Council Agenda Item
MEETING DATE: July 2, 2018
AGENDA ITEM:WTP #1 Filter Rehabilitation
SUBMITTED BY: Terry Thene, Public Works Director
Randy Sabart, City Engineer
BOARD/COMMISSION/COMMITTEE RECOMMENDATION:
PREVIOUS COUNCIL ACTION: Award Bid for WTP #1 Filter Rehabilitation
Approve Piping Modifications
BACKGROUND INFORMATION:
The Project Manual for the WTP #1 Filter Rehabilitation Project (Project) included the filter
manufacturer’s original construction drawing of the existing filter. The manufacturer’s drawing indicated
the coatings inside the filter tank should have had a maximum thickness of 15.0 mils. Field measurements
of coatings thickness collected during construction when the filter was emptied indicated areas that were
approximately double the expected thickness. The Contractor incurred additional costs related to
sandblasting the filter to properly prepare the surface for the new coating system.
Change Order No. 2 includes the additional costs related to labor and materials of the additional
sandblasting and coatings work completed for the project, based on information that was discovered
during construction. It also includes painting of the raw water piping within the WTP that was not
included in the original contract. With the addition of Change Order No. 2, the contract price for the
project increases to $199,813.00.
Pay Application No. 3 (Final) in the amount of $26,837.78 is the last pay application for the Project.
This pay application brings the final amount eligible for payment to $191,459.00, which is $2,241.00 less
than the original bid price. The final payment amount is less than the original bid price because of
adjustments in the unit price work that was completed. Rice Lake Construction Group has completed all
work related to the Project and has submitted all of the close out documentation required in the contract.
BUDGET/FISCAL IMPACT: $26,837.78 (including Change Order No. 2)
ATTACHMENTS:Change Order No. 2 – Additional Sandblasting and Painting
Pay Application No. 3 (Final)
REQUESTED COUNCIL ACTION: Approve Change Order No. 2 and Pay Application No. 3 (Final)