to experience increases in travel demand in the future. The overall number of daily vehicle trip ends that originate or are destined to the north St. Joseph growth area is forecast to nearly double by year 2030 and increase five-fold under conditions beyond year 2030. Beyond year 2030, approximately 52,400 daily vehicle trip ends are forecast to originate from or are destined to the north St. Joseph growth area. Approximately one-fifth of these are vehicle trip end are focused within the north St. Joseph growth area. 2.4.2.2. CSAH 75 Traffic Operations and Capacity CSAH 75 Functional Classification CSAH 75 is located at the southern limits of north St. Joseph growth area and bisects the City of St. Joseph. CSAH 75 extends from I-94 northwest of St. Joseph, through the St. Cloud Metropolitan Area, to the Stearns County border with Wright County. CSAH 75 is currently classified as a minor arterial roadway from I-94, through St. Joseph and St. Joseph Township, to the City of Waite Park, and is identified as a future minor arterial roadway in the 2030 Stearns County Comprehensive Plan (March 2008). The City of St. Joseph Transportation Plan (2006, revised January 2007) identifies CSAH 75 as a future principal arterial roadway. As a minor arterial roadway, CSAH 75 functions to primarily serve the mobility needs for short- to medium length trips (e.g., internal-community travel and travel between sub regions). Minor arterial roadways provide some accessibility through intersections with other principal, minor arterial and collector roadways, although mobility is typically emphasized over accessibility.6 Traffic Operations Analysis A critical lane operations analysis was performed for the p.m. peak hour at the College Avenue North (CSAH 2) intersection with CSAH 75 in St. Joseph as part of the 2006 Corridor Study. College Avenue North (CSAH 2), a minor arterial roadway, is a key route that connects the north St. Joseph growth area and beyond to CSAH 75. CSAH 75 is an east-west minor arterial roadway through St. Joseph that connects I-94 to the St. Cloud urban core. The CSAH 75/College Avenue intersection is a signalized intersection with dedicated turn lanes. A critical lane analysis is a planning-level tool that is used to determine the general capacity sufficiency of an intersection. Traffic volumes for critical movements at the studied intersection are identified and added together to obtain the sum of critical lane volumes for the intersection. The critical lane volumes are then compared to the theoretical capacity of the intersection. While capacity of a signalized intersection will vary considerably based on the cycle length, number of traffic signal phases, lane widths, grades, vehicle mix, and a number of other factors, the capacity 6 St. Cloud APO 2030 Transportation Plan. Chapter 6: Access Management. St. Joseph North Corridor - 13 - February 2009 Scoping Document of a signalized intersection is typically assumed to be 1,400 vehicles per hour (vph). Intersections with critical lane volumes less than 1,200 vph are typically considered under capacity, while intersections with critical lane volumes over 1,400 vph are considered over capacity. When an intersection has critical lane volumes between 1,200 and 1,400 vph, it is considered near capacity. The critical lane thresholds and capacity levels are summarized in Table 6. TABLE 6 CRITICAL LANE THRESHOLDS AND CAPACITY RELATIONSHIPS Si nalized Intersections Sum of Critical Lane Volumes [vphJ Relationship to Probable Ca aci 0 - 1200 Under Capacity 1201 - 1400 Near Ca acit > 1400 Over Ca acity As shown in Table 7, analyzed intersections along CSAH 75 operate under capacity under existing conditions during the p.m. peak hour. Under future (2030) No-Build conditions during the p.m. peak hour, the 2nd Avenue Northwest and College Avenue North intersections with CSAH 75 are forecast to be over capacity. This is due to increasing traffic volumes on CSAH 75, which will approach capacity under future No Build conditions (see discussion below). TABLE 7 CRITCAL LANE ANALYSIS RESULTS: EXISTING AND NO BUILD (CSAH 75 INTERSECTIONS) Existin Conditions 2005 No-Build Conditions 2030 ~l~ Sum of Critical Sum of Critical Lane Volumes Lane Volumes Intersection (critical Relationship to (critical Relationship to with CSAH 75 movements Probable Ca acit movements Probable Ca aci 450 vph 1,025 vph CSAH 3 (WB Thru/EB Left Under Capacity (WB Thru/EB Left Under Capacity and SB Left and and SB Left and Ri ht Ri ht) 775 vph 1,600 vph 2nd Ave NW (EB Thru1WB Left Under Capacity (EB Thru/WB Left Over Capacity and NB Left and and NB Left and lti ht Ri ht 900 vph 1,700 vph College Ave N (WB Thru/EB Left Under Capacity (WB Thru/EB Left Over Capacity and NB Thru/ and NB Thru/ Ri htISB Left) Right/SB Left) ~'~ Year 2030 No Build conditions critical lane analysis based on the St. Cloud APO fiscally constrained network. ~ 2nd Avenue Northwest is presently the designated truck route through St. Joseph from Interstate 94 to CSAH 75. Stearns County will be constructing a new CSAH 2 roadway between CSAH 75 and the CSAH 2/Interstate 94 interchange west of St. Joseph. This project is identified for construction in year 2009 in the Stearns County Five- Year Construction Project Plan. St. Joseph North Corridor - 14 - February 2009 Scoping Document CapacitYAnal~sis CSAH 75 Access in St. Joseph The portion of CSAH 75 within the project area is characterized by multiple at-grade roadway and driveway accesses. There are currently two traffic signals on CSAH 75 in the 1.6 miles through St. Joseph from CSAH 3 to CSAH 133. Existing at-grade access points include both full access intersections (allows all movements) and restricted access intersections (e.g., right- in/right-out only). Local roads, county roads, businesses and one residence have direct access to CSAH 75 within the project area. There are a total of 11 intersections within the 1.6 miles from CSAH 3 to CSAH 133. This equates to, on average, approximately 7 access points per mile on CSAH 75 within St. Joseph. Table 8 summarizes existing access on CSAH 75 in the study area. TABLE 8 SUMMARY OF EXISTING ACCESS ON CSAH 75 THROUGH ST. JOSEPH FROM CSAH 3 TO CSAH 133 T e of Access Full Access Ri ht-in/Ri ht-out Local Road 9 2 Business Access 2 0 Residential Access 1 0 TOTAL (2) 12 2 ~`~ Includes access to Millstream Park from CSAH 75. l2> Several access points may be located at one intersection (e.g., a local road across from a driveway). These are counted separately in the total for this table, but consolidated as one access point for the total cited in the text. CSAH 75 Average Daily Traffic (ADT) As population grows, the transportation needs of the area will also increase. Increases in,travel demand within the north St. Joseph growth area, combined with increases in travel demand throughout the City in general, will result in increases in traffic volumes within the project area. Table 9 shows existing (year 2006) and future No-Build (year 2030) traffic volumes for CSAH 75 through the St. Joseph from CSAH 3 to CSAH 133. Traffic volumes are forecast to increase by approximately 11,000-17,000 vehicles per day on CSAH 75 from existing to future (2030) No Build conditions. Aselect-link analysis under year 2030 No Build conditions indicates that approximately 30 percent of the CSAH 133 traffic east of St. Joseph are destined for CSAH 75 west of St. Joseph. TABLE 9 CSAH 75 AVERAGE DAILY TRAFFIC VOLUMES: 2006 AND 2030 N0 BUILD Year 2030 Year 2006 ~1~ No Build c2~ CSAH 75 Se ment (vehicles er da) (vehicles er da CSAH 3 to CSAH 2 16,100 33,500 CSAH 2 to CSAH 133 23,700 34,600 ~'~ Mn/DOT 2006 Traffic Flow Maps for City of St. Joseph and Steams County. (2> St. Cloud APO 2030 fiscally constrained network. St. Joseph North Corridor - I S - February 2009 Scoping Document The St. Cloud APO 2030 Transportation Plan identifies planning-level threshold volumes for various roadway cross-sections and functional classifications. Thresholds vary for individual roadway segments, depending upon access control, signal spacing and intersection operations, roadway geometrics, etc. However, these thresholds provide aplanning-level estimate for conditions when of when the average daily traffic volume on a particular roadway may approach a level that is over capacity (i.e., delays and congestion). CSAH 75 is a four-lane, divided roadway through St. Joseph. According to the St. Cloud APO 2030 Transportation Plan, the planning-level threshold capacity for afour-lane divided urban street is 35,000 vehicles per day (vpd). Based upon operations at CSAH 75 intersections, and the access information described above and in Table 8, the threshold volume for CSAH 75 through St. Joseph is likely less than the 35,000 vpd identified in the St. Cloud APO plan. The forecast traffic growth on CSAH 75 indicate that it is approaching capacity under future 2030 No Build conditions. This is consistent with the St. Cloud APO 2030 Transportation Plan, which identifies the CSAH 75 segment through St. Joseph as congested (level of service E or worse) under year 2030 conditions.g 2.4.3 Other Transportation Goals and Objectives The transportation objectives described above establish the basic transportation purpose of and need for the proposed project. The proposed project would also address other transportation objectives including: system connectivity, transportation system spacing, accommodating bicycles and pedestrians, consistency with adopted regional plans, and corridor preservation in support of future, planned land uses. These objectives are described in the following sections. 2.4.3.1 System Connectivity The City of St. Joseph was originally developed along a railroad line with a grid street system. Currently, access into the historic downtown of St. Joseph is from I-94 via CSAH 2, or from CSAH 75 or CSAH 133, all minor arterial roadways. CSAH 3 on the northwest and CR 121 south of St. Joseph are community collectors that also provide entry into St. Joseph. Despite these system components, the St. Joseph vicinity lacks a continuous network of east- west and north-south roadways. CSAH 2, a minor arterial, enters southwest St. Joseph from its connection to I-94 (which runs south and west of the city); CSAH 2 (also known as Minnesota Street) travels diagonally in a general east-west direction until College Avenue in downtown St. 3oseph, where it turns north and continues out of town. College Avenue continues south from Minnesota Street, providing a north-south roadway for travelers in southern St. Joseph (also CR 121). Minnesota Street continues east from College Avenue, connecting to CSAH 75 and providing access to St. Cloud. CSAH 3, also a minor arterial, enters St. Joseph from the northwest, and terminates at CSAH 75. CSAH 133, a community collector, comes into St. Joseph from Sartell to the northeast, travels diagonally in a generally north-south direction, forms the eastern terminus of the North Corridor project, and continues south of CSAH 75 where it becomes 7th Avenue SW/95th Avenue. Approximately one mile north of St. Joseph city limits, 320th Street/Township Road 125 provides east-west access between CSAH 2 and CSAH 133. a St. Cloud APO 2030 Transportation Plan. Chapter 5: Roadway Plan. Exhibit SF - St. Cloud Metro Area 2030 Congested Locations. St. Joseph`North Corridor - 16 - February 2009 Scoping Document Historically,. there have been no connections between the minor arterials and community collectors in St. Joseph. These roadways each act as spokes that radiate out from the downtown core, much like spokes from a hub on a wheel, except there is no connection around the perimeter to support the spokes. While the existing roadways provide access to the community, they all connect through the heart of St. Joseph. A vehicle traveling south on CSAH 133 must pass through downtown St. Joseph to reach I-94 (and vice versa); likewise, a driver traveling north on CR 121 must pass through downtown to reach CSAH 2 or CSAH 75. Almost all trips on any of the minor arterials or community collectors must travel through the center of St. Joseph to reach another minor arterial or travel in a different direction. The only east-west continuous route in St. Joseph is CSAH 75. As previously described, land use changes and development have occurred and are planned for lands within St. Joseph north of CSAH 75. As lands in the north St. Joseph growth area develop, local and regional trips are forced onto CSAH 75. Regional trips through the St. Joseph area to Interstate 94 are also forced onto CSAH 75. As such, there is a need to provide a new east-west link in the existing transportation system to connect to existing roadways and facilitate east-west movements. As St. Joseph expands from its older, historic core, there is a need to provide enhanced connections between existing transportation corridors. As noted in the Corridor Study Report, one of the goals of the North Corridor and CSAH 2 Realignment Project was to work towards developing an arterial roadway network in the City of St. Joseph that provides linkages between key corridors (e.g., I-94, CSAH 2, CSAH 3, CSAH 133) and activity centers. Therefore, studied alternatives should provide for efficient connections to these existing roadways. 2.4.3.2 System Spacing According to functional classification guidelines established by FHWA and used in the city's 2007 Transportation Plan, "[f)unctional classification is the process by which streets and highways are grouped into classes, or systems, according to the character of service they are intended to provide." Roadway. functional classification consists of principal arterials, minor arterials, collectors, and local streets. The St. Joseph Transportation Plan was completed in 2006 and revised in 2007. The 2007 plan sets a goal of providing supporting arterial roadways within the roadway network every one mile, and providing .supporting collector roadways every 0.5 miles. Minor arterial roadways are intended to connect to other arterial or collector roadways and serve moderate-length trips, as opposed to shorter-length trips characteristic of collector roadways. To further enhance the roadway network within the project area, the Corridor Study Report identified a goal of providing supporting arterial roadways every 0.5 to one mile, in order to enhance overall connectivity. The St. Cloud APO has established similar guidelines (see Table 10). As the City of St. Joseph continues to expand to the north and annex land, there will be a greater need for connections to other arterial roadways consistent with the spacing needs defined in the Corridor Study Report. St. Joseph North Corridor -17 - February 2009 Scoping Document TABLE 10 ST. CLOUD APO SYSTEM SPACING GUIDELINES: URBANIZING AREAS Functional Classification Facility T e Facilit S acin (Miles Interstate/Freewa 2 to 5 miles Principal Arterial Non-Freewa 2 to 3 miles Minor Arterial 4-lane divided or 4-lane undivided 0.7 to 1.5 mile Collector 4-lane undivided, 3-lane, or 2-lane 0.3 to 1 mile Spacing of existing facilities indicates a need for a minor arterial connection north of St. Joseph. As discussed previously, CSAH 75, located approximately 0.8 mile south of the North Corridor study area, is the only existing east-west minor arterial through St. Joseph. No continuous east- west roadway is available in the northern portion of the community. As such, future studied alternatives should be consistent with system spacing goals identified in the Corridor Study Report and St. Cloud APO system spacing guidelines. 2.4.3.3 Consistency with Regional Land Use and Transportation Plans Regional and local plans have recognized the role of a future North Corridor in serving the transportation needs of the St. Joseph area. These plans have also recognized the role of the proposed North Corridor in serving the transportation needs of the greater St. Cloud Metropolitan Area. Regional Growth Plans In 2000, the St. Cloud Area Joint Planning District Board approved the St. Cloud Area Joint Planning Project District Plan (May 18, 2000). The Joint District Plan was developed based on direction from the Community-Based Planning Act, which encourages voluntary, cooperative land use planning among governments. The St. Cloud Area Master Plan component of the Joint District Plan addressed the planned urban area and service area for the cities of Sartell, Sauk Rapids, St. Cloud, St. Joseph and Waite Park as well as the townships in the St. Joseph vicinity (St. Joseph, St. Wendel and Le Sauk Townships). It identifies land south of the North Corridor project area as a primary planned urban area, and lands north of the North Corridor project area as a secondary planned urban area. Primary planned urban areas are defined as those planned to develop with urban densities within the next 20 years. Secondary urban areas are those not expected to urbanize until beyond the 20-year time horizon, but which still need to be preserved for urban development. The location of the proposed North Corridor is in keeping with projections for the development of this area over the next two decades. The St. Cloud APO publishes ametropolitan-wide Surveillance Plan as a mechanism to monitor changes in the St. Cloud area transportation system, socioeconomic conditions, and land use. The 2007 St. Cloud Metro Area Growth Report was prepared in October 2007. According to this report, the City of St. Joseph annexed approximately 397 acres from St. Joseph Township in 2006. St. Joseph North Corridor - 18 - February 2009 Scoping Document Regional Transportation Plans An arterial facility between St. Cloud and St. Joseph is .identified in the St. Cloud APO 2030 Transportation Plan. The project is defined as a New Growth/Access project and is described as a new four-lane alignment from Rolling Ridge Road to Stearns CSAH 3, and south extension of CSAH 3 to Stearns CSAH 2. (This APO plan was adopted when the Corridor Study had not yet split the project into three separate projects and environmental review processes. Refer to Section 3.1 for additional detail of that project history). The St. Joseph North Corridor project is identified as an illustrative project in the St. Cloud APO 2030 Transportation Plan. Illustrative projects cannot be included in the St. Cloud APO's fiscally constrained plan because it is not anticipated that funds will be available for these projects within the plan's timeframe. Illustrative projects are those projects that are only eligible to compete for high priority project (HPP) funding from Congress. The APO's current (2009-2013) Transportation Improvement Program (TIP) identifies that FHWA prioritized programming has been assigned for the completion of the North Corridor's Tier I EIS (from CSAH 3 to CSAH 133, its current project limits) in Fiscal Year 2009. The St. Cloud Area Master Plan section of the St. Cloud Area Joint Planning District Plan includes a transportation component. This transportation component highlights the North Corridor study area as a general corridor requiring further study and refinement as part of a smaller sub-area corridor study. It goes on to recognize "the east/west corridors north of St. Joseph [as] an example of corridor preservation areas where growth may require additional roadway capacity." Further, it states that, "timing of roadway developments can play a great part in either assisting or inhibiting good land use planning. As identified as part of the APO's strategy, advance purchase or preservation of sufficient right of way for future roadway expansion is often the best policy for accommodating future transportation decisions" (page 6-23). Stearns County Growth Plans .The 1998 Stearns County Comprehensive Plan predicts future residential growth north, west and south of existing city limits. Commercial and industrial growth is expected east of St. Joseph city limits, creating a growing geographic connection .with Waite Park and St. Cloud. The plan identifies significant infrastructural segments where population growth has been the highest. Two of these sectors include CSAH 75, between St. Cloud and St. Joseph, and I-94 from Trunk Highway (TH) 15 to CSAH 75. The North Corridor arterial would provide the necessary infrastructure to support these growth projections. Stearns County recently completed an update of their comprehensive plan (last updated and adopted in 1998). The 2030 Stearns County Comprehensive Plan identifies several objectives and policies with which the North Corridor is compatible. These include encouraging development to take place where infrastructure exists or is planned (Objective 5.1), supporting the provision of joint services among jurisdictions (Objective 5.3), and supporting the policies of the Joint District Plan regarding regional service coordination (Metropolitan Area Policy 1). The North Corridor project area appears entirely within an area identified by Stearns County's Future (2030) Land Use Plan map as an "Urban Expansion" area. St. Joseph North Corridor - 19 - February 2009 Scoping Document Stearns County Transportation Plans Stearns County's 1998 Transportation Plan identifies a future major collector in the general North Corridor study area. Although this is no longer the functional classification intended for the North Corridor roadway, its identification in the 1998 plan indicates that this roadway has been under consideration for some time (Figure VI-15). The 1998 plan also identifies the need for a bypass around St. Joseph, generally to connect from CSAH 75 east of town to CSAH 75 west of town (Appendix A, page A-10). The 2030 Stearns County Transportation Plan (March 2008) acknowledges the environmental study currently being conducted for the North Corridor (an "east-west collector"), as well as a general corridor location north of CSAH 75. The General Transportation Policies section of the plan states that, "where future roadway corridors have been identified... Stearns County will not approve subdivisions adjacent to those corridors unless it can be demonstrated that the corridor will remain adequately protected and that access management guidelines can be met" (page 6-43). 2.4.3.3 Accommodate Bicycle/Pedestrian Facilities Stearns County Parks Department recently completed a trail feasibility study to examine opportunities to extend the Lake Wobegon Trail (a regional trail). The Lake Wobegon Trail is a regional trail that extends from the City of Sauk Centre to the eastern limits of the City of St. Joseph. An extension of the Lake Wobegon Trail would connect St. Joseph to the Mississippi River in St. Cloud. In addition to the Lake Wobegon Trail, the Stearns County Comprehensive Plan identifies CSAHs 2, 3, and 75 as existing bicycle routes in the project area, and CSAH 133 as a proposed future bicycle route. The Lake Wobegon Trail crosses the northwest portion of the North Corridor study area (around CSAH 3). The trail goes into St. Joseph parallel to CSAH 75, utilizing former railroad tracks. Studied alternatives should accommodate abicycle/pedestrian trail, provide pedestrian bicycle connections north of St. Joseph and should provide connections to the Lake Wobegon Trail. 2.4.4 Social, Economic and Environmental Considerations In addition to the transportation goals and objectives identified in Section 2.4.3, it is also necessary to consider social, economic and environmental resource impacts as part of the roadway development process. Social, economic and environmental issues have been identified for study in the EIS and are described in Section 5.0. Qualitative and quantitative measurements of social, economic and environmental impacts will be described in detail in the EIS. Methodologies used to evaluate these impacts are summarized in Section 5.0 of this document. St. Joseph North Corridor - 20 - February 2009 Scoping Document 3.0 DEVELOPMENT OF SLOPING ALTERNATIVES The NEPA and MEPA scoping process for the North Corridor project was formally initiated in December 2007 at a meeting with Corridor Study project partners and representatives from FHWA, Mn/DOT District 3, and Mn/DOT State Aid. However, all previous development of alternatives in the Corridor Study was conducted with NEPA and MEPA requirements in mind. The steps in the development of alternatives for the project are discussed below. 3.1 ALTERNATIVES DEVELOPED DURING CORRIDOR STUDY (PRE-NEPA PROCESS) As has been discussed previously, the St. Joseph North Corridor and CSAH 2 Realignment Corridor Study was undertaken by the City of St. Joseph, Stearns County, St. Joseph Township and the St. Cloud APO in an effort to define new, primary transportation corridors before areas surrounding the city are developed. The purpose of the study was to identify preferred corridor alignments that would provide safe, reliable, and efficient mobility for both motorized and non- motorized travel in and around the St. Joseph area. The Corridor Study's findings and recommendations are the basis for this Scoping Document. The partners, along with the Corridor Study's Corridor Advisory Committee (CAC), identified the following four key goals for the outcome of the Corridor Study: 1. Ensure safe and efficient mobility for the traveling public. 2. Ensure consistency with regional and local transportation plans. 3. Ensure consistency with local land use, growth, and economic development plans. 4. Document the project's readiness to advance to provide a basis for environmental documentation. As a first step in the process of developing alignment alternatives for the new roadways, the study partners and CAC developed a corridor vision and design standards. The design standards for all parts of the study area call for a minor arterial roadway with 150 feet of right of way, access spacing of 0.5 mile for signalized access and 0.25 mile for restricted access, and a separated bicycle path. The design speed for the North Corridor was identified as 45 mph. The North Corridor typical roadway section was identified as a two- to four-lane divided urban roadway (the final number of lanes will be decided based on capacity needed to serve forecast future traffic volumes). The study group used the corridor vision and design standards to develop three Corridor Study Alternatives for the North Corridor. At the time, the North Corridor Study Alternatives extended from approximately existing CSAH 2 north of St. Joseph City limits to Westwood Parkway in St. Cloud, and were referred to in the Corridor Study as Yellow Alternatives 1, 2, and 3. In general, each of these Initial Corridor Study Alternatives followed a fairly direct route between the two termini. Alternatives 1 and 2 followed a similar, .southerly route; Alternative 3 followed a more northern alignment, avoiding a wetland complex in the area; it eventually rejoined Alternatives 1 and 2 approximately 0.5 mile west of Westwood Parkway. Refer to the Corridor Study Report for additional background detail. St. Joseph North Corridor - 21 - February 2009 Scoping Document Building on the identified project needs and goals, the study partners and CAC established specific. project objectives and measurable criteria by which to "rate" all preliminary alternatives. The criteria by which the Yellow Alternatives (now the North Corridor) were evaluated included: intersection capacity analysis, ability to promote connectivity, ability to meet the 0.5 mile to one mile spacing objectives, consistency with regional and local transportation and land use plans, and anticipated effect on economic development. The study partners and CAC used the evaluation criteria to identify those alternatives that should not be carried forward for further study. 3.1.1 Corridor Study Alternatives Dismissed Based on the alternatives screening process, the study group dismissed Corridor Study Yellow Alternative 3 from further consideration because it bowed substantially to the north as compared to other Yellow alternatives, providing inefficient connectivity between existing CSAH 2 and Westwood Parkway and complicating spacing for arterials. In addition, Yellow Alternative 3 was dismissed because it was only marginally consistent with project locations shown in regional and local transportation plans. Finally, the study group determined that the northern bow of Yellow Alternative 3 created more industrial area than had been planned for at the proposed Feld site development. The alternative also provided access primarily to low-density residential areas, rather than mobility for travelers throughout St. Joseph. 3.1.2 Corridor Study Alternatives Retained Based on the alternatives screening results, the study group retained Yellow Alternatives 1 and 2, which differ based only on their location north or south of a wetland located north of the Northland Heights development. These alternatives address the project purpose and need as summarized below. Forecast Increases in Travel Demand: Approximately 15,400 daily vehicle trip ends are forecast for the north St. Joseph growth area by year 2030. Under future conditions beyond 2030, a total of approximately 52,400 daily vehicle trip ends are forecast for the north St. Joseph growth area. A majority of the daily vehicle trips ends in the north St. Joseph growth area are forecast to originate from or are destined to other locations within the St. Cloud APO planning area under future 2030 conditions and under future conditions beyond 2030. CSAH 75 is the only existing east-west, continuous, arterial route in St. Joseph. Trips originating from or destined to points within the north St. Joseph growth area would have to rely, for the most part, on CSAH 75. As described in Section 2.4.2.2, CSAH 75 is forecast to approach capacity under future (2030) No Build conditions. The .North Corridor roadway serves as a convenient link within the transportation network to serve as an alternate east- west route for the forecast increase in travel demand in the north St. Joseph growth area. CSAH 75 Operations: Analyzed CSAH 75 intersections in St. Joseph are anticipated to operate at or under capacity during the p.m. peak hour with a North Corridor roadway. Critical .lane volumes and capacity levels under future 2030 Build conditions are shown in Table 11. Because a North Corridor roadway will attract daily vehicle trip ends that would otherwise use CSAH 75, a North Corridor roadway is forecast to improve traffic operations on CSAH 75. St. Joseph North Corridor - 22 - February 2009 Scoping Document TABLE 11 CRITCAL LANE ANALYSIS RESULTS: FUTURE BUILD CONDITIONS (CSAH 75 INTERSECTIONS). Build Conditions (2030) tt) Sum of Critical Lane Volumes Relationship to Intersections with CSAH 75 .(critical movements) Probable Ca aci 1,325 vph CSAH 3 (WB Thru/EB Left and SB At Capacity Thru/NB Left 925 vph 2nd Ave NW (EB Thru/WB Left and NB Left Under Capacity and Ri ht) 1,225 vph College Ave N (WB Thru/EB Left and NB Thru/ Under Capacity Right/SB Left) ~'~ Year 2030 Build conditions critical lane analysis based on the St. Cloud APO fiscally constrained network. Preserving CSAH 75 Capacity: A North Corridor roadway will attract trips that would otherwise use CSAH 75, reducing future traffic volumes on CSAH 75 and helping to preserve its function as an east-west minor arterial roadway in St. Joseph. Forecast traffic volume results for CSAH 75 and North Corridor are tabulated in Tablel2. Future (2030) No Build traffic volumes on CSAH 75 through St. Joseph (St. Cloud APO's fiscally constrained network) are forecast to range from 33,500 vpd to 34,600 vpd. The future .(2030) traffic volumes on CSAH 75 with a North Corridor roadway are expected to decrease by approximately 5,400 vpd to 8,300 vpd. A select-link analysis on CSAH 75 west 13 percent of CSAH 75 traffic would use t represents nearly 40 percent of the CSAH 75 destined to CSAH 133 in northeast St. Joseph. of St. Joseph illustrates that approximately he North Corridor roadway. Moreover, this traffic west of CSAH 75 originating from or TABLE 12 TRAFFIC VOLUME FORECASTS: CSAH 75 AND NORTH CORRIDOR Forecast (2030) ADT Forecast (2030) ADT Difference No Build Conditions No Build Conditions (No Build-Build) (vehicles er da ) cl) (vehicles er da t2) (vehicles er da CSAH 75 33,500. 25,200 8,300 CSAH 3 to 2nd Ave NW CSAH 75 600 34 29,200 5,400 (2nd Ave NW to CSAH 133) , North Corridor N/A 15,300 N/A (CSAH3 to CSAH 2) North Corridor N/A 13,400 N/A (CSAH 2 to CSAH 133) ~'~ Year 2030 No Build forecast volumes based on the St. Cloud APO fiscally constrained network. (2> Year 2030 Build forecast volumes based on the St. Cloud APO illustrative network. St. Joseph North Corridor - 23 - February 2009 Scoping Document Traffic volume forecasts: Traffic volume forecasts were prepared for CSAH 75 and a North Corridor roadway using the St. Cloud APO's travel demand model. These forecasts were prepared using the St. Cloud APO's illustrative roadway network for year 2030 conditions and conditions beyond year 2030. A North Corridor arterial link is forecast to serve approximately 13,400 to 15,300 vehicles per day under future (2030) Build conditions (see Table 9). Under future Build conditions beyond year 2030, the North Corridor roadway is forecast to serve approximately 31,000 to 36,000 vehicles per day. In addition to addressing the transportation purpose and need, the studied alternatives are also consistent with the other transportation goals and objectives. System Connectivity: These alternatives support the regional transportation network and provide connections between CSAH 75, CSAH 2 and CSAH 133. • System Spacing: These alternatives are consistent with the arterial spacing plan for the urban growth area of north St. Joseph. System Plan Consistency: Location and orientation of these alternatives is consistent with regional and local transportation plans and is consistent with future land use and growth plans, providing access to existing and planned residential, commercial, and industrial areas. 3.1.3 Corridor Study Organization The Corridor Study team originally understood that one EA/EAW would be suitable documentation for the proposed improvements throughout the entire study area, which at that time, included the proposed realignment of CSAH 2 around the northwest portion of St. Joseph, north to CSAH 75, north and east to existing CSAH 2 north of St. Joseph, east to Westwood Parkway. However, as the study progressed, as forecast traffic volumes were formalized, and as roadway capacity needs were identified, it became clear that one EA/EAW would not be appropriate environmental documentation for improvements throughout the entire study area. Based on this unanticipated situation, the Corridor Study team felt it needed to identify the appropriate environmental documentation approach, before Preferred Alternatives could be identified. Through the study process it also became clear that the study partners intended to complete parts of the overall project independent of one another. Stearns County had programmed the CSAH 2 South Realignment project in its Capital Improvement Program (CIP) using county and state aid funds allocated in 2008 for right of way acquisition and in 2009 for roadway construction. The City of St. Joseph had recently negotiated development of the Feld farm north of CSAH 75 and east of CSAH 133, which would include part of the eastern portion of the North Corridor (part of the roadway extending from CSAH 133 to Westwood Parkway). Neither agency, however, had a timeline in mind for construction of CSAH 2 North (approximately CSAH 75 to existing CSAH 2) or the western end of the North Corridor (existing CSAH 2 to CSAH 133), and, instead hoped to officially map the corridor to protect the future right of way from encroaching development. St. Joseph North Corridor - 24 - February 2009 Scoping Document Working closely with officials from FHWA and Mn/DOT, the Corridor Study team reconsidered. the number of highway projects included in the original North Corridor and CSAH 2 Realignment study area. FHWA regulations (23 CRF 771.111(f)) state the following in regard to identifying a highway project: In order to ensure meaningful evaluation of alternatives and to avoid commitments to transportation improvements before they are fully evaluated, the action evaluated in each EIS or finding of no significant impact (FONSI) shall: 1. Connect logical termini and be of sufficient length to address environmental matters on a broad scope; 2. Have independent utility or independent significance, i.e., be useable and be a reasonable expenditure even if no additional transportation improvements in the area are made; and 3. Not restrict consideration of alternatives for other reasonably foreseeable transportation improvements. Based on these guidelines, the study partners, with direction from FHWA and Mn/DOT officials, concluded that the original study area consisted of three independent projects for which different environmental documentation should be prepared. The three independent projects were the following: Stearns CSAH 2 South Realignment • Line Color on Corridor Study Map: Blue. • Termini: I-94 to CSAH 3 near the Lake Wobegon Trail. • Environmental Documentation: state-level EAW • Preferred Alternative: Blue Alternative 4. • Project Status: EAW was published in September 2007; construction is anticipated to begin in 2009. CSAH 2 North/North Corridor-West • Line Color on Corridor Study Map: Green and Yellow. • Termini: CSAH 3 near the Lake Wobegon Trail to CSAH 133. • Refer to additional project detail below. City of St. Joseph North Corridor-East: • Line Color on Corridor Study Map: Yellow. • Termini: CSAH 133 to Westwood Parkway/Rolling Ridge Road • Environmental Documentation: combined federal-level EA and state-level EAW. St..Ioseph North Corridor - 25 - February 2009 Scoping Document Preferred Alternative: the alignments for Yellow 1 and 2 are the same in this portion of the study area. The study partners recommend combined Yellow l -2 as the Preferred Alternative in this area. • Project Status: EA/EAW is currently under development (publication anticipated. in 2009). North Corridor-East is not programmed for construction and is identified as an illustrative project in the St. Cloud APO 2030 Transportation Plan. The North Corridor project that is under study in this SD is a result of the discussions and decisions described above and was referred to as the "CSAH 2 North/North Corridor-West" project at the end of the Corridor Study process. 3.1.4 North Corridor Identification in Corridor Study Once identified as a separate project at the conclusion of the Corridor Study, discussions turned to how the North Corridor project met the logical termini and independent utility/independent significance criteria specified by the FHWA regulations. This section describes those conclusions. 3.1.4.1 Logical Termini The North Corridor project would connect logical termini, extending from the CSAH 2 South Realignment (northern terminus is existing CSAH 3 near the Lake Wobegon Trail) to CSAH 133. These are logical termini points for the project because they key arterial roadways in the St. Cloud APO's future regional transportation network. The distance of 2.5 miles would be of sufficient length to address environmental matters on a broad scope, requiring an EIS. 3.1.4.2 Independent Utility or Independent Significance The North Corridor project has independent utility/significance in three ways. First, it is necessary to complete environmental documentation for the North Corridor project in order to prepare an official map that documents and protects the roadway right of way from encroaching development, which is currently occurring 60_feet south of Alternative 1 (the southern alignment prepared for this project). Development has not yet been proposed to the north, but that area is included in the six- to 10-year development scenario in the St. Joseph Orderly Annexation Plan (2002). Second, the North Corridor project is independent from the other transportation projects included in the Corridor Study because, unlike the CSAH 2 South Realignment project, there are no funds currently programmed for it in the Stearns County or City of St. Joseph CIPs. Finally, the North Corridor project would, by itself, provide relief for CSAH 75 by allowing traffic to bypass the CSAH 75 segment through St. Joseph. Future (2030) traffic projections for the area indicate that such a new four-lane divided arterial would support high traffic levels (the APO's illustrative network forecasts 13,400 to 17,600 vehicles per day on the proposed North Corridor roadways, diverting approximately 5,000 to 8,000 vehicles per day from CSAH 75), and enable efficient and safe travel that would support existing CSAH 75. The North Corridor project can be constructed without any other projects, can function independently, and can achieve its project goals independent of the CSAH 2 South Realignment or North Corridor-East projects. St. Joseph North Corridor - 26 - February 2009 Scoping Document Based on the logical termini-independent utility/significance discussion and the possible environmental documentation options available, the study partners considered results from the screening and technical evaluation processes and input from agencies, the public, the Corridor Advisory Committee, St. Joseph City Council, and Stearns County Board and concluded that the termini for what had now become the North Corridor project were CSAH 3 near the Lake Wobegon Trail (on the west) and CSAH 133 (on the east). It was determined that afederal- and state-level EIS was the appropriate environmental documentation (and that a Preferred Alternative would be identified as a result of the anticipated EIS process). 3.1.5 Final Corridor Study Alternatives A description of the final alternatives for the North Corridor that were developed in the Corridor Study follows. 3.1.5.1 Yellow Alternative 1 Yellow Alternative 1 begins where the proposed CSAH 2 Realignment project terminates between CSAH 75 and the Lake Wobegon Trail, just outside the northwestern city limits of St. Joseph. Yellow Alternative I begins to curve east just past the Lake Wobegon Trail. It continues in a nearly due east direction until its termination at CSAH 133. 3.1.5.2 Yellow Alternative 2 Like Yellow Alternative 1, Yellow Alternative 2 begins where the proposed CSAH 2 Realignment project terminates, just outside the northwestern city limits of St. Joseph. Yellow Alternative 2 follows largely the same route as Yellow Alternative 1; however, approximately 0.1 mile east of its intersection with existing CSAH 2, it splits to the north of Yellow Alternative 1. It rejoins the alignment of Yellow Alternative 1 approximately 0.1 mile west of its termination at CSAH 133. Yellow Alternative 2 follows this alignment in order to minimize impacts to a wetland complex in the area. 3.1.6 Tiered EIS Decision Subsequent discussions between FHWA and study partners resulted in the decision to proceed with a Tiered EIS for the North Corridor project. This decision recognized the gap in time anticipated to occur between identification of a Preferred Corridor Alternative for official mapping and right of way acquisition and project construction. This approach was determined to best meet the project goals, purpose, needs, and objectives. The study partners also largely agreed that the Final Corridor Study Alternatives identified above had the fewest anticipated impacts on the study area. The Corridor Advisory Committee (CAC) unanimously supported the findings of the Corridor Study (see Section 6.0). St. Joseph North Corridor - 27 - February 2009 Scoping Document 3.2 POST-CORRIDOR STUDY ALTERNATIVE CHANGES Focus group and public meetings were held for the Corridor Study Report in July 2006. Public input at the time indicated that a third alternative should be added to the North Corridor alternatives for further study, in order to minimize property impacts by following property lines more closely north of Yellow Alternative 2 That alternative, identified as Alternative 3, is discussed in additional detail below. 3.3 DESCRIPTION OF SLOPING ALTERNATIVES 3.3.1 No-Build Alternative Under the No-Build Alternative, no improvements other than routine roadway maintenance to existing roadways within the project area would be implemented. The No-Build Alternative does not meet the transportation needs of the project as described below. The No-Build Alternative will be carried forward into the Tier I DEIS as per NEPA and MEPA procedures as a baseline comparison for the other Tier I DEIS alternatives. 3.3.2 Build Alternatives All three Build Alternatives start at the same point, where the proposed CSAH 2 Realignment project terminates between CSAH 75 and the Lake Wobegon Trail, just outside the northwestern city limits of St. Joseph (see Figure 2). From CSAH 3, all Alternatives travel in an easterly direction for approximately two miles until their easterly terminus at CSAH 133. These alternatives are consistent with the purpose and need for the project and other project objectives as described in Section 3.1.2. 3.3.2.1 Alternative 1 Alternative 1 (Alternative Yellow 1 in the Corridor Study) begins to curve east just past the Lake Wobegon Trail. It continues in a nearly due east direction until its termination at CSAH 133. 3.3.2.2 Alternative 2 Alternative 2 (Alternative Yellow 2 in the Corridor Study) follows the same route as Alternative 1; however, approximately 0.1 mile east of its intersection with existing CSAH 2, it splits to the north of Alternative 1. It rejoins the alignment of Alternative 1 approximately 0.1 mile west of its termination at CSAH 133. Alternative 2 follows this alignment in order to minimize impacts to a wetland complex in the area. 3.3.2.3 Alternative 3 Alternative 3 was created in order to minimize severing properties in response to public feedback after the Corridor Study. It follows a more northerly route than Alternatives 1 and 2. Its alignment is approximately 1000 feet north of Alternative 1 for most of its length. It joins Alternative 2 at that alternative's northern-most point, approximately 0.25 mile east of existing CSAH 2. St. Joseph North Corridor - 28 - February 2009 Scoping Document 3.4 BUILD ALTERNATIVES FOR STUDY IN EIS 3.4.1 Build Alternative Alignments Based on the evaluation described in Section 3.3.3, all three scoping alignments (Alternative 1, Alternative 2, and Alternative 3) are recommended for evaluation in the Tier 1 EIS. The Tier 1 EIS Build Alternative alignments are illustrated in Figure 4. 3.4.2 Build Alternative Typical Section The Corridor Study Report describes a corridor vision and design standards for the proposed North Corridor alternatives. This corridor vision was developed by the study partners and Corridor Advisory Committee. Elements of the corridor vision and design standards are summarized in Table 13. TABLE 13 CORRIDOR VISION AND DESIGN STANDARDS St. Joseph North Corridor (Approx. Lake Wobegon Trail to CSAH I33) Functional Classification Minor Arterial Desi n S eed 45-55 m h T ical Roadwa Section 4 lane divided urban Pedestrian and Bic cle Trails Se arate bic cle ath Access Spacing Guidelines %z mile for signals mile restricted access Ri ht-of-Wa 150 feet The design standards identified in Table 13 will be applied to all Build Alternatives during Tier I EIS engineering studies and evaluation of social, economic, and environmental (SEE) impacts. 4.0 COST AND FUNDING SOURCE Planning-level cost estimates have been prepared for the North Corridor project for purposes of this SD. These cost estimates were prepared using the St. Cloud APO planning estimate of construction costs of $2 million per mile and $1 million per mile for right of way acquisition. Engineering and construction administration cost estimates were assumed to be 20 percent of the project cost. The proposed project costs are estimated at approximately $8.2 million to $8.5 million (2005 dollars). The Tier I DEIS will include more detailed cost estimates for the Build Alternatives based on preliminary design. Total project cost (construction, right of way, engineering) for the North Corridor Project was estimated for future year of construction. This estimate was based on planning-level project cost St. Joseph North Corridor - 29 - February 2009 Scoping Document estimates developed as part of the St. Cloud APO 2030 Financial Plan Amendment. An inflation factor of 2.05 was assumed when estimating future costs. Total project cost for construction beyond year 2030 is estimated at $16.9 million to $17.3 million (2030 dollars). As previously described, funding for the North Corridor project has not been identified. Future funding for the project is anticipated from a combination of federal, state, and local funds. The specific contribution amounts from each of these three funding sources has not been identified. The St. Cloud APO 2030 Transportation Plan identifies the North Corridor as an "illustrative project." Illustrative projects cannot be included in the St. Cloud APO's fiscally constrained plan because it is anticipated that funds will not be available for these projects within the plan's timeframe based on projected revenue streams. Illustrative projects are only eligible to complete for high priority project (HPP) funding from the United States Congress. 5.0 SOCIAL, ECONOMIC AND ENVIRONMENTAL ISSUES 5.1 ISSUES IDENTIFICATION PROCESS A comprehensive review of a wide range of social, economic, and environmental (SEE) issues is required by federal and state legislation as part of the environmental review process. A detailed analysis of SEE impacts is not required for scoping; however a preliminary assessment has been made to identify the types of SEE impacts that will be discussed in the Tier I DEIS. Identification of SEE issues during the Corridor Study and scoping process utilized a number of information sources including agency correspondence, compilation of mapped data, and input from project stakeholders. Local governments and public resource regulatory agencies were given opportunities to provide input on potential issues during the Corridor Study that was conducted as a part of this project, as well ~as through early project correspondence, public meetings, Project Management Team (PMT) meetings for the scoping process, and individual agency contacts. The general public was given the opportunity to identify potential social, economic and environmental impacts related to the project during public meetings held as part of the Corridor Study. The following sections discuss the level of study proposed for Tier I EIS analysis of issues and the rationale for each issue, based on information compiled during scoping. The overall Tier I EIS analysis is intended to provide sufficient information on relative potential impacts of the proposed alternatives to make a Preferred Corridor Alternative decision; identify the approximate right of way limits that should be preserved for the Preferred Corridor Alternative; and to identify impacts that need to be addressed in the Tier II EIS process, as well as methodology for addressing those impacts. The Tier I DEIS will provide analysis of the potential social, economic, and environmental impacts of all Corridor Alternatives, and the Tier I FEIS will provide more detailed analysis of the impacts associated with the alignment identified as the Preferred Corridor Alternative following the DEIS comment period. A Tier II EIS process, including a Tier II DEIS and Tier II FEIS, will be initiated in the future, as the project moves forward for implementation. The Tier II process will focus on Preferred Corridor Alternative design details (i.e., a layout with cross sections, bridge locations and type, stormwater ponds, and so on), an updated assessment of environmental impacts, and identification of mitigation. St. Joseph North Corridor - 30 - February 2009 Scoping Document Because the Tier I FEIS will generally focus on analyzing specific potential impacts once a Preferred Corridor Alternative has been identified, the below discussion focuses primarily on the analysis to be conducted as part of the Tier I DEIS. 5.2 ISSUES TO BE ADDRESSED iN TIERED EIS The following areas of potential concern will be studied in detail in the Tier I DEIS, including preparation of a special study (separate report) for each issue. The rationale for providing a special study for each issue is provided. • Cultural Resources This is identified as an issue requiring special study because of the expertise required to identify and evaluate potential impacts to cultural resources in the project area. • Traffic Operations Forecasting traffic operations in the project area is critical to understanding how the transportation network may function over the next 20 years-with or without the construction of the North Corridor. This analysis would build upon the information used in identifying the project need. The following issues are of major concern for the project at the Tier I level, since impacts related to these issues could have a substantial influence on selection of the Preferred Corridor Alternative. The Tier I DEIS will provide detailed analysis of impact for each of these environmental concerns, but no separate report. Rationale for assigning these issues to this category is provided below. Issues of major concern tend to be location-dependent, and the difference in alternatives' impacts to each issue may be critical to identifying a Preferred Corridor Alternative. The issues included in this category are by no means the only issues that may be considered of "major" concern to various project stakeholders. Rather, their inclusion in this category refers to the possibility that potential relative impacts of the alternatives may help to identify a Preferred Corridor Alternative, based on their physical location. In other words, for these "locational" issues, any impacts to these resources would depend on the location of the Preferred Corridor Alternative. It is therefore desirable to identify the Preferred Corridor Alternative least likely to negatively impact those resources. It should be noted that, given the proximity of the Corridor Alternatives to each other, the assignment of issues to the "major concern" category may seem somewhat arbitrary. However, EQB scoping directions require evaluation of social, economic, and environmental issues by these categories; the following assignments were determined by the PMT to appropriate for considering the potential impacts of the Corridor Alternatives objectively. • Public Park, Recreational, Wildlife Management and Section 4(f)/6(f) Lands • Vegetation/ Cover Types/ Areas of Biodiversity • Fish and Wildlife • Threatened and Endangered Species St. Joseph North Corridor - 31 - February 2009 Scoping Document • Wetlands • Floodplains/ Water Body Modification • Surface Water/ Water Quantity and Quality Management • Land Use • Farmlands • Right of Way Acquisition and Relocation • Environmental Justice/Social and Neighborhood Impacts/Community Facilities Impacts • Hazardous Materials, Contaminated Properties • Cumulative Impacts The following issues are of moderate concern for the project at the Tier I level. While some of the issues may be of substantial concern for the construction of the project and will be so addressed in the Tier II analysis, major substantive differences among alternatives that would affect the decision regarding a Tier I Preferred Corridor Alternative (location) are not anticipated. Issues of moderate concern are those whose impacts are not expected to vary greatly between Corridor Study Alternatives, and therefore are not anticipated to play as substantial a role in the identification of a Preferred Corridor Alternative. The distinction between "issues of major concern" and "issues of moderate concern" is not always clear in a project like the North Corridor, in which the alternatives under study are physically rather close to each other. As a general rule, those placed in the "issues of moderate concern" category are typically expected to be impacted more by the nature of the proposed project (e.g., number of lanes, general length of roadway) than by the precise location of the project alignment. The Tier I DEIS will identify qualitative impacts, including analysis in accordance with federal and state requirements where appropriate, for each of these areas of environmental concern. • Traffic Noise • Air Quality • Intermodal Transportation (includes Bicycle/Pedestrian Movement and Handicapped Accessibility, Truck Traffic, Rail, Transit) • Construction Impacts • Erosion Control and Slope Stability • Economic Impacts • Excess Materials • Groundwater, Geology and Soils • Utility Locations • Visual ImpactslQuality • Indirect Impacts • Irreversible and Irretrievable Commitment of Resources • Relationship of Local Short-Term Uses versus Long-Term Productivity St. Joseph North Corridor - 32 - February 2009 Scoping Document The following areas of environmental concern are not relevant to this study area and will not be discussed in the EIS: • Coastal Zones: There are no coastal zones in the project area. Wild and Scenic Rivers: There are no Wild and Scenic Rivers within the project area. • Critical Areas: There are no designated critical areas in the project area. 5.2.1 Issues Requiring Separate Study These issues will require technical analysis and/or fieldwork to assess potential impacts. The results will be compiled in a "Special Study" technical document. The findings of the studies as they relate to impacts of the proposed alternatives will be summarized in the Tier I DEIS. 5.2.1.1 Cultural Resources The project will require review under Section 106 of the National Historic Preservation Act (I6 USC 470 et seq.) and its implementing regulations (36 CFR Part 800). It is anticipated that the EIS will also serve as the required documentation for the Section 106 review as well as the NEPA and MEPA review. A preliminary request was made to the Mn/DOT Cultural Resources Unit (CRU) in 2005, for review of known historic and archaeological resources within the study area. According to this review, there are no known historic structures in the project area; however, it is likely that a Phase I identification survey will be required. While portions of the area are documented as having moderate archaeological constraints (meaning they have moderate potential for containing archaeological sites), much of the area is rated as having "unknown" potential archaeological constraints. Research for the CRU assessment relied on background research using site and survey files from the Mn/DOT CRU and the Minnesota Archaeological Predictive Model (Mn/Model). The Tier I DEIS will require identification of cultural resources properties in the study area. The cultural resources study will establish an "area of potential effect" (APE) for each alternative; conduct Phase I and Phase II investigations as needed to evaluate historic structures and potential archaeology sites; and identify the anticipated impacts (if any) of alternatives on identified sites. If impacts are anticipated, documentation assessing issues relevant to Section 4(f) will be compiled. The Tier II analysis (near time of project construction) will include conducting additional research to identify impacts of the Preferred Alternative and preparation of Section 4(f) documentation, if needed, including mitigation strategies. Consultation with SHPO, representatives of Native American tribes, as appropriate, will occur during both the Tier I and Tier II environmental processes. Refer to Section 5.2.2.1 below for more detailed discussion of addressing potential Section 4(f) impacts. St. Joseph North Corridor - 33 - February 2009 Scoping Document 5.2.1.2 Traffic Operations Traffic demand forecasts for year 2030 average daily traffic (ADT) were completed as part of the Corridor Study, in consultation with the St. Cloud APO. The forecast ADT for the North Corridor, based on the St. Cloud APO's illustrative network, varies from approximately 15,400 vehicles per day between CSAH 3 and CSAH 2, to approximately 13,300 vehicles per day between CSAH 2 and CSAH 133. In addition to studying traffic demand forecasts, the Corridor Study team evaluated intersection capacity using critical lane analysis. This analysis involved the development of peak hour turn movement forecasts. Existing peak hour turn movement volumes were collected at three intersections along CSAH 75. CSAH 3, 2nd Avenue NW (the truck route), and College Avenue (CSAH 2). Based on the counted volumes, the Corridor Study team identified turn movement proportions that were then applied to the forecast ADTs to produce 2030 peak hour turn movement forecasts at the three counted intersections. For new intersections (e.g., CSAH 21North Corridor) or intersections that change substantially, the Corridor Study team used the existing turn movement proportions as a basis to estimate turn proportions at the new/modified intersections and develop turn movement forecasts. New traffic demand forecasts for 2030 will be completed for the Tier I DEIS. Reevaluation of forecasts is necessary in order to focus modeling on the proposed North Corridor system, to reflect specific EIS alternative alignments and system connections and estimated lane requirements for Build Alternatives to provide acceptable level of operation. The Tier I DEIS will assess the future Level of Service (LOS) of the No-Build and Build Alternatives based on lane volume-to-capacity (or v/c) analysis, as well as intersection operations analysis. The Tier II analysis (near time of project construction) will verify the additional detail on geometric requirements to provide acceptable operations .for the Preferred Alternative using detailed traffic operations analysis. Other traffic-related issues to be addressed include potential roadway jurisdiction changes that may result from any of the proposed alternatives and consistency with access spacing goals (see Table 13). These issues will be discussed in relative terms in the Tier I DEIS to compare alternatives, with additional detail on impacts and issues provided, as needed to inform final design decisions, in the Tier II analysis. 5.2.2 Issues of Major Concern Requiring Detailed Analysis These issues were identified by project stakeholders during the Corridor Study and scoping as issues of potential major concern that could have a strong influence on which alternative is selected as the Tier I FEIS Preferred Corridor Alternative. The Tier I DEIS will analyze these issues with respect to relative potential impacts of proposed alternatives, to provide sufficient information to assist in making a Preferred Corridor Alternative decision. St. Joseph North Corridor - 34 - February 2009 Scoping Document 5.2.2.1 Public Park, Recreational, Wildlife Management and Section 4(f)/6(f) .Lands The Lake Wobegon Regional Trail is a 50-mile trail that runs from St. Joseph to Sauk Centre (within the project area; refer to attached figures). Stearns County completed a feasibility study in spring 2007 to examine the potential to extend the trail from St. Joseph to the Mississippi River in Waite Park and St. Cloud. The Transportation chapter of the Stearns County 2030 Comprehensive Plan identifies CSAH 75, CSAH 2 and CSAH 3 as existing bikeway routes (i.e., they meet four-foot minimum shoulder requirements); it also identifies a proposed bicycle route along CSAH 133. The North Corridor would likely have impacts to these existing and planned facilities. The College of Saint Benedict owns a .private Scientific and Natural Area (SNA) east of CSAH 3 within the study area. This area is adjacent to the proposed Build Alternatives. The area is not recognized by the Minnesota Department of Natural Resources (MnDNR) as a state SNA. If the area were open to the public, federal (Section 4(f)) regulations could be triggered if the area was impacted by one or more Build Alternatives. Based on current information, it does not appear that these requirements apply. Millstream Park, acity-owned park, is located outside of, but within proximity to, the study area (between the Lake Wobegon Trail and CSAH 75, at the southern reach of the Watab River). The CSAH 2 realignment project provides a new entry to this park. The park would not be impacted by the North Corridor project. Development of the scoping alternatives included avoidance and minimization of impacts on recreational, wildlife and other potential Section 4(f) properties in the project area. However, given the location of the Lake Wobegon Trail through the project area, impacts to it will likely be unavoidable. Development and evaluation of alternatives will be performed consistent with the requirements of federal Section 4(f), as applicable, regarding impacts to this and any other applicable public park, recreational, or wildlife properties. The Tier I DEIS will document the alternatives development and evaluation process, including avoidance and minimization efforts and potential mitigation measures, consistent with Section 4(f) documentation requirements. The project has been reviewed for potential 6(f) involvement. The project will not cause the conversion of any land acquired, planned or developed with funds from the Land and Water Conservation Fund (LAWCON). No Section 6(fj involvement exists on this project. The Tier II analysis (near time of project construction) will include more detailed discussion of the impacts of the Preferred Alternative, based on Tier I findings, and if applicable, a Section 4(fj Evaluation of the Preferred Alternative. 5.2.2.2 Vegetation, Cover and Areas of Biodiversity The primary types of vegetative cover within the study area include cultivated and pastured farm fields, woodlands and forested areas, brushland and grasslands, as well as wetland vegetation. Portions of the study area, particularly the central piece of the North Corridor, have been disturbed by urban suburban development, and agricultural land uses are found throughout the study area. As noted, the College of St. Benedict owns a SNA to the east of CSAH 3 within the St. Joseph North Corridor - 33 - February 2009 scoping Document project area (but outside of any of the proposed Build Alternatives). This SNA is primarily wooded. This site is identified by the DNR as a site of "moderate" biodiversity.9 Based on information from the Minnesota County Biological Survey, there are no natural plant communities within the project area.10 This will be confirmed through coordination with the DNR during Tier I DEIS studies. Information regarding anticipated impacts of project alternatives on important vegetation biological communities will be provided in the Tier I DEIS. Additional discussion of impacts and mitigation for the Preferred Alternative will be included in the Tier II environmental analysis. 5.2.2.3 Fish and Wildlife Information on fish and wildlife resources in this SD is based on input from the U.S. Fish and Wildlife Service (USFWS), MnDNR and Mn/DOT Office of Environmental Services (OES). Land within the study area provides habitat for a variety of wildlife species. Natural habitats within the study area include, but are not limited to, the South Fork of the Watab River, remnant forests-particularly woodlands to the west of St. Joseph, and wetlands. The Watab River provides habitat for a variety of aquatic species, including two mussel species of special concern, the Creek Heelsplitter and Black Sandshell. The project could remove some kinds of habitat and displace wildlife in some areas. The Tier I DEIS will compare the impact of project alternatives on fish and wildlife habitat. The Tier II EIS will identify the Preferred Alternative's potential impacts on fish and wildlife and mitigation for those identified impacts. 5.2.2.4 Threatened and Endangered Species Early coordination with the MnDNR Natural Heritage and Nongame Research program indicates there are no species present within one mile of the study area that are listed as threatened or endangered under the Minnesota Endangered Species Act. According to the USFWS' Federally-Listed Threatened, Endangered, Proposed, and Candidate Species County Distribution List for the State of Minnesota (September 2007 version), there are no federally-listed threatened, endangered, proposed, or candidate species or critical habitat within Stearns County. The Tier I DEIS will conduct an updated Natural Heritage review, due to the time lapse since the last request. Analysis within the Tier I DEIS will also compare the list of any identified species to impacted habitat types and coordinate .with MnDNR and U5FWS to assess the impact of proposed North Corridor alternatives on identified species. The Tier II analysis will assess the y Sites of moderate biodiversity are defined as sites containing occurrences of rare species and/or moderately disturbed native plant communities, and/or landscapes that have a strong potential for recovery. Minnesota County Biological Survey, Division of Ecological Services, Minnesota Department of Natural Resources. 2008. The Minnesota Department of Natural Resources Web Site (online). Metadata: MCBS Sites of Biodiversity Significance accessed 02-04-2009 at httpaldeli.dnr.state.mn.us/metadatalmcbs_sbspy3.htm1#metainfo. 10 Minnesota County Biological Survey, Division of Ecological Services, Minnesota Department of Natural Resources. 2009. The Minnesota Department of Natural Resources Web Site (online). Native Plant Communities and Rare Species of Stearns County, Minnesota accessed 02-04-2009 at http://www.dnr.state.mn.us/eco/mcbs/maps.html#maps St. Joseph North Corridor - 36 - February 2009 Scoping Document Preferred Alternative's potential impacts on any identified species and identify mitigation, in coordination with the MnDNR and the USFWS, as these relate to more detailed alternative alignments. 5.2.2.5 Wetlands Potential wetland impacts related to the proposed project are regulated by federal (Clean Water Act) and state (Wetland Conservation Act) wetland protection laws. Current wetland regulations require sequencing: avoidance of, minimization of, and compensation for impacts resulting from a proposed project. Federal and state wetland regulatory agencies have been identified as cooperating and participating agencies (see Section 6.1). These agencies will provide input on the proposed project, wetland identification and wetland impacts throughout the EIS process. Evaluation of wetlands within the study area during the Corridor Study included identification of wetland boundaries within each of the alternative corridors. Wetland locations and extent were determined following the criteria set forth in the Corps of Engineers Wetlands Delineation Manual (1987). The determination included field review of the boundaries of all wetlands within the alternative corridors, but did not involve a formal delineation. Identified wetlands were classified according to Wetland Plants and Plant Communities of Minnesota & Wisconsin - Second Edition (USCOE Publication; Eggers and Reed, 1997) and Wetlands of the United States (USFWS Circular 39, Shaw and Fredine, 1971). The Corridor Study's evaluation of wetlands within the study area also included further review of soils data (NCSS Web Soil Survey of Stearns County and the Hydric Soils List for Stearns County), National Wetland Inventory (NWI) mapping, USGS 7.5-minute quadrangle mapping, as well as recent aerial photography. Several wetlands are located throughout the North Corridor study area (see Figure 2}. There are no public ditches located in the project area. An updated site visit will occur during the Tier I DEIS phase in order to ensure that field conditions have not changed dramatically since the last review. The Tier I DEIS will provide a preliminary estimate of wetland impacts of each of the proposed alternatives. Initial avoidance and minimization efforts for the alternatives will also be discussed in the Tier I DEIS. The Tier II environmental analysis will include formal wetland delineation and will provide more detailed study of potential wetland impacts of the Preferred Alternative. The current version of the Minnesota Routine Assessment Methodology for Evaluating Wetland Functions (MnRAM) will be used to develop representative analyses or to assess specific wetlands that are believed to provide a high level of function in one or more areas. In addition, a summary of the wetland avoidance, minimization, impacts (including area and types of wetlands impacted), and details of the proposed mitigation will also be provided in the Tier II analysis and subsequent wetland permitting process. The Corridor Study, scoping process, and .associated agency meetings included early coordination with federal and state wetland regulatory agencies to review and discuss project purpose and need, alternatives development (including avoidance and minimization efforts) and discussion of future permit review requirements. This coordination and request for input on the proposed action will continue throughout the EIS process. St. Joseph North Corridor - 37 - February 2009 Scoping Document 5.2.2.6 Floodplains/ Water Body Modification Construction of any of the Build Alternatives would not involve crossing any floodplain. If any potential floodplain impacts are identified, the Tier I analysis will consider the relative potential for floodplain encroachment and relative potential for hydraulic impacts among the Build Alternatives. Hydraulic issues that may affect design or maintenance will also be discussed. The Tier I DEIS will also discuss floodplain and floodway protection requirements and potential mitigation. Potential impacts on the South Fork of the Watab River will be addressed through the examination of impacts on surface water quality and quantity, and wetlands. Any potential impacts to these water bodies and initial avoidance and minimization efforts will be discussed in the Tier I DEIS. The Tier II environmental analysis will address efforts to avoid, minimize, and compensate for the Preferred Alternative's identified impacts. 5.2.2.7 Surface Water Quantity and Water Quality Management Water resources within and in the vicinity of the study area includes the South Fork of the Watab River and wetlands. The Watab River does not currently appear on the Minnesota Pollution Control Agency (MPCA)'s 2008 Impaired Waters list. The Tier I DEIS will include a description comparing alternatives with respect to potential water quality and quantity impacts and feasibility of providing mitigation. The Tier II analysis will detail water quality impacts and mitigation for the Preferred Alternative based on more detailed road and bridge design development. 5.2.2.8 Land Use Existing land use within the North Corridor study area includes agricultural lands, open space, undeveloped lands, rural residential properties, single-family development, and commercial and industrial land uses. The study area encompasses portions of the City of St. Joseph's Orderly Annexation Area and St. Joseph Township. These areas are experiencing development pressure as the City of St. Joseph grows to the north, and development is currently taking place approximately 60 feet south of Alternative 1. Adopted long-range local and regional plans forecast development (primarily low-density residential growth) for the project area, north of the City of St. Joseph, and identify the need to plan for infrastructure in anticipation of that growth. Local and regional plans identify a number of future developments that are anticipated to take place in the area and which will be associated with a need for increased transportation network connections and capacity in the area. Specific development sites have been identified for several locations within the study area (e.g., the Northland Heights housing development south of the proposed North Corridor, and the proposed Feld development east of CSAH 133). Development of alternatives during this scoping study attempted to minimize impacts to existing and proposed development sites to the extent feasible. St. Joseph North Corridor - 38 - February 2009 scoping Document The Tier I DEIS will examine the compatibility of the project alternatives with the existing land uses in the area and with future land use plans for affected properties. The Tier I DEIS will also compare the direct land use impacts due to right of way acquisition, access changes, and potential indirect land use impacts that may occur as a result of changes in traffic volumes and traffic patterns on area roadways following construction of the proposed project. Induced or indirect land use impacts will be considered in terms of potential acceleration of planned development or potential changes in land use type that may occur due to improved or changed access. The Tier II analysis will examine the compatibility of the Preferred Alternative with existing and future land uses. 5.2.2.9 Farmlands The federal Farmland Protection Policy Act (FPPA) and the Minnesota Agriculture Land preservation and Conservation Policy Act ensure that impacts on agricultural lands are integrated into the environmental decision-making process and that impacts are minimized to the extent feasible. Roadway construction projects processed through the FHWA are subject to the FPPA. As noted, the majority of land within the project area is in agricultural use. These lands may be affected by the Build Alternatives. Preservation of a future roadway corridor would not prohibit agricultural uses. The conversion of farmland to roadway use will depend upon the location of the Build Alternatives and the timing of roadway construction. The Tiex I DEIS will estimate relative impacts among alternatives on farmland areas based on existing land use. The Tier I DEIS will also discuss whether future land use plans indicate continued agricultural land use or planned conversion to other land uses within the impact area of each alternative. The Tier II EIS will document the specific farmland impacts of the Preferred Alternative. 5.2.2.10 Right of Way Acquisition and Relocation The Build Alternatives will require land acquisition within the study area for right of way. Acquisitions may require relocation of residents or businesses. The Tier I DEIS will analyze relative right of way acquisition impacts of each alternative based on total land area to be acquired and subdivided into categories including agricultural, residential, commerciaUindustrial, public, and open space. This analysis will be based upon existing land uses. The analysis will also address the appropriate means of mitigating adverse impacts in accordance with state and federal requirements governing right of way acquisition and relocation. The Tier II analysis will provide detailed assessment of the Preferred Alternative's right of way impacts and will discuss mitigation. 5.2.2.11 Environmental Justice/Social and Neighborhood Impacts/Community Facilities The communities considered a part of the study area are the City of St. Joseph as well as St. Joseph Township. The Build Alternatives include potential impacts to existing development, including existing residential neighborhoods. St. Joseph North Corridor - 39 - February 2009 Scoping Document Executive Order 12898 requires that the evaluation of environmental impacts resulting from a proposed project include assessment of the extent of these impacts on minority and low-income populations. Preliminary data collected during the Corridor Study indicate that there are low- income populations in the study area, and therefore have potential sensitivity to environmental justice issues. The Tier I DEIS will identify minority and/or low-income populations in the project area (based on current population data) and assess the relative impact of the project alternatives on any such populations identified. The environmental justice evaluation will follow the Mn/DOT's Environmental Justice Draft Guidance, dated August 5, 1998. The Tier I DEIS will also compare alternatives with respect to impacts on community facilities; access to residential areas and community facilities and services; neighborhood and community cohesiveness; and provision of emergency services, based primarily on existing land uses. The Tier II analysis will provide detailed assessment of the Preferred Alternative's impacts to minority and low-income populations, neighborhoods and community facilities, and mitigation for these impacts as applicable. 5.2.2.12 Hazardous Materials, Contaminated Properties Preliminary research of known and potential sources of soil and groundwater contamination identified no known contaminated sites within the study area (Minnesota Pollution Control Agency, 2008). However, land uses identified as potential sources of contamination in the study area include agricultural uses that pose the possibility of contamination due to pesticide or petroleum spills or dump sites. An aggregate supply operation is located in St. Joseph Township, within the project area. The Tier I DEIS will summarize the results of MPCA "What's in my Neighborhood" searches, as well as discussions with county and local officials, to determine the relative potential for alternatives to impact contaminated property. The Tier II analysis will be based on a Phase I Environmental Site Assessment to be conducted to determine any potential contamination source impacts to be avoided or minimized. 5.2.2.13 Cumulative Impacts Cumulative impacts are defined as "the impact on the environment which results from the incremental impact of the action when added to other past, present, and reasonably foreseeable future actions regardless of what agency (federal or non-federal) or person undertakes such other actions" (40CFR1508.7). Cumulative impacts are not causally.linked in their entirety to the project, but are the total effects of actions with similar impacts in a broader geographic area. The purpose of a cumulative impacts analysis is to look for impacts that may be minimal and therefore neither significant nor adverse when examined within the context of the proposed action, but that may accumulate and become significant and adverse over a large number of actions. Other foreseeable future actions that would likely occur within the study area include development (e.g., the expansion of St. Joseph North Corridor - 40 - February 2009 Scoping Document St. Joseph's Industrial Park, the proposed Feld development) and transportation projects (e.g., CSAH 2 Realignment, Field Street) anticipated to occur within the study area through year 2030. Past actions include development over the last 20 years. The purpose of cumulative impacts analysis is to look for impacts that. may be minimal and therefore neither significant nor adverse. when examined within the context of the proposed action, but that may accumulate and become significant and adverse over a large number of actions. All resources affected by the proposed action will be assessed with respect to cumulative impacts. Resources with the greatest potential for cumulative impacts will likely include: wetlands, farmland, surface water quality, groundwater, vegetation, fish and wildlife, and threatened and endangered species. The Tier I DEIS will evaluate the relative incremental impacts among the proposed alternatives compared to the total impacts from other foreseeable future actions. The cumulative effects analysis in the Tier I DEIS will follow the analysis process as developed by the Council on Environmental Quality (CEQ) (Considering Cumulative Effects Under the National Environmental Policy Act (NEPA), Council on Environmental Quality, January 1997). The assessment of cumulative effects will include a qualitative evaluation. as described in the CEQ guidance. The Tier II EIS will evaluate the relative incremental impacts among the Preferred Alternative compared to the total impacts from other foreseeable future actions using the CEQ and FHWA accepted methodology in place at the time of the Tier II analyis. 5.2.3 Issues of Moderate Concern Requiring. Less Detailed Analysis These issues are less likely to have a substantial impact on selection of a Preferred Alternative than issues identified in the previous two sections because they are either 1) likely to be minimally impacted by any of the project alternatives or 2) likely to have similar impacts resulting from any of the alternatives. Analysis of these issues in the Tier I EIS will focus on identifying potential concerns, relative differences among alternatives and how these issues need to be addressed in the Tier II EIS. 5.2.3.1 Traffic Noise Construction noise impacts are of limited concern because of their short-term duration relative to the long-term operational noise of a roadway. Therefore, the EIS process will focus on traffic noise impacts. All alignments include proximity to existing and/or planned residential development and other potentially sensitive receptors. The project will be subject to federal and state noise standards. Most of the representative receptors within the study area include rural residential uses or industrial uses. Impacts on school and park locations will be considered, if applicable. Monitoring of existing noise levels at various locations within the study area will be completed. The Tier I DEIS will discuss the relative noise impacts of each alternative, utilizing existing and future traffic volumes, as well as monitored existing noise levels at various locations within the study area. Traffic noise levels will be modeled for the Tier I DEIS to identify representative St. Joseph North Corridor - 41 - February 2009 Scoping Document traffic noise levels, given the noise model input file assumptions and existing and projected traffic volumes that were used to generate the model input files and the model output. The noise analysis results will describe distances from the North Corridor where regulatory noise thresholds are anticipated to be approached and/or exceeded for various land uses (e.g., residential, commercial, industrial, etc.) based on the assumptions used to generate the model input files and the traffic volumes used with each model run. These distances are intended to be used as a reference guide in community planning to help minimize future noise impacts. Modeling of existing and future traffic noise levels will be completed using the noise model adopted by Mn/DOT and approved by MPCA for use in Minnesota at the time the traffic noise analysis is prepared. The Tier II analysis will address noise impacts and proposed mitigation for the Preferred Alternative in conformance with applicable regulatory requirements. 5.2.3.2 Air Quality In 1993, the City of St. Cloud was designated as a maintenance area for carbon monoxide (CO). The North Corridor study area is located outside of and to the west of the City of St. Cloud maintenance area. The project is not located in an area in which conformity requirements apply. The Tier I DEIS will discuss relative traffic operations projections among alternatives in relation to potential air quality issues for No-Build and Build Alternatives. The Tier II EIS will include air quality analysis in compliance with relevant requirements and standards. MPCA staff will be consulted during the development of the scope, methods and procedures to be used in performing the air quality analysis. 5.2.3.3 Intermodal Transportation Bicycle and Pedestrian Movements and Handicapped Accessibility As previously described, the Lake Wobegon Trail is located within the project area; trail feasibility studies have been completed by Stearns County to examine opportunities to extend the trail to the City of St. Cloud. All Build Alternatives would require a crossing of the Lake Wobegon Trail The North Corridor would be planned to include separate bicycle facilities. The Tier I DEIS will evaluate relative potential impacts of the project alternatives on current trail plans and pedestrian and bicycle access to/from and between these facilities, as well as evaluate opportunities to benefit planned trail facilities within the project area. The Tier I analysis will also indicate if additional or more detailed assessment of pedestrian/bicycle issues is recommended for Tier II study. The Tier I analysis will also identify if any special considerations are needed for handicapped accessibility in conjunction with project design. St. Joseph North Corridor - 42 - February 2009 Scoping Document Truck Traffic The St. Joseph area road network regularly carries truck traffic. The existing CSAH 2 truck route is currently designated on 2nd Avenue NW. The North Corridor is not currently a truck route and is not anticipated to affect the location of a future truck route. The Tier I EIS will assess the likely impact of the project alternatives on truck traffic and travel patterns based on travel time estimates for each alternative. The Tier II analysis will provide detailed assessment of the Preferred Alternative's impacts on truck traffic. Rail There are no active rail lines within the project area. Transit Transit services in the project area are limited to Tri-Cap Transit Connection and Volunteer Driver Program dial-a-ride services. There are no plans for a substantial increase in transit service in the future. The existing park-and-ride facility is adjacent to I-94 and would not be impacted by the North Corridor. It is primarily used for ridesharing and carpooling. The Tier I DEIS will identify relative impacts of each. of the alternatives on existing and planned transit services in the area based on transit plans in effect at time of Tier I DEIS preparation. The Tier II EIS will discuss the relationship of the project to transit plans in effect when that phase of the project's environmental documentation is prepared. 5.2.3.4 Construction Impacts Impacts on the physical and natural environment can be expected during the construction phase of the project. The Tier I DEIS will describe the relative construction phase impacts on water and air quality, erosion, noise, vibration, vegetation, and traffic of alternatives being considered. The Tier II analysis will provide additional detail on construction of the Preferred Alternative and discuss mitigation measures. 5.2.3.5 Erosion Control and Slope Stability The potential for erosion/sedimentation impacts are not expected to differ substantially among Build alternatives. The Tier I DEIS will compare the relative potential for erosion sedimentation impacts and feasibility of providing mitigation. 5.2.3.6 Economic Impacts Potential economic impacts include direct effects due to right of way acquisition and indirect effects due to changes in land use patterns. The Tier I DEIS will compare alternatives with respect to economic impacts on the regional and local economy (e.g., effects on development, tax revenues and public expenditures, employment opportunities, accessibility, retail sales), any impacts to nearby businesses, as well as indirect effects due to changes in land use patterns. The St. Joseph North Corridor - 43 - February 2009 Scoping Document assessment of economic impacts will include a qualitative evaluation and comparison of alternatives in the Tier I DEIS. The Tier II EIS will analyze impacts from the Preferred Alternative upon those local economic factors. 5.2.3.7 Excess Materials Construction of a Build Alternative could require the disposal of excess material outside of the project construction limits. Excess materials would be predominantly soil materials, which, if not contaminated, pose little environmental hazard, but may also include demolition of existing highway pavement and/or building materials. All demolition and construction material removed from the construction area will be recycled and/or disposed of in compliance with federal and state solid waste management regulations. The Tier I DEIS will provide general discussion of appropriate handling of excess materials if appropriate, as this will have limited influence on the identification of a Preferred Alternative. 5.2.3.8 Groundwater, Geology and Soils The depth to groundwater within the study area ranges from 0 to 20 feet, with the potential for encountering the water table close to the ground surface adjacent to wetlands. According to the Geologic Atlas of Stearns County (1998), the general movement of groundwater through the project area is to the east towards the City of St. Cloud and the Mississippi River. Impacts on groundwater will be examined in the Tier I DEIS, including potential impacts from infiltration of stormwater runoff from new impervious surfaces, impacts on existing wells, and potential impacts resulting from any excavation to the depth of the existing water table. Resources to be consulted include, but are not limited to, the Geologic Survey of Stearns County and the Soil Survey of Stearns County. Early studies have not indicated any geological concerns that would impact alternative selection for this prof ect, with the exception of the need to avoid a large aggregate mining operation northwest of St. Joseph. The potential for erosion impacts are not expected to differ substantially among alternatives at the Tier I level. The Tier I DEIS will review potential geology or soils concerns that could affect selection of a Preferred Alternative, address the relative potential for each alternative to affect groundwater, and determine the relationship of alternatives to any municipal wellhead protection areas identified in the area at the time. The Tier II analysis will provide additional analysis based on specific design information related to the Preferred Alternative. 5.2..3.9 Utility Locations Known utilities, including electric power transmission lines, electric substations, natural gas lines, sewer lines, and water lines, were identified as part of this scoping study. Utilities within Minnesota and the surrounding region are planning expansion of the electric transmission line system (i.e., CapX 2020 projects). One of the CapX 2020 projects is a 345-kilovolt (kV) transmission line between Fargo, North Dakota and Monticello, Minnesota. The North Corridor St. Joseph North Corridor - 44 - February 2009 scoping Document study area is located within the proposed project study corridor for the Twin Cities -Fargo 345 kV Project. The Tier I DEIS will identify utility locations and any substantive differences in utility impacts among alternatives that could affect selection of the Preferred Alternative. The Tier II EIS will review the utility locations and incorporate any new information that should be considered in the analysis of the Preferred Alternative. 5.2.3.10 Visuallmpacts/Quality The existing visual character of the study area includes the natural and built environments. The Tier I DEIS will identify the relative visual impacts of each Build Alternative on views from within the study area, as well as measures to avoid, minimize, or reduce adverse visual impacts. The Tier II analysis will provide detailed assessment of the Preferred Alternative's visual impacts. 5.2.3.11 Indirect Impacts The Tier I DEIS will compare alternatives with respect to potential indirect land use impacts that may occur as a result of changes in traffic volumes, patterns and/or access to the transportation system for each alternative (e.g., acceleration of planned development or potential changes in land use type based on changes in accessibility created by each alternative). The indirect effects analysis in the Tier I DEIS will follow FHWA guidance and will include qualitative and quantitative methodologies following the eight steps that comprise the community of practice for the analysis of indirect effects (Louis Berger Group, Inc., 2002). These eight steps are identified below. 1. Initial scoping for indirect effects analysis. 2. Identification of study area goals and objectives. 3. Inventory of notable social, environmental, and cultural resource features. 4. Identification ofimpact-causing activities of the proposed action and alternatives. 5. Identification of potentially significant indirect effects for analysis. 6. Analysis of indirect effects. 7. Evaluation of analysis results. 8. Assessment of the consequences and development of appropriate mitigation and enhancement strategies. The Tier II analysis will provide detailed assessment of the Preferred Alternative's indirect impacts. St. Joseph North Corridor - 45 - February 2009 scoping Document 5.2.3.12 Irreversible and Irretrievable Commitment of Resources The Tier I DEIS will discuss relative differences among alternatives regarding the proposed project's commitment of resources, including, as appropriate, natural, physical, human and fiscal resources, which would be permanently dedicated to public use, and not able to be reversed or retrieved. The Tier II EIS will review this analysis and update it as necessary to reflect the impacts of the Preferred Alternative. 5.2.3.13 Relationship of Local Short-term Use versus Long-term Productivity The Tier I DEIS will discuss relative differences among alternatives regarding the proposed project's short-term adverse impacts and use of resources and their relationship to the long-term gains in productivity resulting from the proposed project. The Tier II EIS will review this analysis and update it as necessary to reflect the impacts of the Preferred Alternative. 5.2.4 Issues Not to be Addressed in Tiered EIS Coastal Zones -The study area is not located within a coastal zone. • Wild and .Scenic Rivers - No wild and scenic rivers are located within the project area. Therefore, this issue will not be addressed in the EIS. • Critical Areas -There are no state designated critical areas within the project area. 6.0 PUBLIC AND AGENCY INVOLVEMENT The Corridor Study process sought to promote effective decision-making by fostering a cooperative spirit and building trusting relationships among state, regional and local partners, and the public. These relationships were important elements in completing the corridor study: The various study partners worked together to develop a corridor plan that improved safety and mobility, addressed environmental concerns, and respected community values. The Corridor Study used the following means to promote public involvement: Corridor Advisor~Committee (CAC) -The CAC, composed of elected officials and senior technical staff of local decision-making bodies, met regularly during the study period. The CAC guided the overall study process, considered input from public involvement activities, participated in the technical analysis, and made recommendations to the St. Joseph City Council and Stearns County Board of Commissioners. CAC activities included reviewing and evaluating alternatives and recommending a preferred alignment. St. Joseph North Corridor - 46 - February 2009 Scoping Document Focus group meetings - The focus group, .which was composed of private citizens, businesses, and local government provided input on needs, issues, constraints, and opportunities early in study process, and again on alignment alternatives during the evaluation process. At these meetings the Corridor Study team learned which North Corridor alternatives were preferred by key landowners facing the largest impact from these future roadways. The groups also suggested new alignment and access alternatives that the Corridor Study team had not considered earlier. • Open house public meetings -The meetings provided opportunities for the general public to participate in the corridor planning process. The meetings also provided opportunities for key stakeholders to come back. and take a second look at materials presented during the focus group meetings and bring family/friends/other affected parties to learn about and comment on the study. Open house input was recorded and provided to the CAC for. consideration. • Review agency and key stakeholder coordination -The Corridor Study team met with officials from FHWA, Mn/DOT, and the Stearns County Technical Evaluation Panel (TEP) two times during the study process. Through these meetings FHWA and Mn/DOT officials provided insight into appropriate environmental documentation, while the TEP provided insight into wetland and local development issues. • Presentations to governing bodies -The Corridor Study team met with the St. Joseph City Council and Stearns County board at several points throughout the study process. The presentations briefed officials on key study recommendations and allowed the Corridor Study team to seek comments, input on policy, final decisions, and final approval of study products. • Project website -The City of St. Joseph website was used to disseminate important study information, including focus group/public meeting materials, CAC agendas, CAC meeting summaries, and public meeting notices. The scoping process has been guided by the participation of the PMT. The PMT consists of staff from Mn/DOT District 3, St. Cloud APO, Stearns County, the City of St. Joseph, and St. Joseph Township. The role of the PMT is to provide the .direction to advance the proposed project through this scoping study and the environmental review process. As a result of public input received on the Corridor Study at focus group and public meetings in July 2006, another Corridor Alternative was added to the project, as described in Section 3.2. Agency and local government input opportunities were also provided during the scoping process. Letters requesting input on potentially significant issues within the study corridor were sent to regulatory agencies early in the scoping process. The City of St. Joseph, as project proposer, along with members of the PMT, will continue to engage community organizations, area property owners, residents, business owners, and local, county, regional, state and federal agencies in the development of the proposed project. The Agency and Public Coordination Plan is included in Appendix B. St. Joseph North Corridor - 47 - February 2009 scoping Document 6.1 COOPERATING AND PARTICIPATING AGENCIES The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) establishes a new environmental review process for transportation projects developed as environmental impact statements. These requirements are intended to promote efficient project management by lead agencies and enhanced opportunities for coordination with the public and with other federal, state, local, and tribal government agencies during the project development process. To enhance interagency coordination and ensure that issues of concern are identified, SAFETEA-LU created a new category of involvement in the environmental review process termed "participating agency." The intent of the new category is to encourage governmental agencies at any level (federal, state, and local). with an interest in the proposed project to be active participants in the NEPA evaluation (US Department of Transportation, 2006). The following federal agencies were invited by FHWA to serve as cooperating and participating agencies for the project. • U.S. Army Corps of Engineers (COE) • U.S. Environmental Protection Agency (EPA) • U.S. Fish and Wildlife Service (USFWS) • U.S. Department of Agriculture, Natural Resources Conservation Service (MRCS) The following state and local agencies were invited by FHWA to serve as participating agencies for the project. State A eg ncies • Minnesota Department of Natural Resources (MnDNR) • Minnesota Pollution Control Agency (MPCA) • Minnesota Department of Agriculture • Minnesota Board of Soil and Water Resources (BWSR) • Minnesota State Historic Preservation Office (SHPO) • Minnesota Department of Transportation (District 3) Local A encies • Sauk River Watershed District • Stearns County Environmental Services • St. Joseph Township • St. Wendel Township • City of St. Cloud The role of cooperating and participating agencies as part of the North Corridor environmental review and project development process is documented in the Agency and Public Coordination Plan in Appendix A. St. Joseph North Corridor - 48 - February 2009 Scoping Document 7.0 PERMITS AND APPROVALS 7.1 PERMITS AND APPROVALS REQUIRED A list of applicable permits and approvals anticipated for the proposed North Corridor project is provided in Table 14. TABLE 14 ANTICIPATED PERMITS AND APPROVALS REQUIRED AGENCY PERMIT/APPROVAL Federal Advisory Council on Historic • Section 106 of the National Historic Preservation Preservation Act-Memorandum of A Bement if needed Federal Highway Administration EIS A royal draft and final for both Tiers • EIS Record of Decision ROD for both Tiers • Section 4(fj Evaluations (draft and final for both Tiers) (if needed) U.S. Army Corps of Engineers Section 404'of the Clean Water Act-Permit (fill in waters of the U.S. • Section 10 of the Rivers and Harbors Act-Permit (if needed for construction of brid e over Watab River State Minnesota Department of Transportation EIS A royal draft and final for both Tiers • Section 106 of the National Historic Preservation Act Cultural Resources Determination • Section 106 of the National Historic Preservation Act-Memorandum of Agreement (if needed) • Plan Review Minnesota Department of Natural Public Waters Work Permit (if needed Resources Mussel Relocation Permit (if needed for construction of brid e over Watab River) Minnesota Pollution Control Agency Section 401 Water uali Certification • NPDES Permit Minnesota State Historic Preservation Section 106 of the National Historic Preservation Office Act-Cultural Resources Concurrence • Section 106 of the National Historic Preservation Act-Memorandum of Agreement (if needed Local City of St. Joseph • Scoping Decision Document • EIS Approval (draft and final for both Tiers) • EIS Adequacy Determination Stearns County Wetland Conservation Act (WCA) Stearns County Soil and Water Coordination of Grading and Drainage Plans Conservation District St. Joseph North Corridor - 49 - February 2009 Scoping Document 7.2 LEVEL OF ACTION The proposed North Corridor Project is considered a federal Class I action as defined in 23 CFR 771.115(a). As previously noted, FHWA is the lead federal agency for this project. The proposed North Corridor Project also meets the mandatory EIS threshold under Minnesota Rules 4410.4400, subp. 16 (construction of a road on a new location which is four or more lanes in width and two or more miles in length). The City of St. Joseph is the RGU for this project. St. Joseph North Corridor - SO - February 2009 Scoping Document References Louis Berger Group, Inc. (2002) National Highway Cooperative Research Program Report 466 Desk Reference for Estimating the Indirect Effects of Proposed Transportation Projects.. Project B25-10(02) FY '96 Transportation Research Board, National Research Council Washington, D.C.: National Academy Press, 109 pp. U.S. Department of Transportation. Federal Highway Administration and Federal Transit Administration. November 2006. SAFETEA-LU Environmental Review Process Final Guidance. St. Joseph North Corridor - 51 - February 2009 Scoping Document APPENDIX A SLOPING DOCUMENT FIGURES r ~ ~ ~~ ~ w o m i- ~ ~ Um o ~ ~ '; .~ o <`a _~ o ~ o ~' ' a m_ ` : Y a j - / ~ U ~ o > l34 y ' o ~ ~ ~ __,, .. , ~~ _ ~ ~ ' ~ _ r~ a~ _ ~~ , ~ ..~ ~ U `-" ._._._.._ -e._-~_~ ~ ,~ f. -y ~ w Ln ~C~oY r N d ~.~---. V in o P ~ ~ 0~1 '~ ~o ' w , ;,E ~ ~ O ~ f ._ r ,~ ,~ ,- 6 .,,te . r N h ~. , ~ a ` o 0 ~ c e ` ~ o ~ E ~ - ~~~. m v m ~ N 9 . ~ s a a ~ ~ I~ ` f m Y ° 1. ~ ad C Q a F fi ~ ~ ~U O :,,~ v w ~ ~ U ~ \ i m ~ alOr ~ . ~ m _ - ~ a U e` C ~ - 8 ai 01 d J r r r =.,.k Pxw 16414VON eM'1515~JS01Pxw1£ESASdeyy6f ~L c U O 01 C .Q O 0 U n Z L L ~ 0 d ~ N N N O ~ `o ~~g _~~ ~ ae _~ ~ a ~ ~ e ~ - < ~ 5 ~ ~, c "~ ~ 8 C~ " ~ ~ o ~ z N N~ j ~ 4 ~~ 1 ~ ff ~ ~ ~ Y a o _ t ~ ~ a s ff ~~ ~ 7 ~~ ~ o~~~ v ~` Ya w V ~ O 1 ~ ' ~"' &,'" ~ ~ o .. ... ;~ W, ~ ~ T, ~ ~ t~ ~ l ~ r a. :+ 1 ~- ~ z ~. i ~I ti x.: , , y ~ -_ C ;' ~ t¢q a ~~ ~ ~,~ y ~~„ tid~~ it ~~:~~~. r, , a' ,I r. .c a ~ w j ,~ ~ f y c~ i r~ ~, ~ pi t ~ ~ ~ o ;r ~ ~~ ~~ j ~_ f 3` ~~ .k;~ , 0 ~ ~ ~ii~ n ~ ~ ~ + ., v - . :' c O y N N O 0 N M C J d Q N O O .-. V Z ~C~..~ C U l^ V Z a O U O 0 O U Or z a 2 ~ d~ W ~" Oo H .~ Cn U d t ~ w ti ~ ~ ~ y ~ i ~ mU , ` ~( U s ~ ~ ~' ~ 1 ~~ ~~ ~ ~ ~ ~ N .uL..m~~-~ ~' t M II z ~_.~.~~.-.z .... ~>r._. v ~~,__._..._ ~~ ~ ~_ ' M i ~ p ~ C' d C+J $ i~ and U#08 t I' a a 4'~q eN ~r-~., ~ V) ~ S.. l ~ F ~+ 5 ` ~) ~ ~ ` ~ E ~: ~ ~ C F M' I ~'i ~ ~I N I (!! ub4o,P .. VIZ t~,;:, N G ~ !1J-_ ~ ~I", ~ ~ _ a^b 4l5g } , and#S46 > ~ ~ li '~ l~A °iV' C ~ . ~~{ N ~/ L ~ ',. _ 118} \\\\} ~~Pc I A ' ~ % 1, ~ L ~ ~ L ~ ~ jPy roe ild d0~ ~' ~ e o ~ a d ~ r V ~ •~ ~ ~ I; ~ ~ I ` any puZ04 I,I ~ o a-r,~ ~ Z any Pa£04 9P~p~~ , ~~ ~'ri dim e./ Jc ' ~,.. ~ , i ~ ~~~n ~o ~,,, i'~il ~ ~' ~~ ' Q-a ~ e p m ~ .~ i ~tiaA ~ ~ ~~o `l o J +~ ~ ~ ;~ ~ ~, ~ ;, I If any 4#5l4 3 ~' ~ `~ o\\e9e~~ I ~~n~p r Rd J „F.m. t ~~ ~ cowl unwwou mns~sasmecssU~mcr d' d E U 0 0 .~ U N O t 0 U L r a o z ~ z d in 0 0 f!) U APPENDIX B PUBLIC AND AGENCY COORDINATION PLAN St. Joseph North Corridor Project Stearns County, MN Agency and Public Coordination Plan (March 2008) The purpose of the St. Joseph North Corridor Project Agency and Public Coordination Plan is to facilitate and document the Federal Highway Administration's (FHWA), Mn/DOT's, and the City of St. Joseph's structured interaction with local governmental units, regulatory agencies, and the public. The plan is also intended to inform these agencies and the public of how project coordination will be accomplished throughout the project development process. The Agency and Public Coordination Plan will be updated periodically to reflect any changes to the project schedule, or to update other items as necessary during the project development and environmental review process. The FHWA is the lead Federal agency for the proposed project. Mn/DOT, as the direct recipient of Federal funds for the proposed project, is the joint lead agency. The City of St. Joseph, as project sponsor responsible for design and construction of the proposed project, and sub- recipient of Federal funds, will also serve as a joint lead agency. The St. Joseph North Corridor Project will follow a Tiered Environmental Impact Statement (EIS) process. In general, the Tier I EIS will identify and evaluate the social, economic and environmental issues associated with the Corridor Alternatives, as the basis for identifying a preferred corridor alternative that can be preserved for future use. The Tier I EIS will consist of a Tier I Draft EIS (DEIS), a Tier I Final EIS (FEIS), and a Tier I Record of Decision .(ROD). In general, the Tier I DEIS will provide analysis of the potential social, economic, and environmental impacts of all Corridor Alternatives, whereas the Tier I FEIS will provide more detailed analysis of the impacts associated with the alignment identified as the Preferred Corridor Alternative following the DEIS comment period. A Tier II EIS process will be initiated in the future, as the project moves forward for implementation. The Tier II process will focus on Preferred Corridor Alternative design details, an updated assessment of environmental impacts, and identification of mitigation. Specific content for the Tier II DEIS and FEIS documents will not be known until they are initiated; the Tier II process is essentially the same as the Tier I EIS process (DEIS, FEIS, ROD). The St. Joseph North Corridor Project's Tier I EIS has several key coordination points. These coordination points are listed and described below. As discussed above, the Tier II EIS process, to take place in the future closer to project construction, will follow approximately the same process. • Notice of intent publication and scoffing activities - A notice of intent will be published in the Federal Register by FHWA. It is currently anticipated that the notice of intent will be published in the Federal Register in 2009. Review copies of the Scoping Document/Draft Scoping Decision Document (SD/DSDD) will be distributed to the Participating Agency group (made up of staff from federal, state, and local agencies). Review copies of the SD/DSDD are anticipated to be available for Participating Agency review in April 2009. Members of the Participating Agency group will be provided a 30-day review and comment St. Joseph North Corridor B-1 Agency and Public Involvement Plan period to provide feedback. A Participating Agency workshop will be held following the 30-day Participating Agency review period to discuss the draft SD/DSDD and other scoping activities (date to be determined). Agency feedback will be requested prior to the publication of the document for public/agency review and comment. A June 2009 publication date is anticipated for the SD/DSDD, which will also initiate the official 30-day scoping review and comment period. The SD/DSDD Notice of Availability will be published in the Minnesota Environmental Quality Board (EQB) Monitor. A public scoping meeting will be held during the 30-day comment period to afford an opportunity for the public and agencies to learn more about the proposed project, ask questions, and submit comments. • Development of purpose and need -The purpose and need for the St. Joseph North Corridor project will be included in the SD/DSDD. FHWA, Mn/DOT and the City of St. Joseph will be requesting specific input on the purpose and need from the Participating Agency group at the Participating Agency workshop. • Identification of the range of scoping alternatives -The full range of alternatives to be considered will be identified in the SD/DSDD: FHWA, Mn/DOT and the City of St. Joseph will be requesting specific input on the range of alternatives from the Participating Agency group at the Participating Agency workshop. • Collaboration on impact assessment methodologies -The impact assessment methodologies will be documented in the SD/DSDD. FHWA, Mn/DOT and the City of St. Joseph will be requesting specific input on these methodologies from the Participating Agency group at the Participating Agency workshop. • Completion of the Tier I Draft Environmental Impact Statement LDEIS) -The schedule for preparation and review of the Tier I DEIS will be determined at a later date. Review copies of the Tier I DEIS will be distributed to the members of the Participating Agency group with a 30-day review and comment period to provide feedback. The Tier I DEIS will then be revised and published for public/agency review and comment. The schedule for requesting agency review and feedback on the Tier I DEIS will be determined at a later date. A public hearing will be held during the official 30-day (45 days if Section 4(f) involvement) comment period on the Tier I DEIS to afford an opportunity for the public and agencies to ask questions and submit formal comments. Identification of the Preferred Corridor Alternative and the level of design detail - A second Participating Agency workshop is planned following the official comment period on the Tier I DEIS. The schedule for this Participating Agency workshop will be determined at a later date. Comments received on the Tier I DEIS will be shared with the Participating Agencies. FHWA, Mn/DOT and the City of St. Joseph will be requesting specific input from the Participating Agency group on the identification of a Preferred Corridor Alternative. St. Joseph North Corridor B-2 flgency and Public Involvement Plan • Completion of the Tier I Final Environmental Impact Statement (FEIS -The schedule for preparation and review of the Tier I FEIS will be determined at a later date. Review copies of the Tier I FEIS will be distributed to the members of the Participating Agency group with a 30-day review and comment period. The Tier I FEIS will then be revised and published for public/agency review. • Completion of the Tier I Record of Decision (RODS -The Tier I ROD will be distributed to all members of the Participating Agency group. The schedule for distribution of the Tier I ROD to the Participating Agency group will be determined at a later date. Completion of permits, licenses, or approvals after the Tier IROD -Numerous permits and/or approvals will need to be obtained from several Participating Agencies. These permits/approvals will be requested following the final design phase and when funding for construction becomes available. A St. Joseph North Corridor project public involvement plan has been prepared in addition to this Agency Coordination Plan. A draft matrix presenting the various opportunities for publiclagency involvement scheduled during the St. Joseph North Corridor project scoping process is attached on the following pages. This matrix will be periodically updated throughout later stages of the project development and environmental review process as appropriate. St. Joseph North Corridor B-3 Agency and Public Involvement Plan ~ ~; ,~ a o ~' U ~ O it ~ O z~ '~ O ~ ti a bA O V o ~ U O ' ~ • '" " ~ ~ p ^O ~ ~ O ti y O N W U ~ U N rn ^O ^~ „ y s. R. O C GL v, C ~ ~ ~ ~ ~ ^ ~ 1'~'I W O h CC p ~ ~ V ~ Q) .C .~= UN ^ ~ + bA ~ G y UU ^ ^ dv~a; ^ ^ ^ 00 °U ^ ^ ^ rn ~ W ^ ^ N U C v ~ op '' Q a ~ ~~ ~A ~y p N ~ " •~p one G~ ~ V (~ O ~ + C '~ N ~ N iC ~ R ~" N ~~• 'O r..LS. 'O r. "O q ~ • °~ ~ p A ~ pY. ~ A. vi Q ~ . C ti A ~i y ~ ~ ~~ ~ ~ C O ~ ~ O Q .U+ C/1 0 U • ~ 0 ~c w ~- i U ~ ~ ~ y 3 3 . ~ b . .. ~t ,~ ^ N ^ r o ~ p 0 •v .~ o ai ~ Q c.' ? O •~ ~ ~ a~ '~ •~ ~ o ~ ~ r ~ 'C3 O G ~ ~ U " ' ~ •... w ~ ~ ~ ~ a o Chi •v ~ U s ., ~ ~ ~ ~ ... ~ .a, • O .. ° ~ o o ~ N rn U O U v ~ v ~ cd p" c ~ O ~ ' N 7 a~~~ . a 3ca~ a.~ ~w °: ~ ~a °; ~ ~~ ~a°1 ~ . '~ w o o N '.o ~ ~ O o •~ p., -d ~~U y ~~~ ~U o~ Ucn ~ aZ ~" ~ .k ~ N ~^ Rf -~"~ ,~ V1 M S.. ~ ~ a ~ j V V v1 i ' ~ •o o ° ¢, ~ ~, ~ ~ j ~ ~ v i ~ ~ ~ ti. ' ° .~ °' '~ LL " U .c 1--I ~ ~ > er ~ o~ ~ o tia ~~CQF" c ai ~ -a ~ ~- Y o• O ° ~ W o ~Q ~ e y a ~CQ~~ oUE" p ,, y ~ ~ N N > V G. U ^~ F-^ A. ~' • ~ ~ O ~, n ~ `n•~'~ ' ~ bD V E"' O U Q. P, .., ~+-~ F-~ p, C ~ F ~ Q ~ ~ Q .~•o W y ti O O y •~°°~ Qp ~. cC .~ F~~~ _ N y vpi y .S: ~ N Q, ~" O Cam. ~ O~ ti Y •~ ae p~ ~~.~~~e.~~pp~ O ~ O ~ .~ N ~' ~. aU+ U ~ a-+ Uvsv~v~~v~ /-. O ~ N aaww P. ~ xi q ~' ~' O y ~ ~ acC. W C" O N a% ' O w~av~U~¢ °wwrn o~av~v~v~F-' • • C9 ~ ~ a ~ ~ U _ '~ O U N Ri ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ~ p p F4 «! ^ ^ ^ ^ ^ ^ ~ ~ y . . o ~ ,., a . ~ c U Cq ~ ~ ~ to ~ ~ ~ oA on ~ ~ ~ ~ ~.i U ~ /1 ~ H ~ 'fi nA ~.a c a U ~~ r., `~' c U~~ ,, o ~ ~ ~ ~ 'Z7 y a i ~ ~O ~ ~ ~ ~ G~ ~ a 'r,3 a> •~ a~ 0 ~; tci W H .~. H ~s ~r W A ~. H w 0 ~i+ t'r 0 U .~ ~° ~ ~ b ~ .~ W ~; 4. o ~, o k+ .~ >, ~ o Y ~ 0 0 o ¢' bA ~•~ 'b O ~ U N '~• ~•' i.. ~O ~ ~w ~ ~~ o C ~ ~w o ou ~ ~ ~ ~• :- W ~ ~ ~ Oa"~ z a ~. fi U U ao a w a~ O C x, 0 .~ x. 0 U .i.., O Z ~/ o a, ~ ~ 0 ~ ~ ~ o O ., a ~ 4-r ~ o •~ ~ ~ U 3 ~ U N ~ O V C." ~ ~ ~ o ' G> ~ "' A. ,~ ~3 ~ ~ 3 ~ JAI W N ~ gyn. '~ ~ ~i ~-I ti ~ N Q ~ ~ ~ ~ . w" ~ 3 ~~ ~ ~ 0 C7 a ~ ~ ~ o on ~ o ~ O o . ~ ~ U . ,~ ~ a o ~ a"O a~ 0 ~+ o ~ y O '~ ~, O i.i ~j ~ ~./ ~ _ O ~ ~ ~ ~ ~ ~ '~ H ~' U U ~ •^7 Q ^Itl~ 1^~~!~ P1 ~ N C.' .~ Y w w w Q 0 0 r: U fem.." .~ ~ ~ ~ ~~ w ~ ~ o .~ o w ~~' c ,~ o a~ N ~ ~ U O O s. ~. O pq .~' A, '~ O ~ v b N ~ y ~. ~ w ~o ~ ~w n. " y U ~ ~ ~ ~ ~~ U Lam" v~l ^~ O ~1 za ~ ~ '~ o O ~ ,U ~ ~ ~~ d rr^~ ~ vJ St. Joseph North Corridor Project Stearns County, MN Agency and Public Coordination Plan (March 2008) The Agency and Public Coordination Plan will be updated periodically to reflect any changes to the project schedule, or to update other items as necessary during the project development and environmental review process. The following matrix identifies changes to the Agency and Public Coordination Plan, and the date at which these changes occurred. -- -Date I Description of Change 1. 2. 3. 4. 5. 6. 7. 8. 9. St. Joseph North Corridor B-6 Agency and Public Involvement Plan APPENDIX C DRAFT SLOPING DECISION DOCUMENT DRAFT SCOPING DECISION DOCUMENT ST. JOSEPH NORTH CORRIDOR PROJECT City of St. Joseph, Minnesota City of St. Joseph Minnesota Department of Transportation Federal Highway Administration SRF No. 0055533 TABLE OF CONTENTS Page No. 1.0 INTRODUCTION ..............................................................................................................................1 2.0 PROJECT DESCRIPTION ...............................................................................................................1 3.0 PROJECT COST, FUNDING SOURCE, AND SCHEDULE ............................................................1 3.1 PROJECT COST AND FUNDING SOURCE ........................................................................................... 1 3.2 PROJECT SCHEDULE ................................................................................:.....................................2 4.0 RESPONSIBLE GOVERNMENTAL UNIT AND PROJECT MANAGER ........................................3 5.0 ALTERNATIVES TO BE STUDIED IN THE DEIS ...........................................................................3 5.1 NO BUILD ALTERNATIVE ................................................................................................................. 3 5.2 BUILD ALTERNATIVE ALIGNMENTS ...........................:.............................................................:.........4 5.2.1 Alternative 1 ........................................................................................................................ 5 5.2.2 Alternative 2 ........................................................................................................................ 4 5.2.3 Alternative 3 ........................................................................................................................ 5 6.0 ISSUES TO BE ADDRESSED IN THE DEIS ...................................................................................5 7.0 ISSUES NOT TO BE ADDRESSED IN THE DEIS ...........................................................................7 8.0 PUBLIC AND AGENCY INVOLVEMENT ........................................................................................7 8.1 PROJECT MANAGEMENT TEAM ........................................................................................................ 7 8.2 COOPERATING AND PARTICIPATING AGENCIES ...................................................................:............8 8.3 PUBLIC MEETINGS .............................................................................:............................................9 8.4 PROJECT WEBSITE ........................................................................................................................9 9.0 PERMITS AND APPROVALS .........................................................................................................9 9.1 PERMITS AND APPROVALS REQUIRED ............................................................................................. 9 LIST OF TABLES Page No. Table 1: Anticipated Permits and Approvals Required .............................................................................10 H:\Projects\5533\EP\Scoping\Reports\draft Scoping Decision Document\MnDOT FHWA review\North Corridor DSDD 02 09.doc St. Joseph North Corridor - i - February 2009 Draft Scoping Decision Document 1.0 INTRODUCTION The Scoping Document (SD) describes the purpose of and need for the proposed project, the process followed in the development and evaluation of corridor alternatives, and what social, economic, and environmental (SEE) issues will affect the continuing development of the proposed project. The Draft Scoping Decision Document (DSDD) indicates the issues and alternatives that will be examined in depth in the Tier I Draft Environmental Impact Statement (DEIS), as well as initial expectation for issues that will be examined in the Tier II EIS process. A final scoping decision will be made by the City of St. Joseph,. in consultation with the Minnesota Department of Transportation (Mn/DOT) and Federal Highway Administration (FHWA) after the public scoping meeting and at the end of the 30-day comment period. 2.0 PROJECT DESCRIPTION The North Corridor Project study area is located within the southwest St. Cloud Metropolitan Area in Stearns County (see Figure 1). The St. Cloud Metropolitan Area consists of the cities of Sartell, Sauk Rapids, St. Cloud, St. Joseph, and Waite Park, as well as Haven, Le Sauk, Minden, St. Augusta, St. Joseph, St. Wendel, and Sauk Rapids townships (St. Cloud Area Joint Planning District Plan, May 2000). The "Southwest St. Cloud Metropolitan Area" is defined as the cities of St. Joseph and Waite Park, as well as the portion of St. Joseph Township that is northeast of Interstate 94 (I-94). The study area boundaries extend north from County State Aid Highway (CSAH) 75, along CSAH 3 and then east, north of the City of St. Joseph to CSAH 133, as shown in Figure 1. The study area presently lacks continuous east-west roadways, other than CSAH 75. It is primarily agricultural today, but is experiencing substantial development pressure. The study area is located outside of St. Joseph city limits, within the City's annexation areas into St. Joseph Township. The purpose of the North Corridor study is to identify a minor arterial roadway corridor that can be preserved for future roadway development. The proposed future roadway would be part of a minor arterial network intended to improve mobility in the St. Joseph area by providing an alternative to CSAH 75, and providing connections to other minor arterial roadways (such as CSAH 2, CSAH 3, and CSAH 133) that also serve this growing area. The following primary needs are to be addressed by the proposed project: system connectivity, system spacing, and corridor preservation in support of future, planned land uses. 3.0 PROJECT COST, FUNDING SOURCE, AND SCHEDULE 3.1 PROJECT COST AND FUNDING SOURCE Planning-level cost estimates have been prepared for the North Corridor project for purposes of the draft Scoping Decision Document. These cost estimates were prepared using the St. Cloud APO planning estimate of construction costs of $2 million per mile and $1 million per mile for right of way acquisition. Engineering and construction administration cost estimates were St. Joseph North Corridor - 1 - February 2009 Draft Scoping Decision Document assumed to be 20 percent of the project cost. The proposed project costs are estimated at approximately $8.2 million to $8.5 million (2005 dollars). The Tier I DEIS will include more detailed cost estimates for the Build Alternatives based on preliminary design. Total project cost (construction, right of way, engineering) for the North Corridor Project was estimated for future year of construction. This estimate was based on planning-level project cost estimates developed as part of the St. Cloud APO 2030 Financial Plan Amendment. An inflation factor of 2.05 was assumed when estimating future costs. Total project cost for construction beyond year 2030 is estimated at $16.9 million to $17.3 million (2030 dollars). Funding for the North Corridor project has not been identified. Future funding for the project is anticipated from a combination of federal, state, and local funds. The specific contribution amounts from each of these three funding sources has not been identified. The St. Cloud APO 2030 Transportation Plan identifies the North Corridor as an "illustrative project." Illustrative projects cannot be included in the St. Cloud APO's fiscally constrained plan because it is anticipated that funds will not be available for these projects within the plan's timeframe based on projected revenue streams. Illustrative projects are only eligible to complete for high priority project (HPP) funding from the United States Congress. The Tier I EIS will update the North Corridor funding status based on the St. Cloud APO's Transportation Plan. 3.2 PROJECT SCHEDULE The following lists the anticipated schedule for completion of project activities: Federal Notice. of Intent Scoping Document/Draft Scoping Decision Document Public Scoping Meeting Scoping Decision Document Tier I Draft Environmental Impact Statement Identification of Preferred Alternative Tier I Final Environmental Impact Statement Tier I Adequacy Determination Tier I Record of Decision (ROD) Corridor Preservation/Official Mapping Initiation of Tier II EIS Process Winter 2009 Summer 2009 Summer 2009 Fa112009 2010-2011 2012 2013 2013 2013 To Be Determined 3 Years Prior to Construction St. Joseph North Corridor - 2 - February 2009 Draft Scoping Decision Document 4.0 RESPONSIBLE GOVERNMENTAL UNIT AND PROJECT MANAGER The FHWA is the lead federal agency under NEPA. Mn/DOT, as the direct recipient of federal funds for the project, is a joint lead agency under NEPA. The City of St. Joseph, as project sponsor, is ultimately responsible for design and construction of the proposed project, and as the sub-recipient of federal funds, is also a joint lead agency under NEPA. The City of St. Joseph is the project proposer and Responsible Governmental Unit (RGU) under Minnesota Rules Chapter 4410.0500 for the purposes of this DSDD, and for the EIS, with respect to state environmental review requirements. The contact person for St. Joseph is listed below: Judy Weyrens City Administrator City of St. Joseph 25 College Avenue North St. Joseph, MN 56374-0668 (320) 363-7201 jweyrens@cityofstj oseph. com 5.0 ALTERNATIVES TO BE STUDIED IN THE DEIS In addition to the No-Build Alternative, three Build Alternative alignments will be evaluated in the Tier I DEIS. A final decision regarding the number of alternatives will be made based on input received from the public and reviewing agencies during. the scoping period, and any additional studies, if necessary. The alternatives currently proposed to be studied in the Tier I DEIS are illustrated in Figure 1. 5.1 No Build Alternative Under the No Build Alternative, no improvements other than routine roadway maintenance to existing roadways within the project area would be implemented. The. No Build Alternative will be carried forward into the Tier I DEIS as per NEPA and MEPA regulations as a baseline for comparison of the other Tier I DEIS alternatives. St. Joseph North Corridor - 3 - February 2009 Draft Scoping Decision Document r Y f' -_ w e ~ c ~ ~ i ! U a ~. ~ .m o i LL ~ ~ I ~ [ t tJ N U , J, ~_ t ~ ICI Z .._ c»_:- _...._.____._ _.__ ¢ f..~.:. ~i~ _..__.. f "O M r' ~ ~th9 a and U~0 r f a a N N ~ ~. M Q Vl \ ~ C ~~ C O ., m ~ ~ a ~ ~ In / 'c ^~ r ._ ~ t' ~MI ~ ~ ojl ~ M''' `I r p J ~ ~~ ~ N ~ ~ ~av~P ~a oy lil N ..~ ~ it any WSG h N anylsl6 r~_~ >` > i m U I~,i, ~ •~;,~ t 'aiy ~ ~ .~"' j m N lil _ L ~ ~ f'..s IO PoOM~% ~~ Q ~ ~ ~ ~ qq ~~I II ~ Q ~ 'b 2(IE nd ao y -~ k ,, ~ ~ ~ f an ~ U ~ ~ II L any puZOl fi ~ 0 ~a~'•d~ ,!, Z any Pa£04 9PJE,~ 1, ~~~ Y,I,I ~ ~~ a M x %jm~ 1, ~ ~ ~ ~- ~ a ~ ~ ~ ta~ ! ~ '-' O~ ii ~ Q ~ ~. ~ ~ p~ /a~ * 1._.. ill ~~ ~~ __. any 4lS G L ,~~~ ~ ~~a GI ~~~_ ~ _' ~ .,~ ~ -_..y~/i7 / 'iii ~ -- ~. ~~d ~~ ~~ ~~ ~ N o ~ `a ~e~w~ s~ : ~ e J\\~e~ ~ y Go\\eg Jun~P .. f I F.` pew C IPY~YAYYOry aoC151505f1\tC9SV e'N1'f .~ c E U O O c 0 U N C .Q O [n m D o` ;a C 0 a ~i' z z o t d in 0 0 .~' in U 5.2 Build Alternative Alignments The alternatives described below correspond to the alignments shown in Figure 1. These alignments represent efforts to identify corridors that address the transportation need for the project, are consistent with evaluation criteria identified in the St. Joseph North Corridor and CSAII 2 Realignment Corr°idor Study (connectivity and spacing objectives, consistency with regional and local plans; and avoid or minimize social, economic and environmental impacts with respect to known resources within the study area. All three Build Alternatives start at the same paint, where the proposed CSAH 2 Realignment Project terminates between CSAH 75 and the Lake Wobegon Trail, just outside the northwestern city limits of St. Joseph (Figure 2). From CSAH 3, all Alternatives travel in an easterly direction for approximately two miles until their easterly terminus at CSAH 133. 5.2.1 Alternative 1 Alternative 1 begins to curve east just past the Lake Wobegon Trail. It continues in a nearly due cast direction until its terminus at CSAH 133. 5.2.2 Alternative 2 Alternative 2 follows the same route as Alternative 1. Approximately 0.1 miles east of its intersection with existing CSAH 2, it splits to the north of Alternative L It rejoins the alignment of Alternative I approximately 0.1 miles west of its termination at CSAH 133. Alternative 2 follows this alignment in order to minimize impacts to a wetland complex in the area 5.2.3 Alternative 3 In response to public feedback following the Corridor Study, Alternative 3 was created in order to minimize severing properties within the study area.. It follows a more northerly route than Alternatives 1 and 2. Its alignment is approximately 1,000 feet north of Alternative 1 for most of its length. It joins Alternative 2 at the northern-most point, approximately 0.25 miles east of existing CSAH 2. 6.0 ISSUES TO BE ADDRESSED IN THE DEIS Based on information received during the scoping study, the following areas of potential environmental concern will be studied in detail in the Tier I DEIS, including preparation of a special study (separate report) for each issue. Cultural Resources This is identified as an issue requiring special study because of the expertise required to identify and evaluate potential impacts to cultural resources in the project area. St. Joseph North Corridor - 5 - February 2009 Draft Scoping Decision Document • Traffic Operations Studying and forecasting traffic operations in the project area are critical to understanding how the transportation network may function over the next 20 years -with or without the construction of the North Corridor -and is the foundation for understanding the project's purpose and need. Environmental Quality Board scoping directions require evaluation of social, economic, and environmental issues to be categorized as "issues of major concern" and "issues of moderate concern." The distinction between these categories is not always clear in projects like the North Corridor, in which all alternatives share a close physical proximity to each other. The Project Management Team identified the following as issues of major concern for the project at the Tier I level, since impacts related to these issues could have a substantial influence on selection of the Preferred Corridor Alternative: • Public Park, Recreational, Wildlife Management, and Section 4(f)/6(f) Lands • Vegetation/Cover Types/Areas of Biodiversity • Fish and Wildlife • Threatened and Endangered Species • Wetlands • Floodplains/Water Body Modifications • Surface Water/Water Quantity and Quality Management • Land Use • Farmlands • Right of Way Acquisition and Relocation • Environmental Justice/Social and Neighborhood Impacts/Community Facilities Impacts • Hazardous Materials, Contaminated Properties • Cumulative Impacts The Tier I DEIS will provide detailed analysis of impact for each of these environmental concerns, but no separate report. The following issues are of moderate concern for the project at the Tier 1 level. Issues of moderate concern are those whose impacts are not expected to vary greatly between Build Alternatives, and therefore are not anticipated to play as substantial a role in the identification of the Preferred Corridor Alternative. As a general rule, those issues identified as of moderate concern are typically expected to be impacted more by the nature of the proposed project (e.g., number of lanes, general length of roadway) than by the precise location of the project alignment. St. Joseph North Corridor - 6 - February 2009 Draft Scoping Decision Document Traffic Noise • Air Quality • Intermodal Transportation (includes Bicycle/Pedestrian Movement and Handicapped Accessibility, Truck Traffic, Rail, Transit) • Construction Impacts Erosion Control and Slope Stability Economic Impacts Excess Materials • Groundwater, Geology, and Soils • Utility Locations Visual Impacts/Quality • Indirect Impacts • Irreversible and Irretrievable Commitment of Resources • Relationship of Local Short-Term Uses versus Long-Term Productivity 7.0 ISSUES NOT TO BE ADDRESSED IN THE DEIS The following areas of environmental concern are not relevant to this study area and will not be discussed in the EIS. • Coastal Zones: There are no coastal zones in the project area. • Wild and Scenic Rivers: There are no Wild and Scenic Rivers within the project area. • Critical Areas: There are no designated critical areas in the project area 8.0 PUBLIC AND AGENCY INVOLVEMENT The City of St. Joseph, as project proposers, along with members of the Project Management Team (PMT), will engage community organizations, area property owners, residents, business owners, and local, county, regional, state and federal agencies in the development of the proposed project. Public and agency involvement is described below. 8.1 Project Management Team The PMT consists of staff from the City of St. Joseph, St. Joseph Public Works, Stearns County Public Works, St. Cloud APO, Mn/DOT District 3, and St. Joseph Township. The role of the PMT is to provide direction to advance the proposed project through this scoping study and the environmental review process. St. Joseph North Corridor - 7 - February 2009 Draft Scoping Decision Document 8.2 Cooperating and Participating Agencies The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) establishes a new environmental review process for transportation projects developed as environmental impact statements. These requirements are intended to promote efficient project management by lead agencies and enhanced opportunities for coordination with the public and with other federal, state, local, and tribal government agencies during the project development process. To enhance interagency coordination and ensure that issues of concern are identified, SAFETEA-LU creates a new category of involvement in the environmental review process termed "participating agency." The intent of the new category is to encourage governmental agencies at any level with an interest in the proposed project to be active participants in the NEPA evaluation. The following federal agencies were invited by FHWA to serve as cooperating agencies for the project. • U.S. Army Corps of Engineers (COE) • U.S. Environmental Protection Agency (EPA) • U.S. Fish and Wildlife Service (USFWS) • U.S. Department of Agriculture, Natural Resources Conservation Service (MRCS) The following state, and local agencies were invited by FHWA to serve as participating agencies for the project. State Agencies • Minnesota Pollution Control Agency (MPCA) • Minnesota Department of Agriculture • Minnesota Board of Soil and Water Resources (BWSR) • Minnesota State Historic Preservation Office (SHPO) • Minnesota Department of Transportation (District 3) • Minnesota Department of Natural Resources (MnDNR) Local A eg ncies • Sauk River Watershed District • Stearns County Environmental Services • St. Joseph Township • St. Wendel Township • City of St. Cloud St. Joseph North Corridor - 8 - February 2009 Draft Scoping Decision Document The role of Cooperating and Participating Agencies as part of the North Corridor environmental review and project development process is documented in the Agency and Public Involvement Plan in Appendix A of the Scoping Document. 8.3 Public Meetings The Corridor Study process sought to promote effective decision making by fostering a cooperative spirit and building trusting relationships among state, regional, and local partners, and the public. The various study partners worked together to develop a corridor plan that improved safety and mobility, addressed environmental concerns, and respected community values. Focus group meetings were held in February 2006 and July 2006. The focus groups, which were composed of local officials .and residents, provided input on needs, issues, constraints, and opportunities early in the study process, and again on alignment alternatives during the evaluation process. Open house meetings were also held in February 2006 and July 2006. Open house meetings were held at the St. Joseph .Fire Hall. These meetings provided opportunities for the general public to participate in the corridor planning process. Feedback from citizens was recorded and provided to the Corridor Advisory Committee (CAC) for consideration. A public scoping meeting will be held during the 30-day public comment period for the SD. The public scoping meeting will present the findings of the SD and the draft SDD. Comments received at the scoping meeting will be considered in the final SDD. Open house meetings and public hearings will also be held during the Tier 1 DEIS phase of the environmental review process. 8.4 Project Website A part of the City of St. Joseph website was used to disseminate important study information, including information from the Corridor Study process such as focus group/public meeting materials, CAC agendas, and CAC meeting summaries. Public meeting notices are also published on the project website. 9.0 PERMITS AND APPROVALS 9.1 Permits and Approvals Required A list of applicable permits and approvals anticipated for the proposed North Corridor project is provided in Table 1. St. Joseph North Corridor - 9 - February 2009 Draft Scoping Decision Document TABLE 1 ANTICIPATED PERMITS AND APPROVALS REQUIRED AGENCY PERMIT/APPROVAL Federal Advisory Council on Historic Preservation Section 106 of the National Historic Preservation Act-Memorandum of A eement if needed Federal Highway Administration EIS A royal (draft and final for both Tiers) • EIS Record of Decision ROD for both Tiers • Section 4(f) Evaluations (draft and final for both Tiers if needed U.S. Army Corps of Engineers Section 404 of the Clean Water Act-Permit fill in waters of the U.S.) • Section 10 of the Rivers and Harbors Act- Permit (if needed for construction of bridge over Watab River State Minnesota Department of Transportation EIS A royal (draft and final for both Tiers • Section 106 of the National Historic Preservation Act-Cultural Resources Determination • Section 106 of the National Historic Preservation Act-Memorandum of A eement (if needed) • Plan Review Minnesota Department of Natural Resources Public Waters Work Waters Permit (if needed) • Mussel Relocation Permit (if needed for construction of brid e over Watab River Minnesota Pollution Control Agency Section 401 Water uali Certification • NPDES Permit Minnesota State Historic Preservation Office Section 106 of the National Historic Preservation Act-Cultural Resources Concurrence • Section 106 of the National Historic Preservation Act-Memorandum of A eement if needed Local City of St. Joseph • Scoping Decision Document • EIS Approval (draft and final for both Tiers) • EIS Adequacy Determination Stearns Count Wetland Conservation Act (WCA Stearns County Soil and Water Conservation Coordination of Grading and Drainage Plans District St. Joseph North Corridor - IO - February 2009 Draft Scoping Decision Document