Loading...
HomeMy WebLinkAboutContractor Payment Tracker - Government Center St.Joseph Government Center Summary of Contract Changes(Price Revisions) Justification Increase(Decrease) Contractors Impacted Control# PR- I Widen sidewalk and leave fire hydrant in $ (852.00) C&L Excavating SEH place PR 1 Changed the exterior lighting $ (3,882.00) Kasella,C&L Excavating PR 2 Change the head steel header plat to $ 1,798.00 HTH,J&H Erectors,Thurnbeck match jamb plates PR 3 Adjust steel structure to support partition $ 103.00 Kasella,HTH,J&H Erectors,Thurnbeck wall Kasella,HTH,Yamry,Mid Central Door, PR 4 Revision for ambulance area,not planned $ 8,218.13 Central MN Ceilings,Floors by Beckers, when plans were drafted Fransen,Breth-Zenzen,Weidener,SCR,Design Electric,C&L Excavating PR 5 Removal of two smoke dampers that are $ (570.00) Yamry,Mid Central Door not needed PR 6 changed the type of verneer to match(no $ - HTH cost) PR 7 Plans did not include header over $ 352.00 J&H Erectors,Thumbeck,Reinert Drywall, Window W3,Room 119 The structural stell as designed did not PR 8 work for the operable wall contractor $ 1,248.00 J&H Erectors,Thumbeck,Reinert Drywall, (partition door).-No cost PR 9 Reviewed door strikes adding where $ 1,610.87 Design Electric,Mid Central Door needed. PR 10 roof parapet flashing accent $ 289.00 Roof 1 Original flag lighting was pole style and PR 11 with the new location we are going $ 1,651.90 Design Electric ground mount. Omit the 2.5 furring behind architectural PR 12 precast but maintain rigid insulation.(no $ - HTH,Yamry cost) PR 13 Dedication Plaque $ 457.00 Benton Trophy,Yamry PR 14 Add bullet proof glass protection for $ 16,560.00 Yamry,ICG,Mid Central Door,American reception areas Door,East Side Glass,Reinert Drywall PR 15 change to corner stone material to match $ - HTH (no cost) PR 16 Change in radius of dias to allow for $ 3,870.00 Design Electric, ICG bullet proof material PR 17 Modifications to hoesbib fixture at the $ - Weidner Mechanical garage and sally port(no cost) PR 18 Remove the casework in the meeting $ (2,016.00) Yamry,ICG room 107,converting to office PR 19 Addition of 12 brick support angles $ 1,639.00 THTH,Thurnbeck,Yamry PR 20 Provide black out shades in the police $ 480.00 Kustom Blinds office windows Change in roof density insulation. The PR 21 original was a longer lead time and both $ (1,616.00) Roof 1 products are similar. PR 22 Add locker ventilation system $ 6,938.92 Roof 1,Fransen,Weidner,SCR,Design Electric PR 23 Add Building Sign Address $ 375.81 North Star Signs PR 24 Add Max Load and room occupancy $ 375.81 North Star Signs signs PR 25 Eliminate guides for shades in Council $ (332.00) Kustom Blinds Chambers Revise size and quantity of lockers. PR 27 Room dimensions do not support the $ (4,523.14) Mid-America(Lockers),Design Electric number of 24"lockers on the plan PR 30 Revision to Lighting in CATV Room $ 455.08 Design Electric St.Joseph Government Center Summary of Contract Changes(Price Revisions) Justification Increase(Decrease) Contractors Impacted Control# PR 31 Revision to storage room 118 $ 1,157.00 HTE,Yamry,Mid Central Door,Reinert Drywall PR 32 Sign on Building $ 7,125.78 Design Electric,Scenic Sign PR 33 Monument Sign $ 56,224.89 Design Electric,Scenic Sign PR 35 Addition of Projector,Screen Power, $ 806.51 Design Electric Data PR 36 Concrete Slab for Generator $ 750.00 Kasella Concrete,Design Electric $ 98,695.56 Contract Summary as of 9-15-16 Additional Design Fees $ 30,000.00 2016 Bond Proceeds $ 4,275,000.00 Contracts-Accepted Bids $ 3,370,302.85 2011 Bond Fund-HVAC $ 84,042.45 Construction Management $ 280,000.00 Sale of Builidng $ 500,000.00 Contingency $ 425,543.58 MN OSHA Grant $ 7,000.00 Architectural/Engineer $ 312,849.05 General Fund Approved $ 30,000.00 Less:Fees paid in 2014 $ (215,584.05) Total Avail Revenue $ 4,896,042.45 Architectural Reimb $ 5,000.00 Civil Engineering/Survey $ 32,199.04 Overhead job costs $ 117,135.00 Spent to date $ (1,989,240.35) Soil Borings $ 2,700.00 Balance remaining $ 2,906,802.10 Fiber Optics $ 7,500.00 Exterior Signage Allowance $ 24,000.00 Technology Allowance $ 150,000.00 Phone System $ 65,000.00 Furniture/Appliances $ 140,000.00 Reroute Gas $ 3,904.00 Finance Costs $ 55,100.35 Building Permit $ 83,350.18 $ 4,889,000.00