BACKGROUND INFORMATION: City staff has been working with the contractors regarding the
humidity issue in the building. The system that was installed is built according to plans. The
administration side comes extremely humid to the point where papers are damp and the sorting machine
does not work. We are also concerned that if we do not do anything it could impact long term the
building itself. The City designed the building for future capacity which would include additional staff.
The additional staff would create additional heat therefore the cooling unit would run longer taking the
humidity out of the air. In talking to different contractors and the design engineer the only way to resolve
the matter is to install additional heat to the building to get the air conditioning unit to run.
BUDGET/FISCAL IMPACT: $ 15,520.00.
ATTACHMENTS: Precise Quote
REQUESTED COUNCIL ACTION: Approve the expenditure of $ 15,500 to resolve the humidity
in the government center.
"Precise...Because We Care"
710 19th Ave NE
St. Joseph, MN 56374
J , Telephone (320) 363-7401
z?> 41~ � _ ,04,-A' "�'' Fax (320) 363-7402
www.precisemn.com
July 26, 2018
City of St. Joseph
75 Callaway Street East
St. Joseph, MN 56374 •
Attn: Terry Thene
The following is a quotation to add additional heat to help dehumidify the office area at St. Joseph
Government Center in St. Joseph, MN.
Option #1 -Price includes: (Natural Gas Furnace)
1. One American Standard 100,000 BTU, two stage, variable speed, 96% efficient furnace. (See
Note#2)
2. Galvanized sheet metal for supply and return duct.
3. PVC pipe and fittings for furnace venting up thru roof and condensate drain to nearest floor drain
located in mechanical room.
4. Steel pipe and fittings for natural gas piping in mechanical room to furnace. (2PSI gas figured)
5. Grilles, Registers, and Diffusers.
6. One dehumidistat.
7. Labor to install the above items.
8. Electrician allowance of$450.00.
9. Roofer allowance of$800.00.
10. Ceiling grid removal and reinstall allowance of$700.00.
11. Freight and sales tax.
12. City permit and inspection fees.
13. Manufacturer's parts warranty and a one year labor warranty on items provided by Precise.
4 Option #1 -Total price: $15,520.00.
Option #2 -Price includes: (Electric Heat Air Handler)
1. One American Standard 4 ton air handler with a 25Kw electric heater. (See Note#2)
2. Galvanized sheet metal for supply and return duct.
3. Grilles, Registers, and Diffusers.
4. One dehumidistat.
5. Labor to install the above items.
6. Electrician allowance of$875.00.
7. Roofer allowance of$800.00.
8. Ceiling grid removal and reinstall allowance of$700.00.
9. Freight and sales tax.
10. City permit and inspection fees.
11. Manufacturer's parts warranty and a one year labor warranty on items provided by Precise.
Option #2 -Total price: $13,315.00.
Notes:
1. Not included is any of the following:
a. Engineered Drawings
b. Overtime or Premium Wages
Sales&Service
Industrial ° Commercial ° Residential
"Precise...Beca use We Care"
710 19th Ave NE
St. Joseph, MN 56374
Telephone (320) 363-7401
Fax (320) 363-7402
www.precisemn.com
c. Bid bond or performance bond.
2. Natural gas is about 1/3 the cost to operate than the electric heat air handler.
3. Quote is valid for 30 days.
Thank you for allowing me to quote this. If you have any questions please give me a call at 320-363-7401
e-mail tory(a�precisemn.com.
Sincerely,
Precise Heating, A/C, Plumbing, Refrigeration
Tory Zamzow Customer Acceptance: Option #: Date:
•
Sales&Service
Industrial - Commercial r Residential