HomeMy WebLinkAbout[06] Government CenterMEETING DATE:
AGENDA ITEM:
SUBMITTED BY:
Council Agenda Item 6
May 15, 2014
Government Center Bids
Administration
BOARD /COMMISSION /COMMITTEE RECOMMENDATION:
PREVIOUS COUNCIL ACTION: The Council authorized the bidding of the proposed
Government Center with bids opened on April 22, 2014. The Council had previously set a budget of 4.4
— 4.5 M for the project.
BACKGROUND INFORMATION: The City utilized the services of a Construction Manager
throughout the process. Therefore, when the project was bid, the City was not seeking a general
contractor; rather, the bidding was for each component. RA Morton serves in the role of the general
contractor and coordinates all the contracts and subs.
BUDGET /FISCAL IMPACT:
ATTACHMENTS: Request for Council Action
Cover Letter RA Morton
Summary of Bids
Full Bid Summary with alternates
Summary of Alternates
THIS PAGE INTENTIONALLY LEFT BLANK
wrtoltl-
CONSTRUCTION MANAGERS
April 28, 2014
City of St. Joseph
Attn: Judy Weyrens, City Administrator
Dear Ms. Weyrens,
3315 Roosevelt Road • Suite 100
St. Cloud, MN 56301
Bus 320.251.0262
Fax 320.251.5749
www.ramorton.com
Bids for the St. Joseph Government Center project were due and opened on April 22, 2014 at
2:00 pm. This was a public opening attended by many local and regional contractors.
The planning, design, estimating and bid process was a collaborative effort between the City
Facilities Committee, Administration, HMA Architects, Design Tree Engineers, and R.A. Morton,
Construction Managers. The large majority of the construction work will be completed by local
area contractors.
The results of this aggressive Bid Package were favorable and include the following highlights:
• 36 independent sections were established and bid.
• 329 local and regional contractors were directly contacted to inform them of the project
and request bids for the project.
• 14 independent builder's exchanges were informed of the project.
• 238 contractors expressed interest in bidding the project.
• 117 separate bids were collected and opened at bid opening.
• 11 Alternates were bid to identify specific costs of value engineering ideas.
Please see the attached handouts for bid results and overall project detail.
a
By utilizing a Construction Management bid process, exact costs by bid section have been
obtained to verify the true cost of work as specified. We are very pleased with the level of local
contractor interest and in the quality of the contractors who submitted low bids. The timing of
this project has been extremely good and the City of St. Joseph is getting a great value.
The next step in the process is to pre -award interview the apparent low bid contractors to
confirm their bid amount and construction schedule. We anticipate there will be some
contracts awarded to the second low contractors due to the selection of alternates or
confirmation of bid completeness.
We are very excited about these results and look forward to the continuation of construction.
Sincerely,
Preston Euerle
President /CEO
Cc: HMA Architects
Design Tree Engineers
S.E.H. Engineers
Preliminary Bid Recap
JOB NAME: St. Joseph Government Center
ARCHITECT: HMA Architects Ltd
BID DATE: Arpil 22, 2014 (aD- 2:00 p.m.
LOCATION: St. Joseph MN
SIZE:
Apparent Low Bid w/ Alt.
Contractor
Name
Bi
DESCRIPTION
G
Phone Expense
$ 810
Allowance
G
Technology
$ 900
Allowance
G
Temporary Office
$ 3,600
Allowance
G
Temporary Storage
$ 990
Allowance
G
Temporary Toilet
$ 2,115
Allowance
G
Temporary Electricity
$ 4,050
Allowance
G
Temporary Heat
$ 16,200
Allowance
G
Temporary Fence and Gate
$ 7,600
Allowance
G
Teardown
$ 3,700
Allowance
G
Survey Construction
$ 1,500
Allowance
G
Testing
$ 9,500
Allowance
G
Construction Supplies Safety
$ 720
Allowance
G
Construction Supplies
$ 810
Allowance
G
Construction Signage
$ 1,200
Allowance
G
Snow Removal
$ 750
Allowance
G
Hourly Workers
$ 6,500
Allowance
G
Dumpsters General
$ 5,700
Allowance
G
Equipment Rental
$ 1,200
Allowance
G
Cleanup Continuous
$ 200
Allowance
G
Cleanup Final
$ 3,850
Allowance
G
Plan Printing
$ 7,500
Allowance
G
Overhead
$ 2,800
Allowance
G
Job Closeout
$ 1,200
Allowance
3
Concrete
$ 182,701
K. Johnson Construction, Inc.
3
Precast Concrete
$ 40,710
County Materials Corporation
4
Masonry
$ 289,181
HTH Building and Masonry, Inc.
4
Stone Cladding
$ 56,220
W. Gohman Construction Co. dba Artistic Stone and Concrete
5
Steel Erection
$ 46,950
Max Steel
5
Steel Fabrication
$ 88,375
K & K Fabrication, Inc.
Preliminary Bid Recap
JOB NAME: St. Joseph Government Center
ARCHITECT: HMA Architects Ltd
BID DATE: Arpil 22, 2014 (D_ 2:00 p.m.
LOCATION: St. Joseph MN
SIZE:
Apparent Low Bid w/ Alt.
Contractor
Name
B
DESCRIPTION
5
Steel Erection & Fabrication
-
Not Used - Combinatiion Bid was higher than individual bids
6
Carpentry
$ 72,442
Yamry Construction
6
Casework
$ 118,882
Interior Components Group
7
Foamed -In -Place Insulation
$ 11,975
Simonson Installation
7
Exterior Insulation & Finish System
$ 60,900
Landmark Stucco
7
EPDM Roofing Systems
$ 159,488
Horizon Roofing, Inc.
7
Sealants
$ 9,470
Sunrise Specialty Contracting
8
Doors, Frames & Hardware
$ 68,780
Mid Central Door Co.
8
Overhead Coiling Doors
$ 16,477
St. Cloud Overhead Door Company
8
Aluminum Entrance Systems & Glazing
$ 83,300
East Side Glass Company
9
Metal Framing & Gypsum Wall System
$ 189,530
R & H Drywall, Inc.
9
Tilework
$ 67,772
Mid -State Tile Co., Inc.
9
Acoustical Panel Systems
$ 34,200
Central Minnesota Ceilings, Inc.
9
Flooring Systems
$ 45,670
Hennen Floor Covering
9
Painting and Coating
$ 36,100
Marks Wall Coating
10
Specialties
$ 20,793
Bartley Sales Company, Inc.
10
Operable Panel Partitions
$ 7,502
Hufcor, Inc.
10
Metal Lockers
$ 38,685
Weldon Company, LLC
10
Flag Poles
-
12
Window Shades
$ 6,393
Kustom Blinds & Draperies, Inc.
21
Fire Suppression
$ 26,310
General Sprinkler Corporation
22
Plumbing
-
23
HVAC
-
23
Plumbing & HVAC Combination
$ 426,800
Lake Country Mechanical
26
Electrical, Electronic Safety /Security
$ 345,000
Klein Electric, Inc.
31
Structure Demolition & Earthwork
$ 75,838
Summit Excavating, Inc.
32
Ashpalt Paving
$ 54,965
Omann Brothers Paving, Inc.
32
Irrigation and Landscaping
$ 11,732
Four Seasons Nursery & Landscaping
33
Utilities
$ 40,145
J & B Excavating, Inc. dba Town & Country Excavating
Preliminary Bid Recap
JOB NAME: St. Joseph Government Center
ARCHITECT: HMA Architects Ltd
BID DATE: Arpil 22, 2014 (aD- 2:00 p.m.
LOCATION: St. Joseph MN
SIZE:
Sac & Wac Allowance
-
Apparent Low Bid w/ Alt.
Contractor
Name
Bi
Builders Risk Allowance
DESCRIPTION
33
Exterior Signage Allowance
Comb. Demo, Earthwork & Utilities
-
Not Used - Combinatiion Bid was higher than individual bids
$ 50,000
Allowance
Finance
$ 30,000
Allowance
A &E Fees Per Contract
$ 266,000
HMA Architects
A &E Reimbursable
$ 2,500
HMA Architects
Civil Engineering and Survey
SUBTOTAL
$ 2,816,681
Soil Borings
$ 2,700
CM Fees
$ 231,500
R.A. Morton & Associates, Inc.
Technology & Server Allowance
$ 150,000
Phone System
$ 65,000
Furnishings, Appliances
ESTIMATED TOTAL COST
$ 3,048,181
Commissioning
Sac & Wac Allowance
-
Building Permit Allowance
-
Builders Risk Allowance
-
Exterior Signage Allowance
$ 24,000
Allowance
Office Relocation During Construction A
$ 50,000
Allowance
Finance
$ 30,000
Allowance
A &E Fees Per Contract
$ 266,000
HMA Architects
A &E Reimbursable
$ 2,500
HMA Architects
Civil Engineering and Survey
$ 20,000
S.E.H.
Soil Borings
$ 2,700
Fiber Optic Connection
$ 7,500
Technology & Server Allowance
$ 150,000
Phone System
$ 65,000
Furnishings, Appliances
$ 140,000
Commissioning
-
Other
-
$ 757,700
$ 250,000
$ 50,000
$ 132,150
Preliminary Bid Recap
JOB NAME: St. Joseph Government Center
ARCHITECT: HMA Architects Ltd
BID DATE: Arpil 22, 2014 (aD- 2:00 p.m.
LOCATION: St. Joseph MN
SIZE:
4,238,031
$ 4,500,000
$ (261,969)
Apparent Low Bid w/ Alt.
Contractor
Name
Bi
DESCRIPTION
4,238,031
$ 4,500,000
$ (261,969)
Preliminary Bid Recap
JOBNAIE: S1A#GoumpfAN
suor w
ARCHITECT: HMAk NedsUd
BID DATE: kPil2,20140200om
�kt/rowthe t"
LOCATION: St A# MN
TOTALPRCJECT $ 4,490,119 $ 4298,091
PlojedFAsAvaiIable 4,500,000 4,500,000
ovslhlla ofl It got S j69.8E S 12619691
S J.G,Caea,.:: ,m -C, P<,I 3H
m-Illlll:'
lull 'ES'1Cll��E)�FL___________�
' • '
m-
Illlll :'ICII'" +'•''li�l,.3'L�l�l4'�'
�II___________'
III
'�.
m-h�l'L'MI'1'LL'llS4l•��
'' � II
___________
' � II
' � .
m-'LLW'k44E1:•lltlCJ�
'' II
___________
'' II
' � .
m-�l'lll�7rJ1Wl!�l�A[S�l��'
III
�'
II
��������
� � • �� � ��. � � •. � � �..
m-1
...i i i liilii
i i f • •.i Iii i �.
m-•
�������������®''
14WOW! WLJIICIBYfi7 "h'14Ma;Y'1��141'�It
I������������'
� II
�• � �.
m-Wf1tJIiCMII�!1:19'I'F9W'I'
CVO 7'F7l�llIlE)•EIAIJ������������'
,I
� I .
m�
• "hLP�F74IIrLI'1�Tt74•ll�Ls�
I I
�������������
I I
• �.
m-
l�if' 1' llllk�l' h74•ll�Ls������������E'EllIE'Flll�
' " ' • '
m-WBWI911N1']d'G'�Rl1011LBlll�
" ' 11
���������
II
' II
' , � .II
. • � �
�-'
III
���������'
III
' III
' 'III
1• •ri
-
IiF711' 7• LI��� •J'IIA��!'i'�iEl'J�����������®'
''
1 : : i ', i
-
WII! tl4 'llrJLlSLll:J9W!��������������
' •.'
.-�
III '
�L�l'A'WI
' I I
Ll• Cltllll��Ll
iA' i1 1L1•
I L1t11'llLl•If.'l'lllLl•:YII'iJl
TOTALPRCJECT $ 4,490,119 $ 4298,091
PlojedFAsAvaiIable 4,500,000 4,500,000
ovslhlla ofl It got S j69.8E S 12619691
S J.G,Caea,.:: ,m -C, P<,I 3H
New Government Center City of St. Joseph
Alternate Summary
Alternate No. 1 - Building Exterior Wainscot:
Change architectural precast concrete wainscot to brick with architectural precast concrete wainscot cap. Provide
control joints in brick veneer at 16' 0" on center maximum.
DEDUCT FROM BASE BID $ 42,295.00
Alternate No. 2 - East and West Main Entrance Stone Veneer:
Change stone veneer to decorative concrete masonry units. In room 109 and 119, change stone veneer to
decorative concrete masonry units.
DEDUCT FROM BASE BID $6,610.00
Alternate No. 3 - Stone Cladding Wainscot, Room 109:
Omit stone cladding wainscot and aluminum cap. Provide granite tile base, honed finish. Paint gypsum board.
(Stone window sills to remain).
DEDUCT FROM BASE BID $4,700.00
Alternate No. 4 - Decorative Wood Panels:
Omit decorative wood panels (offset framing and gypsum board to remain). Finish and paint gypsum board. Paint to
be accent paint color.
DEDUCT FROM BASE BID $22,917.00
Alternate No. 5 - Stone Veneer, Room 109 and 119:
Omit stone veneer. Provide granite tile base, honed finish. Paint gypsum board.
DEDUCT FROM BASE BID $2,933.00
Alternate No. 6 - Operable Partition, Room 119:
Omit operable partitions and pass doors. (Pocket doors, supporting track to remain).
DEDUCT FROM BASE BID $12,477.00
Alternate No. 7 - Operable Partition, Room 137:
Omit operable partitions room 137. (Supporting track to remain).
DEDUCT FROM BASE BID $3,765.00
Alternate No. 8 - Lobby Skylight:
Omit translucent skylight. Provide roof joists and metal deck, roof insulation and membrane roofing, infill framing and
gypsum board and interior finishes as indicated on Drawings. Paint gypsum board.
DEDUCT FROM BASE BID $12,926.00
Alternate No. 9 - East Entrance Partial Height Walls:
Omit architectural precast concrete finish, concrete masonry foundation and concrete footings, and related
accessories. Extend grading and landscaping to edges of concrete sidewalk and steps. Extend cast in place
concrete retaining wall as indicated on Detail 3 /A2.1.(Metal handrails to remain).
DEDUCT FROM BASE BID $7,461.00
Alternate No. 10 - Sallyport, APC Wainscot:
Omit construction of Room 172, concrete aprons and protection bollards and related mechanical, fire protection, and
electrical work. Provide exterior wall finish on south wall of Room 171 of EIFS and architectural precast concrete
wainscot similar to Detail 6/A6.3.
DEDUCT FROM BASE BID $46,053.00
Alternate No. 11 - Sallyport, Brick No. 1 Wainscot:
Omit construction of Room 172, concrete aprons and protection bollards and related mechanical, fire protection, and
electrical work. Provide exterior wall finish on south wall of Room 171 of EIFS and Brick No. 1 wainscot similar to
Detail 12/A6.3.
DEDUCT FROM BASE BID $43,345.00