Council Agenda Item
MEETING DATE:
May 1, 2014
AGENDA ITEM:
2014 Main Pump Station and Collection System Improvements
SUBMITTED BY:
Randy Sabart
BOARD/COMMISSION/COMMITTEE RECOMMENDATION:
PREVIOUS COUNCIL ACTION:
Approved plans and specs and authorized advertisement for bids.
BACKGROUND INFORMATION:
The City received 2 bids for main pump station and collection
system improvements at the opening on April 16, 2014. A complete tabulation and recommendation for
award is attached.
BUDGET/FISCAL IMPACT:
Base Bid $1,613,123.00
Alternate A - RV Dump Station $8,460.00
TOTAL BASE BID PLUS ALTERNATE $1,621,583.00
The low bid amount will exceed the budgeted and bonded project total by $83,753. The project team
reviewed the project and has identified several scope of work items that could potentially be delayed and
removed from the project to help bring the project closer to the budget.
AMOUNT
POTENTIAL SCOPE REDUCTION ITEM DESCRIPTION EXCLUDED
Chlorine contact tank demolition $5,000.00
Removal and replacement of sanitary sewer east of existing RV dump manhole $17,112.00
Removal and replacement of 4-inch water main east of existing RV dump manhole $4,914.00
Turf establishment associated with sanitary sewer and water main exclusion $1,983.00
Placement of class 5 and class 2 gravel on area to the northwest of existing pavement $23,434.00
Pavement for turn-around area for trucks and RVs – use gravel surfacing instead $9,240.00
TOTAL: $61,683.00
We discussed removal of these items from the project contract with the Contractor, and the Contractor
would be willing to do so. Therefore, upon award of the contract a deduct change order could be executed
to remove the items listed above from the total contract price.
Provided the City is agreeable to the low bid amount or the proposed reduced scope of work, we are not
aware of any reason the project should not be awarded to the low bidder.
ATTACHMENTS:
Recommendation to Award and Bid Tabulation
REQUESTED COUNCIL ACTION:
Recommendation to Award is attached.
P:\PT\S\STJOE\common\D39 Req Council Action\2014\126869 Recommend 050114.doc
April 30, 2014 RE: St. Joseph, Minnesota
2014 Main Pump Station and Collection
System Improvement
SEH No. STJOE 126869 7
Honorable Mayor and Members of the City Council
c/o Judy Weyrens, Administrator
City of St. Joseph
25 College Avenue North
PO Box 668
St. Joseph, MN 56374-0668
Dear Mayor and Members of the City Council:
Bids were opened in the City Hall at 11:00 a.m. on Wednesday, April 16, 2014, for the above-referenced
improvement. A complete tabulation of bids is enclosed. The low bid was submitted by Geislinger & Sons.
Base Bid $1,613,123.00
Alternate A - RV Dump Station $8,460.00
TOTAL BASE BID PLUS ALTERNATE $1,621,583.00
The low bid amount will exceed the budgeted and bonded project total by $83,753. The project team
reviewed the project and has identified several scope of work items that could potentially be delayed and
removed from the project to help bring the project closer to the budget.
AMOUNT
POTENTIAL SCOPE REDUCTION ITEM DESCRIPTION EXCLUDED
Chlorine contact tank demolition $5,000.00
Removal and replacement of sanitary sewer east of existing RV dump manhole $17,112.00
Removal and replacement of 4-inch water main east of existing RV dump manhole $4,914.00
Turf establishment associated with sanitary sewer and water main exclusion $1,983.00
Placement of class 5 and class 2 gravel on area to the northwest of existing pavement $23,434.00
Pavement for turn-around area for trucks and RVs – use gravel surfacing instead $9,240.00
TOTAL: $61,683.00
We di
scussed removal of these items from the project contract with the Contractor, and the Contractor
would be willing to do so. Therefore, upon award of the contract a deduct change order could be
executed to remove the items listed above from the total contract price.
Provided the City is agreeable to the low bid amount or the proposed reduced scope of work, we are not
aware of any reason the project should not be awarded to the low bidder.
Engineers | Architects | Planners | Scientists
Short Elliott Hendrickson Inc., 1200 25th Avenue South, P.O. Box 1717, St. Cloud, MN 56302-1717
SEH is 100% employee-owned | sehinc.com | 320.229.4300 | 800.572.0617 | 888.908.8166 fax
Honorable Mayor and Members of the City Council
April 30, 2014
Page 2
Please contact me if you have any questions.
Sincerely,
Colin Marcusen, PE
Project Engineer
djg
Enclosure
c: Randy Sabart, SEH (w/enclosure)
Terry Thene, City of St. Joseph (w/enclosure)
p:\pt\s\stjoe\126869\1-gen\14-corr\l city award 043014.docx
Page 1
TABULATION OF BIDS
STJOE 126869
PROJECT NO.:
2014 MAIN PUMP STATION AND COLLECTION SYSTEM IMPROVEMENTS
NAME:
CITY OF ST. JOSEPH, MINNESOT
OWNER: A
WEDNESDAY, APRIL 16, 2014 11:00 AM
BID DATE: @
12
INC.MAGNEY CONSTRUCTION
ENGINEER'S ESTIMATEGEISLINGER & SONS
,
ITEMQUANTITYUNITDESCRIPTIONUNIT COSTTOTALUNIT COSTTOTALUNIT COSTTOTAL
BASE BID
GENERAL
11.00LUMP SUMMISCELLANEOUS PROJECT $20,000.00$20,000.00$40,000.00$40,000.00$30,000.00$30,000.00
DEWATERING
21.00LUMP SUMMOBILIZATION$50,000.00$50,000.00$60,000.00$60,000.00$110,000.00$110,000.00
31.00LUMP SUMTRAFFIC CONTROL $25,000.00$25,000.00$5,000.00$5,000.00$14,000.00$14,000.00
41.00EACHROCK CONSTRUCTION $750.00$750.00$1,000.00$1,000.00$1,000.00$1,000.00
ENTRANCE
5250.00LIN FTREMOVE WATER MAIN$4.00$1,000.00$2.00$500.00$2.00$500.00
$3.00$1,380.00$5.00$2,300.00$2.00$920.00
6460.00LIN FTREMOVE SANITARY SEWER
73,310.00SQ YDREMOVE BITUMINOUS $3.00$9,930.00$4.00$13,240.00$2.50$8,275.00
PAVEMENT
8130.00SQ YDREMOVE CONCRETE $6.00$780.00$6.00$780.00$10.00$1,300.00
PAVEMENT
91.00LUMP SUMREMOVE/ABANDON $8,000.00$8,000.00$5,000.00$5,000.00$8,500.00$8,500.00
CHLORINE CONTACT TANK
101.00LUMP SUMREMOVE METERING $3,000.00$3,000.00$5,000.00$5,000.00$4,000.00$4,000.00
CHANNEL
111.00LUMP SUMREMOVE DIVERSION $3,000.00$3,000.00$6,500.00$6,500.00$3,500.00$3,500.00
MANHOLE
121.00LUMP SUMREMOVE UNDERGROUND $15,000.00$15,000.00$2,500.00$2,500.00$3,900.00$3,900.00
FUEL STORAGE TANK
132.00EACHREMOVE BOLLARD$200.00$400.00$50.00$100.00$105.00$210.00
141.00EACHREMOVE RV DUMP SIGN$200.00$200.00$50.00$50.00$50.00$50.00
151.00EACHREMOVE CURB STOP$250.00$250.00$25.00$25.00$50.00$50.00
161.00EACHREMOVE GATE VALVE & BOX$400.00$400.00$50.00$50.00$82.00$82.00
171.00EACHREMOVE YARD HYDRANT$300.00$300.00$350.00$350.00$50.00$50.00
183.00EACHREMOVE SANITARY SEWER $1,000.00$3,000.00$350.00$1,050.00$800.00$2,400.00
MANHOLE
19115.00LIN FTSAWING CONCRETE $4.00$460.00$6.00$690.00$5.00$575.00
PAVEMENT
20200.00LIN FTSAWING BITUMINOUS $3.00$600.00$4.00$800.00$3.50$700.00
PAVEMENT
21175.00LIN FTTEMPORARY $5.00$875.00$5.00$875.00$7.00$1,225.00
CONSTRUCTION FENCE
22140.00LIN FTABANDON WATER MAIN$12.00$1,680.00$6.00$840.00$9.00$1,260.00
23765.00LIN FTABANDON SANITARY SEWER$18.00$13,770.00$10.00$7,650.00$10.00$7,650.00
$500.00$500.00$500.00$500.00$250.00$250.00
241.00LUMP SUMABANDON YARD HYDRANTS
AND PIPING - NO GROUT
25290.00LIN FTSALVAGE CHAIN LINK FENCE$15.00$4,350.00$10.00$2,900.00$3.50$1,015.00
$350.00$350.00$250.00$250.00$250.00$250.00
261.00EACHSALVAGE HYDRANT
ASSEMBLY
CONTROL BUILDING AND WET WELL
271.00LUMP SUMEXISTING AND PROPOSED $109,000.00$109,000.00$180,000.00$180,000.00$335,300.00$335,300.00
WET WELL IMPROVEMENTS
281.00LUMP SUMWET WELL DEWATERING$110,000.00$110,000.00$75,000.00$75,000.00$35,000.00$35,000.00
291.00LUMP SUMGENERATOR REMOVAL AND $1,500.00$1,500.00$2,500.00$2,500.00$2,000.00$2,000.00
SALVAGE
Short Elliott Hendrickson Inc., 1200 25th Avenue South, P.O. Box 1717, St. Cloud, MN 56302-1717
SEH is an equal opportunity employer | www.sehinc.com | 320.229.4300 | 800.572.0617 | 888.908.8166 fax
4/17/2014
Page 2
TABULATION OF BIDS
STJOE 126869
PROJECT NO.:
2014 MAIN PUMP STATION AND COLLECTION SYSTEM IMPROVEMENTS
NAME:
CITY OF ST. JOSEPH, MINNESOT
OWNER: A
WEDNESDAY, APRIL 16, 2014 11:00 AM
BID DATE: @
12
INC.MAGNEY CONSTRUCTION
ENGINEER'S ESTIMATEGEISLINGER & SONS
,
ITEMQUANTITYUNITDESCRIPTIONUNIT COSTTOTALUNIT COSTTOTALUNIT COSTTOTAL
301.00LUMP SUMBUILDING SHELL UPGRADES$5,000.00$5,000.00$3,000.00$3,000.00$3,000.00$3,000.00
3130.00LIN FTCONCRETE CRACK SEALING $50.00$1,500.00$150.00$4,500.00$100.00$3,000.00
BY PRESSURE INJECTION
321.00LUMP SUMPUMP LIFTING HOOK $2,000.00$2,000.00$1,200.00$1,200.00$150.00$150.00
REPLACEMENT
331.00EACHWATER HEATER $1,500.00$1,500.00$1,500.00$1,500.00$5,000.00$5,000.00
REPLACEMENT
341.00LUMP SUMCONTROL BUILDING $15,000.00$15,000.00$15,000.00$15,000.00$10,230.00$10,230.00
COATINGS
351.00LUMP SUMBUILDING VENTILATION$8,000.00$8,000.00$3,500.00$3,500.00$23,000.00$23,000.00
361.00LUMP SUMBUILDING PLUMBING $8,000.00$8,000.00$2,500.00$2,500.00$5,500.00$5,500.00
IMPROVEMENTS - WATER
371.00LUMP SUMGENERAL ELECTRICAL $1,000.00$1,000.00$3,500.00$3,500.00$3,300.00$3,300.00
DEMOLITION
381.00LUMP SUMSITE LIGHTING POLE$2,500.00$2,500.00$5,000.00$5,000.00$5,500.00$5,500.00
391.00LUMP SUMINSTRUMENTATION AND $79,000.00$79,000.00$63,000.00$63,000.00$65,000.00$65,000.00
CONTROLS
401.00LUMP SUMBUILDING ELECTRICAL AND $5,000.00$5,000.00$125,000.00$125,000.00$128,500.00$128,500.00
CONTROLS
411.00LUMP SUM175 KW GENERATOR WITH $74,000.00$74,000.00$73,000.00$73,000.00$77,000.00$77,000.00
WEATHERPROOF
421.00LUMP SUMGENERATOR PAD AND $5,500.00$5,500.00$5,000.00$5,000.00$1,500.00$1,500.00
FOUNDATION - INCLUDES
431.00LUMP SUMELECTRICAL SERVICE $10,900.00$10,900.00$10,000.00$10,000.00$10,000.00$10,000.00
ENTRANCE
442.00LUMP SUMPANEL BOARDS$8,350.00$16,700.00$8,000.00$16,000.00$4,500.00$9,000.00
SCREENING CHANNEL
451.00LUMP SUMBAR SCREEN STRUCTURE $21,000.00$21,000.00$25,000.00$25,000.00$21,300.00$21,300.00
MODIFICATIONS
STREET
464,100.00CU YDCOMMON EXCAVATION (P) $8.00$32,800.00$10.00$41,000.00$6.50$26,650.00
(CV)
471,000.00CU YDWET WELL SUBGRADE $8.00$8,000.00$8.00$8,000.00$18.00$18,000.00
EXCAVATION
481,970.00CU YDAGGREGATE BASE PLACED $20.00$39,400.00$22.00$43,340.00$24.00$47,280.00
(CV)(P)
CLASS 5
$22.00$4,400.00$22.00$4,400.00$35.00$7,000.00
49200.00CU YDAGGREGATE BASE PLACED
CLASS 2 (CV)(P)
50435.00TONWEARING COURSE MIXTURE$70.00$30,450.00$74.00$32,190.00$80.00$34,800.00
51680.00TONNON WEARING COURSE $65.00$44,200.00$72.00$48,960.00$77.00$52,360.00
MIXTURE
52225.00GALBITUMINOUS MATERIAL FOR $2.50$562.50$3.00$675.00$2.75$618.75
TACK COAT
53750.00SQ YDGEOTEXTILE FABRIC, $4.00$3,000.00$3.00$2,250.00$5.00$3,750.00
MNDOT TYPE 6
54185.00SQ YD6" CONCRETEPAVEMENT$35.00$6,475.00$75.00$13,875.00$90.00$16,650.00
55550.00LIN FTCHAIN LINK FENCE$18.00$9,900.00$18.00$9,900.00$20.00$11,000.00
561.00EACH12' WIDE DOUBLE LEAF $2,000.00$2,000.00$1,500.00$1,500.00$2,000.00$2,000.00
SWING GATE
571.00EACH16' WIDE ROLLING VEHICLE $4,000.00$4,000.00$4,000.00$4,000.00$3,500.00$3,500.00
GATE
581.00EACH24' WIDE ROLLING VEHICLE $5,000.00$5,000.00$7,500.00$7,500.00$4,500.00$4,500.00
GATE
5910.00EACHBOLLARD$350.00$3,500.00$550.00$5,500.00$275.00$2,750.00
Short Elliott Hendrickson Inc., 1200 25th Avenue South, P.O. Box 1717, St. Cloud, MN 56302-1717
SEH is an equal opportunity employer | www.sehinc.com | 320.229.4300 | 800.572.0617 | 888.908.8166 fax
4/17/2014
Page 3
TABULATION OF BIDS
STJOE 126869
PROJECT NO.:
2014 MAIN PUMP STATION AND COLLECTION SYSTEM IMPROVEMENTS
NAME:
CITY OF ST. JOSEPH, MINNESOT
OWNER: A
WEDNESDAY, APRIL 16, 2014 11:00 AM
BID DATE: @
12
INC.MAGNEY CONSTRUCTION
ENGINEER'S ESTIMATEGEISLINGER & SONS
,
ITEMQUANTITYUNITDESCRIPTIONUNIT COSTTOTALUNIT COSTTOTALUNIT COSTTOTAL
60650.00LIN FTFURNISH & INSTALL 2" PVC $13.00$8,450.00$5.00$3,250.00$5.00$3,250.00
UTILITY CONDUIT
6170.00LIN FTFURNISH & INSTALL 4" PVC $15.00$1,050.00$10.00$700.00$27.00$1,890.00
UTILITY CONDUIT
624.00HOURSTREET SWEEPING$125.00$500.00$115.00$460.00$115.00$460.00
SANITARY SEWER
63160.00LIN FT10" PVC SANITARY SEWER, $35.00$5,600.00$100.00$16,000.00$52.00$8,320.00
SDR35, WITH TYPE 2
6428.00LIN FT24" PVC SANITARY SEWER, $45.00$1,260.00$285.00$7,980.00$110.00$3,080.00
SDR35, WITH TYPE 2
65186.00LIN FT42" CCFRPM SN18 SANITARY $220.00$40,920.00$250.00$46,500.00$258.00$47,988.00
SEWER WITH TYPE 2
66189.00LIN FT42" CCFRPM SN72 SANITARY $215.00$40,635.00$270.00$51,030.00$280.00$52,920.00
SEWER WITH TYPE 1
67120.00LIN FT2" PVC SCH 80 SANITARY $20.00$2,400.00$50.00$6,000.00$33.00$3,960.00
SEWER FORCE MAIN
68180.00LIN FTJACK & BORE 42" SANITARY $800.00$144,000.00$1,000.00$180,000.00$1,000.00$180,000.00
SEWER
691.00LUMP SUMJACKING PIT DEWATERING$26,500.00$26,500.00$25,000.00$25,000.00$20,000.00$20,000.00
70808.00LIN FTCLEAN & TELEVISE $1.25$1,010.00$3.00$2,424.00$1.25$1,010.00
SANITARY SEWER
71825.00SQ YD2" INSULATION$25.00$20,625.00$17.00$14,025.00$20.00$16,500.00
722.00EACH60" FRP SANITARY MANHOLE$20,000.00$40,000.00$15,000.00$30,000.00$12,650.00$25,300.00
731.00EACH72" FRP SANITARY MANHOLE$25,000.00$25,000.00$17,000.00$17,000.00$15,400.00$15,400.00
741.00EACH84" FRP SANITARY MANHOLE$28,000.00$28,000.00$20,000.00$20,000.00$19,800.00$19,800.00
751.00EACHPRECAST SANITARY $3,000.00$3,000.00$7,500.00$7,500.00$5,700.00$5,700.00
MANHOLE
761.00EACHCONNECT TO EXISTING $750.00$750.00$2,500.00$2,500.00$1,100.00$1,100.00
SANITARY FORCE MAIN
771.00EACHCONNECT TO EXISTING $750.00$750.00$3,000.00$3,000.00$1,650.00$1,650.00
SANITARY SEWER
781.00EACHCONNECT TO EXISTING $1,000.00$1,000.00$5,000.00$5,000.00$3,250.00$3,250.00
MANHOLE
791.00LUMP SUMBYPASS PUMPING$40,000.00$40,000.00$100,000.00$100,000.00$125,000.00$125,000.00
WATER MAIN
80400.00LIN FT6" WATER MAIN - DUCT IRON $30.00$12,000.00$40.00$16,000.00$48.00$19,200.00
CL 52
811.00EACHHYDRANT$3,500.00$3,500.00$4,500.00$4,500.00$4,100.00$4,100.00
822.00EACH6" GATE VALVE AND BOX$1,500.00$3,000.00$1,500.00$3,000.00$1,400.00$2,800.00
831.00EACHYARD HYDRANT WITH 4X4 $1,200.00$1,200.00$350.00$350.00$525.00$525.00
TREATED POST
841.00EACHCONNECT TO EXISTING $700.00$700.00$500.00$500.00$1,300.00$1,300.00
WATER MAIN
851.00EACH2" CORPORATION STOP$300.00$300.00$350.00$350.00$600.00$600.00
861.00EACH1" CORPORATION STOP$275.00$275.00$200.00$200.00$375.00$375.00
871.00EACH2" CURB STOP AND BOX$350.00$350.00$550.00$550.00$850.00$850.00
881.00EACH1" CURB STOP AND BOX$325.00$325.00$240.00$240.00$375.00$375.00
89110.00LIN FT2" TYPE K COPPER PIPE$30.00$3,300.00$50.00$5,500.00$44.00$4,840.00
Short Elliott Hendrickson Inc., 1200 25th Avenue South, P.O. Box 1717, St. Cloud, MN 56302-1717
SEH is an equal opportunity employer | www.sehinc.com | 320.229.4300 | 800.572.0617 | 888.908.8166 fax
4/17/2014
Page 4
TABULATION OF BIDS
STJOE 126869
PROJECT NO.:
2014 MAIN PUMP STATION AND COLLECTION SYSTEM IMPROVEMENTS
NAME:
CITY OF ST. JOSEPH, MINNESOT
OWNER: A
WEDNESDAY, APRIL 16, 2014 11:00 AM
BID DATE: @
12
ENGINEER'S ESTIMATEGEISLINGER & SONS INC.MAGNEY CONSTRUCTION
,
ITEMQUANTITYUNITDESCRIPTIONUNIT COSTTOTALUNIT COSTTOTALUNIT COSTTOTAL
90150.00LIN FT1" TYPE K COPPER PIPE$25.00$3,750.00$40.00$6,000.00$33.00$4,950.00
91150.00SQ YD2" INSULATION$20.00$3,000.00$17.00$2,550.00$22.00$3,300.00
923.00EACHCONNECT TO EX WATER $300.00$900.00$500.00$1,500.00$425.00$1,275.00
SERVICE
93500.00POUNDWATER MAIN FITTINGS$6.00$3,000.00$5.00$2,500.00$7.00$3,500.00
TURF RESTORATION
944.00EACHINLET PROTECTION, $150.00$600.00$175.00$700.00$190.00$760.00
MAINTAINED
95835.00LIN FTSILT FENCE, HEAVY DUTY$2.50$2,087.50$3.00$2,505.00$2.80$2,338.00
9685.00LIN FTBIOROLL BLANKET SYSTEM$5.00$425.00$5.00$425.00$6.00$510.00
971,100.00CU YDSCREENED TOPSOIL $14.00$15,400.00$18.00$19,800.00$21.00$23,100.00
BORROW (LV)
981.60ACRESEEDING$750.00$1,200.00$2,500.00$4,000.00$2,750.00$4,400.00
991.60ACRESEEDING (TEMPORARY)$600.00$960.00$300.00$480.00$330.00$528.00
10096.00POUNDSEED MIXTURE 22-111$2.00$192.00$2.00$192.00$2.00$192.00
101704.00POUNDSEED MIXTURE 25-131$3.50$2,464.00$3.00$2,112.00$2.75$1,936.00
1025,000.00POUNDHYDRAULIC SOIL STABILIZER$2.00$10,000.00$1.00$5,000.00$1.00$5,000.00
103560.00POUNDCOMMERCIAL FERTILIZER$1.00$560.00$1.00$560.00$1.00$560.00
TOTAL BASE BID$1,336,701.00$1,613,123.00$1,799,692.75
ALTERNATE A - RV DUMP STATION
1042.00EACHBOLLARD$350.00$700.00$500.00$1,000.00$275.00$550.00
10520.00LIN FTCURB DESIGN V (6")$10.00$200.00$25.00$500.00$27.00$540.00
1065.00SQ YD6" CONCRETEPAVEMENT$35.00$175.00$100.00$500.00$140.00$700.00
10710.00LIN FT4" PVC SANITARY SEWER, $30.00$300.00$100.00$1,000.00$44.00$440.00
SDR26
1082.00LIN FT4" DI SANITARY SEWER$50.00$100.00$100.00$200.00$55.00$110.00
10922.75SQ FTRV DUMP SIGN, WITH POST$50.00$1,137.50$40.00$910.00$8.00$182.00
1101.00EACHRV DUMP 4" SANITARY $300.00$300.00$600.00$600.00$900.00$900.00
HATCH COVER
1111.00EACHYARD HYDRANT WITH 4X4 $1,200.00$1,200.00$750.00$750.00$500.00$500.00
TREATED POST
11260.00LIN FT1" TYPE K COPPER PIPE$25.00$1,500.00$50.00$3,000.00$25.00$1,500.00
TOTAL ALTERNATE A$5,612.50$8,460.00$5,422.00
SUMMARY
TOTAL BASE BID$1,336,701.00$1,613,123.00$1,799,692.75
TOTAL ALTERNATE A$5,612.50$8,460.00$5,422.00
GRAND TOTAL BID$1,342,313.50$1,621,583.00$1,805,114.75
P:\PT\S\STJOE\126869\Bidding Documents\Bidtab.xls
Short Elliott Hendrickson Inc., 1200 25th Avenue South, P.O. Box 1717, St. Cloud, MN 56302-1717
SEH is an equal opportunity employer | www.sehinc.com | 320.229.4300 | 800.572.0617 | 888.908.8166 fax
4/17/2014
THIS PAGE INTENTIONALLY LEFT BLANK