Council Agenda Item \[06\]
MEETING DATE: July 15, 2019
AGENDA ITEM: Engineer Reports
a. Bid Tabulation
SUBMITTED BY: Engineering
BOARD/COMMISSION/COMMITTEE RECOMMENDATION:
PREVIOUS COUNCIL ACTION: The City accepted bids on July 10, 2019 for the 2019 Street Improvement
Project and conducted the Final Assessment Hearing. With only three contentions at the hearing the Council
adopted the final assessment hearing.
The largest cost deltas between the final engineer's opinion of cost and the low bid to be generally in 4 areas of
work, and for a total of about $228,443:
1) Milling/bituminous pavement - items 23, 27, 28 sum difference of $105,214
2) Concrete flatwork - items 61, 62, 66, 67 sum difference of $38,665
3) Jacked steel casing pipe - item 51 difference of $30,720
4) Pavement markings/striping - items 80, 82 sum difference $53,844
Of the four cost difference areas, and based on all the bids, I could accept that our estimate was simply low for the
small amount of casing construction in the project. I plan to reach out to Knife River to further question some of
their pricing. If so inclined, the City could consider deleting the pavement markings (group 4 above) from the
contract and soliciting separate quotes for the work. Knife River's pricing is materially higher than the other bidders,
and I don't have a good explanation for "why?"
BACKGROUND INFORMATION:
BUDGET/FISCAL IMPACT:
ATTACHMENTS: Bid Tabulation
REQUESTED COUNCIL ACTION: Authorize the Mayor and Interim Administrator to execute Resolution
2019-047 awarding the bids for the 2019 Street Improvement Project.
RESOLUTION 2019-047
AWARDING BID
2019 Street Improvement Project
WHEREAS, pursuant to an advertisement for bids for the 2019 Street Improvement Project affecting the
th
following areas: 12 Avenue SE between a point 250 feet north of E Baker Street and a point 250 feet
th
south of Dale Street, Pond View Lane E between E Baker Street and Dale Street, 13 Avenue SE cul-de-
thth
sac south of E Baker Street, E Baker Street between a point 250 feet west of 12 Avenue SE and 16
th
Avenue SE, Callaway Street E between 12 Avenue SE and Pond View Lane E, Cary Court cul-de-sac
th
east of 12 Avenue SE, Cedar Court cul-de-sac east of Pond View Lane E, Dale Street E between a point
ththth
250 feet west of 12 Avenue SE and 16 Avenue SE, 4 Avenue NE between County State Aid Highway
thst
(CSAH) 75 and Minnesota Street E, 4 Avenue SE between Minnesota Street E and E Baker Street, 1
nd
Avenue NW between CSAH 75 and Minnesota Street W, Birch Street W between 2 Avenue NW and
nd
College Avenue N, Ash Street W between 2 Avenue NW and College Avenue N and, Jade Road
between County Road 121 and the south City limits at Interstate 94 by resurfacing the bituminous streets
by overlay, mill and pave, or reclaim and pave methods; and the improvements of Old Highway 52
between Birch Street W and CSAH 75 and, the complete loop of Cypress Drive south west of Old
Highway 52 by reconstructing the sanitary sewer and bituminous streets; and the improvements of Elm
st
Street W between 1 Avenue NW and College Avenue N and Elm Street E between College Avenue N
st
and 1Avenue NE by constructing new water main and sanitary sewer and reconstructing the bituminous
street. Bids were received, opened and tabulated according to law, and the following bids were received
complying with the advertisement:
Knife River Corporation $1,994,349.93
OMG Midwest $2,037,045.92
C&L Excavating $2,090,783.80
AND WHEREAS, it appears that Knife River Corporation is the lowest responsible bidder.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF ST. JOSEPH, MINNESOTA:
The Mayor and Administrator are hereby authorized and directed to enter into the attached contract with
Knife River Corporation in the name of the City of St. Joseph for the 2019 Street Improvement Project as
described above according to the plans and specifications therefore approved by the City Council and on
file in the office of the Administrator.
The Administrator is hereby authorized and directed to return forthwith to all bidders the deposits made
with their bids, except that the deposits of the successful bidder and the next lowest bidder shall be
retained until a contract has been signed.
th
Adopted by the council on this 15 day of July, 2019.
________________________________
Rick Schultz, Mayor
________________________________
Therese Haffner, Interim Administrator