Council Agenda Item 4h
MEETING DATE: August 19, 2019
AGENDA ITEM: Professional Services Agreement
SUBMITTED BY: Kris Ambuehl, City Administrator
Randy Sabart, City Engineer
BOARD/COMMISSION/COMMITTEE RECOMMENDATION:
PREVIOUS COUNCIL ACTION: Ordered preparation of construction documents
Conducted special assessment hearing
Awarded construction contract
BACKGROUND INFORMATION:
Construction for the 2019 Bituminous Street Improvements is tentatively scheduled to begin the
week of September 1, 2019. The final completion date for the construction contract with Knife
River is July 10, 2020.
BUDGET/FISCAL IMPACT:
Construction Contract $1,726,500
Construction Contingency $58,990
Feasibility Report $29,600
Geotechnical Investigation (Soil Borings) $6,150
Design & Est. Construction Engineering $264,100
Est. MSAS Construction Materials Testing $16,160
Legal, Fiscal, & Administrative $110,000
TOTAL $2,211,500
ATTACHMENTS: Professional Services Agreement
REQUESTED COUNCIL ACTION:
1) Execute Professional Services Agreement between the City of St. Joseph and SEH for
construction phase engineering services
July 15, 2019 RE: St. Joseph, Minnesota
2019 Bituminous Street Improvements
Construction Phase Services
SEH No. STJOE 147693 10.03
Honorable Mayor and City Council
c/o Mr. Ambuehl, Administrator
City of St. Joseph
75 Callaway Street East
St. Joseph, MN 56374
Dear Mayor and Members of the Council:
This letter supplements the Agreement for Professional Services between the City of St. Joseph,
Minnesota, Owner, and Short Elliott Hendrickson Inc. (SEH) dated July 1, 2006, and addresses
providing Construction Phase services for the 2019 Bituminous Street Improvements (hereinafter called
the “Project”).
Our services will consist of providing assistance with negotiating a construction contract with the
successful bidder; providing construction services including construction administration, resident project
representation, and construction staking services during construction for the Project, all as set forth in this
letter, and the Agreement for Professional Services between SEH and the Owner dated July 1, 2006. We
will also furnish such Additional Services as you may request or as required.
Task 1: Construction Administration Services
Assist Owner in preparing Construction Agreement.
Conduct pre-construction conference at City Hall.
Review Contractor shop drawing submittals (one time).
Make periodic site visits to observe progress and quality of executed work of Contractor(s), and to
determine in general, if such work is proceeding in accordance with the Contract Documents (up
to 12 site visits estimated).
Prepare and review Contractor applications for payment (7 payment applications estimated).
Review Contractor prevailing wage reports.
Prepare project completion punch list at Substantial Completion.
Review contract close-out documents, including final payment application, and forward to Owner
with recommendation for final payment
Assemble record drawings based on Contractor-collected field measurements.
Task 2: Construction Staking Services
Provide horizontal and vertical control stakes on site (one time).
Provide one set of street centerline subgrade blue tops at 50-foot intervals.
Provide one set of sanitary sewer, water main, and storm sewer offset cut/fill stakes. Sanitary
sewer and water main stakes shall utilize the same hub and witness lath when possible.
Provide one set of street centerline finished aggregate base blue tops on 50-foot intervals.
Engineers | Architects | Planners | Scientists
Short Elliott Hendrickson Inc., 1200 25th Avenue South, P.O. Box 1717, St. Cloud, MN 56302-1717
SEH is 100% employee-owned | sehinc.com | 320.229.4300 | 800.572.0617 | 888.908.8166 fax
Honorable Mayor and City Council
July 15, 2019
Page 2
Provide one set of concrete curb and gutter cut/fill stakes on 25-foot intervals.
Additional staking beyond the scope identified or re-staking or due to Contractor’s operation shall
be at Contractor’s expense.
Task 3: Resident Project Representative (RPR) Services
Provide full-time construction observation by a RPR for utility and street construction (800 hours
budgeted).
Assumptions:
Construction Administration and RPR services have been budgeted assuming the construction contract
duration for utility and street construction operations does not exceed 80 Working Days.
Up to four project newsletters may be prepared for distribution by the Owner.
Additional Services:
The following services from SEH are not included in this proposal but, if required, can be provided to the
Owner:
Construction Administration and Resident Project Representative services beyond the project
duration or labor hours budgeted above.
We will also furnish such Additional Services as you may request or as required.
You will pay us a fee for our services, currently estimated to be $187,485, including expenses (estimated
to be $9,480), in accordance with Exhibit C-1, Hourly Basis Rate Table Method.
Payment for additional services shall be based on the time required to perform the services and the
billable rates for the principals and employees engaged directly on the Project, plus charges for expenses
and equipment, all in accordance with Exhibit C-1.
We will start our services promptly after receipt of your authorization. We estimate our services will be
completed after 13 months. If there are delays in the Project beyond our control, you agree to grant
additional time to complete the services.
Your budgetary limitations for construction of the Project should be provided to us in writing at an early
date. We will endeavor to work within those limitations. Where appropriate, if the estimated cost exceeds
the budget, we will either request an adjustment in the budget or suggest a revision in the extent or
quality of the Project to assist in bringing construction cost back within the budget. We do not guarantee
that our opinions of probable construction cost will not differ materially from negotiated prices or bids. If
you wish greater assurance as to probable construction cost or if you wish formal estimates, an
independent cost estimator should be employed as provided in Section IV.A. of the Agreement and in
Exhibit B.
This letter and the Agreement for Professional Services dated July 1, 2006, along with Exhibits A, B, C-1,
C-2, and D represent the entire understanding between you and us in respect of the Project and may only
be modified in writing signed by both of us. If it satisfactorily sets forth your understanding of our
agreement, please sign the enclosed copy of this letter in the space provided below and return it to us.
Honorable Mayor and City Council
July 15, 2019
Page 3
Sincerely,
SHORT ELLIOTT HENDRICKSON INC.
Randy Sabart, PE
Principal
djg
\\\\sehsc\\projects\\pt\\s\\stjoe\\147693\\1-genl\\10-setup-cont\\03-proposal\\design_constr\\l city supplemental ltr agreement -construction 071519.docx
ACCEPTED BY: CITY OF ST. JOSEPH, MINNESOTA
By: Date: