HomeMy WebLinkAbout[04g] Annual Reports [FD & PW]
2016 St. Joseph Fire
Department Annual Report
Emergency Calls 2015 and 2016
2015 2016
Emergency Calls $40,680.00 $46,442.00
Drill Hours $21,732.50 $16,648.50
Meetings $700.00 $980.00
Chief’s Salary $3,500.00 $3,500.00
Asst. Chief’s Salary $2,500.00 $2,500.00
Captain’s Salary (5) $5,000.00 $5,000.00
Secretary’s Salary $300.00 $300.00
Total: $74,412.50 $75,370.50
2015 2016
Location of Calls
City of St. Joseph 232 248
St. Joseph Township 90 77
St. Wendel Township 42 20
Mutual Aid 6 6
343 351
Total:
02016201550
Type of Call
2015 2016
Type of Emergency Call
Medical Emergency 246 – 71.7% 224 – 63.8%
Car/Truck Accident 27 – 7.9% 27 – 7.7%
False/CO Alarm 21 – 6.1% 23 – 6.6%
Structure Fire 9 – 2.6% 7 – 2.0%
Gas/Fuel Leak 10 – 2.9% 4 – 1.1%
Mutual Aid 6 - 1.7% 6 – 1.7%
Car/Truck Fire 9 – 2.6% 10 – 2.8%
Grass Fire 12 – 3.5% 4 – 1.1%
Other 4 – 1.2% 6 – 1.7%
Canceled Medical Emergency NA 40 – 11.4%
020:00 - 23:5916:00 - 19:5912:00 - 15:598:00 - 11:594:00 - 7:590:01 - 3:592018161412108642020:00 - 23:5916:00 - 19:5912:00 - 15:598:00 - 11:594:00 - 7:590:01 - 3:5918161412108642
2015 Breakdown of Emergency Calls
2016 Breakdown of Emergency Calls
Public Works Department
The public works department consists of eight full time employees: the Public Works Director, Lead
Worker, two Utility Operators and four Maintenance Workers. The Public Works Department is one of
the most diversified departments in the City due to the different services provided to the residents and
businesses.
The functional responsibilities of the Public Works department include: assisting the long and short
term planning and construction of the City’s infrastructure; managing the City’s environmental programs
and operations; and maintaining the City’s Water treatment plants, distribution systems, waste water
collection system, storm water system, streets, parks, buildings, equipment, animal control and City
responsible street lights.
General City Statistics
Current population – 6,864
Square miles in City - 3.89
Miles of maintained streets - 36
Acres of parks maintained - 77.8
2016 Projects
The St. Joseph Government Center was a large project for the City that lasted into the beginning of
2017. Both large and small projects was completed for the Government Center including: re-looping of
the water main, building a parking area for Little Saints, bus access for the school district, signing
Callaway for permitted parking, and blocking off Baker Street. This project required additional
maintenance throughout the year.
The purchase of the Old Kennedy School required more maintenance. The department resolved door
issues as well as plumbing issues. Additionally, 15 acres of mowing was added with the purchase of the
property.
In 2016, the following private and public projects were completed. The projects required assistance
from Public Works for utility work and inspections.
Country Manor – Public streets and private streets
th
Fortitude Senior Housing on 7 Ave SE – Private Street
Kwik Trip - Private
Jasmine Lane – Public Streets – to be completed in 2017
Graceview 4 & 5 – Public Streets – to be completed in 2017
CSB Athletic complex – Private – completion unknown
Streets and Parks
Throughout 2016, staff worked on maintaining the streets whether it was snow removal, street
sweeping or pot hole patching. Staff maintains all the equipment required to perform
maintenance in the City. This includes mandatory DOT inspections on vehicles.
Due to the large amount of park land and turf around all City buildings a considerable amount of
time is spent on mowing and maintaining plantings.
Building Maintenance
Staff maintains 18 different buildings in the City with a wide range of size and age from the
1940’s to 2017
Park improvements
Klinefelter Park has been re-seeded with prairie flowers and grasses. This spring the City will
start to see the new growth on the seeded areas. The dead and dying trees at Klinefelter Park
were removed for safety reasons. The stumps will be removed in 2017.
The camp ground in Millstream Park was closed. Ccamping amenities were removed and the
turf re-established as needed.
The Millstream Park pavilion replacement plan was submitted to the council. Final council
decision will occur in 2017.
Dog Park planning in Millstream Park moved forward in 2016. The Park Board is waiting on
donations to move forward with this project in 2017. It is believed that the fencing will be
installed in 2017. A Boy Scout will be installing a sitting area and plant trees in this area for the
dog park. This will be for his Eagle Scout badge.
Street improvements
An overlay project planned for 2016 was delayed due to the advanced deteriorated condition of
the streets. The City will see what length of time can be managed for these streets then do a
reconstruct of the pavement section when recommended.
The City council authorized seal coating in the City for 2016. The city had completed 84,235
square yards of seal coat for a cost of $79,538.33.
Storm sewer system
The public works staff has maintained the storm sewer system and ponds. Staff had several
repairs in 2016 on the storm water system. Additionally, pond burning is a yearly event ,
weather permitting.
The storm pond behind the small strip mall on Co.75 had the inlet structure repaired. This
required rip rap and grading of the area.
In Millstream Park staff repaired a storm sewer that runs under the softball fields. This pipe is
failing as a whole and will require future reconstruction.
Staff repaired approximately 5 failed catch basins
The City had an MS4 audit with the MPCA. The City did very well with this audit overall. There
are some minor documentation requirements that have been corrected.
Water system yearly summary
Total well water pumped – 141,576,400
Average daily flow – 382,111
Lowest pumping day – 208,900
Highest pumping day – 868,700
Miles of water main – 33.65
2016 total daily flow approximately 3,000,000 higher than 2015
In 2016 staff dropped out the spring hydrant flushing in the system. This is due to the
distribution system being mostly clear of iron and manganese sediment that causes
discoloration of the water. Iron and manganese are natural minerals in the ground water.
Sanitary sewer yearly summary
Total wastewater pumped to St. Cloud – 133,989,756
Clay sanitary sewer pipe 4.1 miles
Approximately manholes - 625
Approximately miles of sanitary sewer pipe – 29 miles
Street Lights summary
Staff maintain approximately 114 decorative street lights
Staff maintains the city parking lot lights
Staff maintains signal lights and security lights in the intersections on Co 75
Staff is in process of switching 100 watt HPS bulbs to 24watt LED lights on decorative poles
Staff has started to look into LED lights at the intersections on Co. 75
If the council has any questions please contact me at 363-7201