HomeMy WebLinkAbout[04a] Lift Station Payment & Change Order Council Agenda Item 4a MEETING DATE: January 5, 2014 AGENDA ITEM: 2014 Main Pump Station and Collection System Improvements SUBMITTED BY: Randy Sabart BOARD/COMMISSION/COMMITTEE RECOMMENDATION: PREVIOUS COUNCIL ACTION: Application for Payment No. 4 BACKGROUND INFORMATION: Included with the attached application for payment is Change Order No. 1 which addresses the following requested changes:  Replacement of grade adjustment rings, and casting with a sealed casting on existing sanitary sewer manhole on the south side of CR 75: $1,098.25  Privacy slats for new fencing fabric: The fencing fabric for the new fence was ordered and installed by the Contractor with privacy slats already installed in the entirety of the new fabric, though the contract documents called for only a portion of the fencing to have slats installed. Staff would like to keep the slats in place in all of the fencing. The Contractor agreed to split the cost of the slats with the City: $3,045.00 BUDGET/FISCAL IMPACT: $75,261.14 (including Change Order No. 1) ATTACHMENTS: Application for Payment No. 5 and Change Order No. 1 REQUESTED COUNCIL ACTION: Approve Application for Payment No. 5 and Change Order No. 1 This page intentionally left blank OWNER CONTRACTOR SEH APPLICATION FOR PAYMENT NO. 5CONTRACTOR FOR:2014 MAIN PUMP STATION & COLLECTION SYSTEM IMP PROJECT NO.STJOE 126869AGREEMENT DATE:5/1/2014 OWNERCITY OF ST. JOSEPH, MN CONTRACTORGEISLINGER & SONS, INC.FOR WORK ACCOMPLISHED THROUGH:12/12/2014 CONTRACTTHIS PAYMENTWORK TO DATE ITEMUNITUNIT COSTQUANTITYAMOUNTQUANTITYAMOUNTQUANTITYAMOUNTDESCRIPTION BASE BID GENERAL 1LUMP SUM$40,000.001.00$40,000.000.10$4,000.000.95$38,000.00MISCELLANEOUS PROJECT DEWATERING 2LUMP SUM$60,000.001.00$60,000.00$0.000.95$57,000.00MOBILIZATION 3LUMP SUM$5,000.001.00$5,000.00$0.000.90$4,500.00TRAFFIC CONTROL 4EACH$1,000.001.00$1,000.00$0.000.00$0.00 ROCK CONSTRUCTION ENTRANCE 5LIN FT$2.00250.00$500.00$0.0020.00$40.00REMOVE WATER MAIN 6LIN FT$5.00460.00$2,300.00$0.00145.00$725.00 REMOVE SANITARY SEWER 7SQ YD$4.003,310.00$13,240.00$0.003,310.00$13,240.00REMOVE BITUMINOUS PAVEMENT 8SQ YD$6.00130.00$780.00$0.0070.00$420.00REMOVE CONCRETE PAVEMENT 9LUMP SUM$5,000.001.00$5,000.00$0.001.00$5,000.00REMOVE/ABANDON CHLORINE CONTACT TANK 10LUMP SUM$5,000.001.00$5,000.00$0.001.00$5,000.00 REMOVE METERING CHANNEL 11LUMP SUM$6,500.001.00$6,500.00$0.001.00$6,500.00REMOVE DIVERSION MANHOLE 12LUMP SUM$2,500.001.00$2,500.00$0.001.00$2,500.00REMOVE UNDERGROUND FUEL STORAGE TANK 13EACH$50.002.00$100.00$0.002.00$100.00REMOVE BOLLARD 14EACH$50.001.00$50.00$0.001.00$50.00REMOVE RV DUMP SIGN 15EACH$25.001.00$25.00$0.001.00$25.00REMOVE CURB STOP 16EACH$50.001.00$50.00$0.001.00$50.00REMOVE GATE VALVE & BOX 17EACH$350.001.00$350.00$0.001.00$350.00REMOVE YARD HYDRANT 18EACH$350.003.00$1,050.00$0.003.00$1,050.00REMOVE SANITARY SEWER MANHOLE 19LIN FT$6.00115.00$690.00$0.006.00$36.00SAWING CONCRETE PAVEMENT 20LIN FT$4.00200.00$800.00$0.000.00$0.00SAWING BITUMINOUS PAVEMENT 21LIN FT$5.00175.00$875.00$0.000.00$0.00TEMPORARY CONSTRUCTION FENCE 22LIN FT$6.00140.00$840.00$0.000.00$0.00ABANDON WATER MAIN 23LIN FT$10.00765.00$7,650.00$0.00500.00$5,000.00ABANDON SANITARY SEWER 24LUMP SUM$500.001.00$500.00$0.001.00$500.00ABANDON YARD HYDRANTS AND PIPING - NO GROUT 25LIN FT$10.00290.00$2,900.00$0.00252.00$2,520.00SALVAGE CHAIN LINK FENCE 26EACH$250.001.00$250.00$0.001.00$250.00SALVAGE HYDRANT ASSEMBLY CONTROL BUILDING AND WET WELL 27LUMP SUM$180,000.001.00$180,000.00$0.000.90$162,000.00EXISTING AND PROPOSED WET WELL IMPROVEMENTS 28LUMP SUM$75,000.001.00$75,000.00$0.001.00$75,000.00WET WELL DEWATERING 29LUMP SUM$2,500.001.00$2,500.00$0.000.00$0.00GENERATOR REMOVAL AND SALVAGE 30LUMP SUM$3,000.001.00$3,000.00$0.000.80$2,400.00BUILDING SHELL UPGRADES 31LIN FT$150.0030.00$4,500.0023.00$3,450.0030.00$4,500.00CONCRETE CRACK SEALING BY PRESSURE INJECTION 1 OWNER CONTRACTOR SEH APPLICATION FOR PAYMENT NO. 5CONTRACTOR FOR:2014 MAIN PUMP STATION & COLLECTION SYSTEM IMP PROJECT NO.STJOE 126869AGREEMENT DATE:5/1/2014 OWNERCITY OF ST. JOSEPH, MN CONTRACTORGEISLINGER & SONS, INC.FOR WORK ACCOMPLISHED THROUGH:12/12/2014 CONTRACTWORK TO DATETHIS PAYMENT ITEMUNITUNIT COSTQUANTITYAMOUNTQUANTITYAMOUNTQUANTITYAMOUNTDESCRIPTION 32LUMP SUM$1,200.001.00$1,200.00$0.001.00$1,200.00 PUMP LIFTING HOOK REPLACEMENT 33EACH$1,500.001.00$1,500.00$0.000.90$1,350.00WATER HEATER REPLACEMENT 34LUMP SUM$15,000.001.00$15,000.00$0.000.00$0.00CONTROL BUILDING COATINGS 35LUMP SUM$3,500.001.00$3,500.000.40$1,400.000.90$3,150.00BUILDING VENTILATION 36LUMP SUM$2,500.001.00$2,500.00$0.000.90$2,250.00BUILDING PLUMBING IMPROVEMENTS - WATER AND WASTE 37LUMP SUM$3,500.001.00$3,500.000.43$1,505.000.85$2,975.00GENERAL ELECTRICAL DEMOLITION 38LUMP SUM$5,000.001.00$5,000.000.65$3,250.001.00$5,000.00SITE LIGHTING POLE 39LUMP SUM$63,000.001.00$63,000.000.11$6,930.000.89$56,070.00INSTRUMENTATION AND CONTROLS BUILDING ELECTRICAL AND 40LUMP SUM$125,000.001.00$125,000.000.16$20,000.000.82$102,500.00 CONTROLS 41LUMP SUM$73,000.001.00$73,000.00$0.001.00$73,000.00175 KW GENERATOR WITH WEATHERPROOF ENCLOSURE GENERATOR PAD AND 42LUMP SUM$5,000.001.00$5,000.00$0.001.00$5,000.00 FOUNDATION - INCLUDES 43LUMP SUM$10,000.001.00$10,000.000.42$4,200.000.67$6,700.00ELECTRICAL SERVICE ENTRANCE 44LUMP SUM$8,000.002.00$16,000.00$0.000.53$4,240.00PANEL BOARDS SCREENING CHANNEL 45LUMP SUM$25,000.001.00$25,000.000.15$3,750.000.95$23,750.00BAR SCREEN STRUCTURE MODIFICATIONS STREET 46CU YD$10.004,100.00$41,000.00600.00$6,000.004,100.00$41,000.00COMMON EXCAVATION (P) (CV) 47CU YD$8.001,000.00$8,000.00$0.001,000.00$8,000.00WET WELL SUBGRADE EXCAVATION 48CU YD$22.001,970.00$43,340.00$0.001,159.00$25,498.00AGGREGATE BASE PLACED CLASS 5 (CV) (P) 49CU YD$22.00200.00$4,400.00$0.00200.00$4,400.00AGGREGATE BASE PLACED CLASS 2 (CV) (P) 50TON$74.00435.00$32,190.00$0.000.00$0.00WEARING COURSE MIXTURE 51TON$72.00680.00$48,960.00$0.00661.00$47,592.00NON WEARING COURSE MIXTURE 52GAL$3.00225.00$675.00$0.000.00$0.00BITUMINOUS MATERIAL FOR TACK COAT 53SQ YD$3.00750.00$2,250.00$0.00400.00$1,200.00GEOTEXTILE FABRIC, MNDOT TYPE 6 54SQ YD$75.00185.00$13,875.00$0.00162.00$12,150.006" CONCRETE PAVEMENT 55LIN FT$18.00550.00$9,900.00533.00$9,594.00533.00$9,594.00CHAIN LINK FENCE 56EACH$1,500.001.00$1,500.001.00$1,500.001.00$1,500.0012' WIDE DOUBLE LEAF SWING GATE 57EACH$4,000.001.00$4,000.000.50$2,000.000.50$2,000.0016' WIDE ROLLING VEHICLE GATE 58EACH$7,500.001.00$7,500.001.00$7,500.001.00$7,500.0024' WIDE ROLLING VEHICLE GATE 59EACH$550.0010.00$5,500.00$0.009.00$4,950.00BOLLARD 60LIN FT$5.00650.00$3,250.00$0.00714.00$3,570.00FURNISH & INSTALL 2" PVC UTILITY CONDUIT 61LIN FT$10.0070.00$700.00$0.0054.00$540.00FURNISH & INSTALL 4" PVC UTILITY CONDUIT 62HOUR$115.004.00$460.00$0.000.00$0.00STREET SWEEPING 2 OWNER CONTRACTOR SEH APPLICATION FOR PAYMENT NO. 5CONTRACTOR FOR:2014 MAIN PUMP STATION & COLLECTION SYSTEM IMP PROJECT NO.STJOE 126869AGREEMENT DATE:5/1/2014 OWNERCITY OF ST. JOSEPH, MN CONTRACTORGEISLINGER & SONS, INC.FOR WORK ACCOMPLISHED THROUGH:12/12/2014 CONTRACTWORK TO DATETHIS PAYMENT ITEMUNITUNIT COSTQUANTITYAMOUNTQUANTITYAMOUNTQUANTITYAMOUNTDESCRIPTION SANITARY SEWER 63LIN FT$100.00160.00$16,000.00$0.00160.00$16,000.00 10" PVC SANITARY SEWER, SDR35, WITH TYPE 2 BEDDING 64LIN FT$285.0028.00$7,980.00$0.0025.00$7,125.0024" PVC SANITARY SEWER, SDR35, WITH TYPE 2 BEDDING 65LIN FT$250.00186.00$46,500.00$0.00181.00$45,250.00 42" CCFRPM SN18 SANITARY SEWER WITH TYPE 2 BEDDING 66LIN FT$270.00189.00$51,030.00$0.00190.00$51,300.0042" CCFRPM SN72 SANITARY SEWER WITH TYPE 1 BEDDING 67LIN FT$50.00120.00$6,000.00$0.0011.00$550.00 2" PVC SCH 80 SANITARY SEWER FORCE MAIN 68LIN FT$1,000.00180.00$180,000.00$0.00180.00$180,000.00JACK & BORE 42" SANITARY SEWER 69LUMP SUM$25,000.001.00$25,000.00$0.001.00$25,000.00 JACKING PIT DEWATERING 70LIN FT$3.00808.00$2,424.00$0.00404.00$1,212.00CLEAN & TELEVISE SANITARY SEWER 71SQ YD$17.00825.00$14,025.00$0.00544.00$9,248.00 2" INSULATION 72EACH$15,000.002.00$30,000.00$0.002.00$30,000.0060" FRP SANITARY MANHOLE 73EACH$17,000.001.00$17,000.00$0.001.00$17,000.0072" FRP SANITARY MANHOLE 74EACH$20,000.001.00$20,000.00$0.001.00$20,000.0084" FRP SANITARY MANHOLE 75EACH$7,500.001.00$7,500.00$0.001.00$7,500.00PRECAST SANITARY MANHOLE 76EACH$2,500.001.00$2,500.00$0.001.00$2,500.00CONNECT TO EXISTING SANITARY FORCE MAIN 77EACH$3,000.001.00$3,000.00$0.001.00$3,000.00CONNECT TO EXISTING SANITARY SEWER 78EACH$5,000.001.00$5,000.00$0.001.00$5,000.00CONNECT TO EXISTING MANHOLE 79LUMP SUM$100,000.001.00$100,000.00$0.001.00$100,000.00BYPASS PUMPING WATER MAIN 80LIN FT$40.00400.00$16,000.00$0.00389.00$15,560.006" WATER MAIN - DUCT IRON CL 52 81EACH$4,500.001.00$4,500.00$0.001.00$4,500.00HYDRANT 82EACH$1,500.002.00$3,000.00$0.002.00$3,000.006" GATE VALVE AND BOX 83EACH$350.001.00$350.00$0.002.00$700.00YARD HYDRANT WITH 4X4 TREATED POST 84EACH$500.001.00$500.00$0.001.00$500.00CONNECT TO EXISTING WATER MAIN 85EACH$350.001.00$350.00$0.001.00$350.002" CORPORATION STOP 86EACH$200.001.00$200.00$0.001.00$200.001" CORPORATION STOP 87EACH$550.001.00$550.00$0.001.00$550.002" CURB STOP AND BOX 88EACH$240.001.00$240.00$0.002.00$480.001" CURB STOP AND BOX 89LIN FT$50.00110.00$5,500.00$0.0094.00$4,700.002" TYPE K COPPER PIPE 90LIN FT$40.00150.00$6,000.00$0.00169.00$6,760.001" TYPE K COPPER PIPE 91SQ YD$17.00150.00$2,550.00$0.0064.00$1,088.002" INSULATION 92EACH$500.003.00$1,500.00$0.001.00$500.00CONNECT TO EX WATER SERVICE 93POUND$5.00500.00$2,500.00$0.00319.00$1,595.00WATER MAIN FITTINGS 3 OWNER CONTRACTOR SEH APPLICATION FOR PAYMENT NO. 5CONTRACTOR FOR:2014 MAIN PUMP STATION & COLLECTION SYSTEM IMP PROJECT NO.STJOE 126869AGREEMENT DATE:5/1/2014 OWNERCITY OF ST. JOSEPH, MN CONTRACTORGEISLINGER & SONS, INC.FOR WORK ACCOMPLISHED THROUGH:12/12/2014 CONTRACTWORK TO DATETHIS PAYMENT ITEMUNITUNIT COSTQUANTITYAMOUNTQUANTITYAMOUNTQUANTITYAMOUNTDESCRIPTION TURF RESTORATION 94EACH$175.004.00$700.00$0.004.00$700.00INLET PROTECTION, MAINTAINED 95LIN FT$3.00835.00$2,505.00$0.00877.00$2,631.00SILT FENCE, HEAVY DUTY 96LIN FT$5.0085.00$425.00$0.000.00$0.00BIOROLL BLANKET SYSTEM 97CU YD$18.001,100.00$19,800.00$0.0072.00$1,296.00SCREENED TOPSOIL BORROW (LV) 98ACRE$2,500.001.60$4,000.00$0.000.00$0.00SEEDING 99ACRE$300.001.60$480.00$0.000.50$150.00SEEDING (TEMPORARY) 100POUND$2.0096.00$192.00$0.000.00$0.00SEED MIXTURE 22-111 101POUND$3.00704.00$2,112.00$0.0050.00$150.00SEED MIXTURE 25-131 102POUND$1.005,000.00$5,000.00$0.001,000.00$1,000.00HYDRAULIC SOIL STABILIZER 103POUND$1.00560.00$560.00$0.000.00$0.00COMMERCIAL FERTILIZER TOTAL BASE BID $1,613,123.00$75,079.00$1,410,530.00 ALTERNATE A - RV DUMP STATION 104EACH$500.002.00$1,000.00$0.002.00$1,000.00BOLLARD 105LIN FT$25.0020.00$500.00$0.0015.00$375.00CURB DESIGN V (6") 106SQ YD$100.005.00$500.00$0.005.00$500.006" CONCRETE PAVEMENT 107LIN FT$100.0010.00$1,000.00$0.0012.00$1,200.004" PVC SANITARY SEWER, SDR26 4" DI SANITARY SEWER 108LIN FT$100.002.00$200.00$0.000.00$0.00 109SQ FT$40.0022.75$910.00$0.000.00$0.00RV DUMP SIGN, WITH POST RV DUMP 4" SANITARY HATCH 110EACH$600.001.00$600.00$0.001.00$600.00 COVER 111EACH$750.001.00$750.00$0.001.00$750.00YARD HYDRANT WITH 4X4 TREATED POST 1" TYPE K COPPER PIPE 112LIN FT$50.0060.00$3,000.00$0.0048.00$2,400.00 TOTAL ALTERNATE A$8,460.00$0.00$6,825.00 CHANGE ORDER NO. 1 113LS$1,098.251.00$1,098.251.00$1,098.251.00$1,098.25REPLACE GRADE ADJUSTMENT RINGS AND CASTING ON EXISTING SANITARY MANHOLE ON SOUTH SIDE OF CR 75. 114LS$3,045.001.00$3,045.001.00$3,045.001.00$3,045.00PRIVACY SLATS INSTALLED IN NEW FENCING TOTAL CHANGE ORDER NO. 1$4,143.25$4,143.25$4,143.25 4 Project No:160-14Date of Work:10/30/2014 Project Name:St. Joseph main pump stationField Report: Description:replace adj rings on existing manholeSPR Number: L A B O R C O S T S HOURS RATESLABOR AMOUNTS NAMECLASS Perdiem Reg O.T.RegO.T.RegularOTPerdiem Total Labor Amounts \[1\]\[2\]\[3\]\[4\]\[1\] X \[3\]\[2\] X \[4\] Melforeman$83.00$0.00$83.001$83.00$124.50$0.00 johnoperator$75.00$0.00$75.001$75.00$112.50$0.00 joelaborer$73.00$0.00$73.001$73.00$109.50$0.00 1$94.00$141.00$0.00 brucesuperintendent$94.00$0.00$94.00 Labor Costs ------->$325.00 15% Markup Costs ------->$48.75 Total Labor Costs ------->$373.75 E Q U I P M E N T C O S T SM A T E R I A L C O S T S HOURSRATES KindQuantityPriceAmount TYPE RegStdbyRegStdby 1$300.00 Amountcasting$300.00 skid loader1$160.00adjusting rings2$60.00$160.00$120.00 $0.00grout, mastic1$50.00$50.00 $0.00 $0.00Material Costs ------->$470.00 $0.0015% Markup Costs ------->$70.50 $0.00Total Material Costs ------->$540.50 $0.00 SUBCONTRACTORS COSTS $0.00 $0.00KindAmountQuantityPrice $0.00$0.00 $0.00$0.00 $0.00 Equuipment Costs------->$160.00Total Sub Costs --->$0.00 15% Markup Costs------->$24.005% Markup Costs --->$0.00 Total Equipment Costs ------->$184.00Total Subs Costs --->$0.00 FORWARDED COSTS SUMMARY OF COSTS Prepared ByDate COSTSAMOUNTCOSTSAMOUNT Total Brought Forward$0.00Labor $373.75 Total for Today's Work$1,098.25Equipment$184.00 Total to be Forwarded$1,098.25Materials$540.50 Checked ByDate Subcontractor$0.00 Total Cost of Today's Work $1,098.25