HomeMy WebLinkAbout[09] 2020 Budget - Engineer Capital Improvement Plan Council Agenda Item 9 MEETING DATE: August 19, 2019 AGENDA ITEM: 2020 Budget - Engineer Capital Improvement Plan SUBMITTED BY: Finance/Administration/Engineer/Public Works BOARD/COMMISSION/COMMITTEE RECOMMENDATION: None PREVIOUS COUNCIL ACTION: Council approves a 5- year Capital Improvement Plan (CIP) with updates annual to identify priorities. BACKGROUND INFORMATION: Public Works and Engineering reviewed the engineer’s 5-year CIP and assigned priorities to the top four project needs. Staff would like to have a discussion with Council on the priorities and get feedback on their concerns and vision. A project description for each item in the CIP follows the summary sheet. The individual forms provide a breakdown of possible funding sources. BUDGET/FISCAL IMPACT: Discussion Item ATTACHMENTS: Request for Council Action– Engineer CIP 2020 Summary Engineer CIP 2020 Individual Engineer CIP Forms REQUESTED COUNCIL ACTION: Provide feedback on the projects listed in the Engineer’s 5-year Capital Improvement Plan. TBDTBDTBDTBDTBDTBDTBDTBDTBDTBDTBDTBDTBD $18,000$95,000$21,000$50,000$71,000$50,000$42,000$50,000$59,000 $653,000$918,000$732,000$236,000$466,000$497,000$912,000$102,000$277,000$103,000$309,000$213,000$111,000$581,000 $1,165,000$2,331,000$4,276,000$1,520,000$4,326,000$6,313,000$2,161,000$4,073,000$1,757,000$1,463,000$3,839,000$2,930,000$1,224,000$5,275,000$3,264,000$1,602,000 Cost @ i=3.5%/yr Opinion of Project Cost @ i=3.5%/yr Opinion of Project TBDTBDTBDTBDTBDTBDTBDTBDTBDTBDTBDTBDTBD 202020202020202420222023202220242020202220202020202020202022202420202020202020232020202420222022202420232022202420202022202220242022202020242020202220202024 Projected YearProjected Year of Constructionof Construction 201820192018200620182005200620052018201520172018201920182019201120042014201720152019201920142012201220052019200520192011201820062006202220182030201820112018200420222014201820302018202220182018 Year ofYear of EstimateEstimate $17,498$89,000$30,000$75,000$86,400$20,049$50,000$65,850$50,000$90,641$39,400$50,000$54,750 $609,706$627,125$800,000$422,221$199,097$450,000$624,328$881,610$128,000$210,200$298,980$310,000$995,600$107,000$472,650 $1,255,092$1,162,876$3,478,875$1,325,000$3,400,000$4,632,058$8,437,500$1,396,393$2,087,581$1,800,855$3,429,248$1,269,205$1,300,000$2,067,000$1,632,470$3,810,928$2,900,000$1,303,275$5,210,000 of Costof Cost Original OpinionOriginal Opinion 20242024 $213,000$581,000$581,000 BudgetBudget $1,165,000$4,276,000$5,441,000$4,326,000$4,326,000$4,073,000$3,839,000$1,224,000$5,063,000$1,602,000$1,815,000 $17,226,000 20232023 BudgetBudget $6,313,000 $2,331,000$2,331,000$6,313,000$2,930,000$2,930,000 $11,574,000 $50,000$50,000$50,000$50,000 20222022 $918,000$582,000$277,000$277,000 BudgetBudget $1,520,000$3,020,000$1,757,000$1,463,000$3,270,000$5,275,000$3,264,000$8,589,000 $15,206,000 20212021 BudgetBudget $18,000$95,000$21,000$71,000$71,000$42,000$59,000$59,000 $653,000$236,000$466,000$497,000$912,000$102,000$103,000$309,000$111,000$153,000 20202020 BudgetBudget $1,447,000$2,161,000 $1,965,000$2,161,000$5,856,000 20192019 BudgetBudget EquipmentEquipment Street Overlays 2020Crack Seals 2020 OAAMinnesota StreetscapingFirst Avenue NE ImprovementsNorthland Drive ImprovementsJade Road Improvements16th Avenue ImprovementsNorthland Heights Phase IIIndustrial Park Expansion Ph II\[Parkway Business Center\]18th Avenue Improvements & IntersectionIndustrial Park EastADA Transition PlanElm Street Extension20th Avenue SE Improvements to Dale StreetAlley ImprovementsMillstream Parking lot ImprovementsWelcome Monument SignsWobegon Welcome Center - S. Parking LotKlinefelter Park UtilitiesCSAH 75 Pedestrian CrossingBaseball Parking Lot ImprovementTrail MaintenanceNorthland Park Trail ImprovementsField Street (7th Avenue to 16th Avenue)North Corridor ROW & Construction \[73rd Ave to CR133\]North Corridor EISJade Road Extension20th Avenue SE Improvements (North)20th Avenue SE Construction (South)North Corridor ROW & Construction \[CR133 to CSAH 3\]CR133 & Elm Street ImprovementsSouthwest Trunk WaterCSAH 2 Water ExtensionNew Water TowerUpgrade Old Water Main16th Avenue ImprovementsIndustrial Park Expansion Ph II\[Parkway Business Center\]St. Wendel Trunk WaterAlley ImprovementsIndust rial Park EastSouthwest Trunk SewerCSAH 2 Sewer ExtensionCR121 Lift Station Generator16th Avenue ImprovementsCIPP Improvements 1st Ave NEIndustrial Park Expansion Ph II\[Parkway Business Center\]St. Wendel Trunk SewerIndustrial Park EastAlley Improvements16th Avenue ImprovementsAlley ImprovementsIndustrial Park Expansion Ph II\[Parkway Business Center\]Total Engineering CIP ProjectProject NumberNumber ENG-1501ENG-1602ENG-1535ENG-1521ENG-1531ENG-1536ENG-1533ENG-1906ENG-1506ENG-1640ENG-1711ENG-1903ENG-1904ENG-1505ENG-1543ENG-1526ENG-1905ENG-1520ENG-1538ENG-1544ENG-1528ENG-1513ENG-1523ENG-1532ENG-154 7ENG-1529ENG-1515ENG-1908ENG-1510ENG-1527ENG-1536ENG-1508ENG-1542ENG-1904ENG-1640ENG-1514ENG-1907ENG-1522ENG-1536ENG-1535ENG-1508ENG-1541ENG-1640ENG-1904ENG-1536ENG-1904ENG-1508 Account CodeAccount Code New-43120-530390-43120-530New-43120-530New-43120-530New-43120-530New-43120-530New-43120-530New-43120-530New-43120-530New-43120-530390-43120-300New-43120-530New-43120-530new-45202-530new-45202-530new- 45202-530new-45202-530200-45202-303new-45202-530new-43120-530new-43120-530new-43120-530new-43120-530New-43120-530New-43120-530new-43120-530601-49440-530601-49436-530601-49430-530601-49440-530New-4312 0-530601-49440-530New-43120-530602-49480-530602-49473-530602-49450-530602-49450-530New-43120-530602-49480-530New-43120-530651-49900-530New-43120-530 ProjectProject PriorityPriority RankingRanking ProjectProject DepartmentDepartment City of St. Joseph2020 Capital Improvement Plan - EngineerDRAFT as of August 16, 2019Street -Parks -Corridor Streets -Water - Sanitary Sewer - Storm Water - ENG-1501 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Street Overlays 2020$653,000 Improvements other than Buildings $653,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Street Maintenance Northland Area Account Code: JUSTIFICATION: Street overlays prolong the life of the streets before a total reconstruction is needed. The City also sealcoats/crack fills the streets annually to prolong the street lives (see Public Works CIP). The street overlays are anticipated on an as needed basis at about the 15-20 year mark after construction/reconstruction. Overlays are paid for by levy and special assessments. The 2020 overlays are proposed to be Jasmine Lane, Northland Drive, Iris Lane, 3rd Ave NW, Hickory Drive, Hackberry Drive, & 7th Ave NE. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments $391,800 $391,800 Debt Levy $261,200$261,200 Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score36.3 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2020 Land Acquisition Construction PROJECT COMPLETION DATE: 2021$653,000 Equipment and Other NEIGHBORHOOD:Total $653,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 2 ENG-1501 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Crack Seals 2020 OAA$18,000 Improvements other than Buildings $18,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Street Maintenance Orderly Annexation Area Account Code: JUSTIFICATION: Street maintenance prolongs the life and quality of the streets. The City performs sealcoats/crack fills on select streets annually to prolong the street life. (see Public Works CIP). Crack fills and seal coats are in addition to overlays that are planned for 15-20 year mark after construction/reconstruction. Crack fills/sealcoats are paid for by street maintenance funds. The 2020 sealcoats are proposed to be the newly annexed areas 1st Avenue NE, 304th Street, 305th Street, 76th Avenue, Cedar Ridge Drive, & a portion of Leaf Road. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Levy $18,000$18,000 Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2020 Land Acquisition Construction PROJECT COMPLETION DATE: 2021$18,000 Equipment and Other NEIGHBORHOOD:Total $18,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 3 ENG-1602 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Minnesota Streetscaping$95,000 Improvements other than Buildings $95,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Streetscaping for Minnesota Street Account Code: 390-43120-530 E205-45203-531 JUSTIFICATION: Currently Minnesota Street has trees with planter boxes and paver stones. Many of the roots from the trees have pushed up and created warping of the paver stones and planter boxes. This plan provides for new plantings, tree grates, and sidewalk replacements in the areas most needed. The US Army Reserve may be able to assist in this project using their community service volunteer hours. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Service Relief $73,500$73,500 Park Tree Fund $1,500$1,500 Army Contribution $20,000$20,000 (in kind labor) Priority Score51.95 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2020 Land Acquisition Construction PROJECT COMPLETION DATE: 2021$95,000 Equipment and Other NEIGHBORHOOD:Total $95,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 4 ENG-1535 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: First Avenue NE Improvements$1,165,000 Utility Extension 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Street, water main, sanitary sewer improvements Fir St to Northland Plat line Account Code: E601-49440-530/E602-49480-530 JUSTIFICATION: Improvements include sanitary sewer between Fir Street and the Northland lot line. A water main would connect at Resurrection Church and extend North to Jasmine Lane. The street is proposed as an urban section from Fir Street to CSAH 2. Utilities from CSAH 2 to Jasmine Lane would be installed in the ditch to minimize disturbance of the pavement. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments $1,165,000$1,165,000 Debt Levy Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score23.65 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2024 Land Acquisition Construction PROJECT COMPLETION DATE: 2025$1,165,000 Equipment and Other Total NEIGHBORHOOD: North City$1,165,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 5 ENG-1521 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Northland Drive Improvements$918,000 Streets, Storm Sewer, Trails 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Northland Dr from CSAH 75 to Fir Street Account Code: New-43120-530; New-43120-33421 JUSTIFICATION: The proposed plan is for a reclaim and pave from CSAH 75 to Fir Street, with the addition of curb & gutter and storm sewer where there is none existing. The intersection of Elm Street and Northland Drive is proposed to be raised in elevation to accomodate storm sewer that will address current drainage issues. It also includes construction of a 6 foot sidewalk from CSAH 75 to Hickory Drive. The project is delayed until 2022 to more properly match the benefit test for assessments. The project may move up if warranted. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments $550,800$550,800 MSAS $367,200$367,200 Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score37 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2022$367,200 Land Acquisition Construction PROJECT COMPLETION DATE: 2023$550,800 Equipment and Other Total NEIGHBORHOOD: Northland Development$918,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 6 ENG-1531 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Jade Road Improvements$2,331,000 Streets 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Street Improvements - Neary Street to I-94 Account Code: New-43120-530 JUSTIFICATION: This plan provides for street reconstrution of Jade Road from Neary Street to I-94. The plan proposes a three lane road, curb & gutter construction with storm sewer, and a sidewalk or trail behind the back of curb. The estimate does not include pond excavation, sanitary sewer, or water main to the school site. These items shall be included with Rivers Bend. Jade Road improvements from CR121 to Neary Street was completed in 2008. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Developer Assessments $2,331,000$2,331,000 Debt Levy Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score23.3 PROJECT COSTS PROJECT STARTING DATE:Preliminaries 2023 Land Acquisition PROJECT COMPLETION DATE:Construction 2024$2,331,000 Equipment and Other NEIGHBORHOOD:Total South City$2,331,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 7 ENG-1536 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: 16th Avenue Improvements$732,000 Street & Utility Extension 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Dale Street to City Limits : New-43120-530, new-49302-39201 \[water,sewer,storm Account Code JUSTIFICATION: This plan provides for street, curb and gutter, sanitary sewer, water main, and storm sewer from Dale Street to the south end of Pond View Court. 16th Avenue improvements from Minnesota St E to Dale Street was completed in 2010. This project will not begin until a developer requests the extension. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments $366,000$366,000 Debt Levy $216,000$216,000 Debt Levy - Storm $50,000$50,000 Debt Levy - Sewer $50,000$50,000 Debt Levy - Water $50,000 $50,000 Priority Score25.3 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2022 Land Acquisition Construction PROJECT COMPLETION DATE: 2023$732,000 Equipment and Other Total NEIGHBORHOOD: Southeast City$732,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 8 ENG-1533 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Northland Heights Phase IITBD Utility Extension 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Northland Phase II Account Code: Account Code: new-43120-530 JUSTIFICATION: The proposed development is the second phase of Northland Heights. The cost is based upon constructing sanitary sewer, water main, streets, and storm sewer for the 70 lot subdivision. The development will be developer driven. With the slow down in the housing market, the project may not occur for a few more years. Lumber One has 44 lots available in Northland Heights 1st addition. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Developer Assessments Debt Levy Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score18.5 PROJECT COSTS Preliminaries PROJECT STARTING DATE: TBD Land Acquisition PROJECT COMPLETION DATE:Construction Equipment and Other Total NEIGHBORHOOD: Northland Heights/North City Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Authorizing Initials Approval to Purchase Date_________________________Date ENG- 9 ENG-1906 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: $7,683,000 Industrial Park Expansion Ph II\[Parkway Busines Private Development - Utility Extension 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Expand NE Industrial Park Account Code: JUSTIFICATION: Phase 2 expansion for the Northeast Industrial Park Area. Includes Sewer, Water, Street and Storm Sewer Improvements to lots. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Debt Levy/Assessments $4,276,000$4,276,000 DEED Funds Debt Levy - Storm $581,000$581,000 Debt Levy - Sewer $1,602,000$1,602,000 Debt Levy - Water $1,224,000$1,224,000 Priority Score36.425 PROJECT COSTS PROJECT STARTING DATE:Preliminaries 2024 Land Acquisition PROJECT COMPLETION DATE:Construction 2025$7,683,000 Equipment and Other NEIGHBORHOOD:Total Industrial Park$7,683,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 10 ENG-1506 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: 18th Avenue Improvements & Intersection$236,000 Streets $236,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Reconstruct 18th Avenue Account Code: JUSTIFICATION: The proposed plan is to reconstruct the deteriorated portion of 18th Avenue to a 32' wide rural section roadway. The proposed roadway has a preliminary typical section of 2" wear, 2" non-wear, 6" class 5 aggregate, and an 18" select granular borrow. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments $141,600 $141,600 Debt Levy $94,400$94,400 Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score42.9 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2020 Land Acquisition Construction PROJECT COMPLETION DATE: 2021$236,000 Equipment and Other NEIGHBORHOOD:Total $236,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 11 ENG-1640 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Industrial Park EastTBD Private Development - Utility Extension 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Extend Utilities to existing Industrial Park East Development Account Code: New-43120-530; new-49302-39201 \[water/sewer\] JUSTIFICATION: St. Joseph Industrial Park East is an commercial and industrial development annexed from St. Joseph Township that was constructed in the early 2000s. The businesses currently do not have City water and sewer available. This plan provides for extending utilities from Borgert's area to the east. The sewer and water within the subdivision would be installed in the boulevard areas to minimize disturbance of the pavement. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Levy Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water TBD Priority Score32 PROJECT COSTS Preliminaries PROJECT STARTING DATE: TBD Land Acquisition PROJECT COMPLETION DATE:Construction Equipment and Other Total NEIGHBORHOOD: Industrial Park East Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 12 ENG-1711 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: ADA Transition PlanTBD 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Handicap Accessibility Transition Plan Account Code: 390-43120-300 JUSTIFICATION: This plan addresses the development of a transition plan identifying physical obstacles limiting accessibility. It is a schedule for necessary improvements to bring the City within compliance of the federal Americans with Disabilities Act (ADA). These improvements include pedestrian access routes (PAR) and pedestrian ramps incorporating truncated domes. The widths and slopes of the PAR and ramp are both controlled by maximum and minimum slopes defined by ADA. The truncated domes need to cover the entire width of the curb opening and there is a landing located at the top of each ramp. Areas without compliance will need to be scheduled for reconstruction to meet the requirements of ADA. The state has requested all cities have a plan in place by 2019. If not in place, the City could potentially become ineligible for future federal funding. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Debt Service Reserves Priority Score PROJECT COSTS Preliminaries PROJECT STARTING DATE: TBD Land Acquisition PROJECT COMPLETION DATE:Construction Equipment and Other NEIGHBORHOOD:Total Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 13 ENG-1903 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Elm Street Extension$1,520,000 Improvements other than Buildings 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Connect Elm Street from Culdesac East Account Code: JUSTIFICATION: Elm Street is currently a non-continuous street with a culdesac termination. This plan provides for a street connection that would develop into a Community Collector Street from the Northland Neighborhoods to the Commercial Businesses to the East near County Road 133. The proposed road section is an urban section 44 foot in width. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Levy $1,520,000$1,520,000 Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2022 Land Acquisition Construction PROJECT COMPLETION DATE: 2023$1,520,000 Equipment and Other NEIGHBORHOOD:Total $1,520,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 14 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: 20th Avenue SE Improvements to Dale Street$466,000 Streets $466,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Minnesota Street to Dale Street Account Code: JUSTIFICATION: This plan provides for street construction to service the Sand Companies apartment site development on the 20th Avenue corridor from Minnesota Street to Dale Street. The roadway is planned as a 24' wide rural section without any utility improvements. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Developer Assessments (70%) $326,200$326,200 Federal/State/County $139,800$139,800 Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score16 PROJECT COSTS PROJECT STARTING DATE:Preliminaries 2020 Land Acquisition PROJECT COMPLETION DATE:Construction 2021$466,000 Equipment and Other NEIGHBORHOOD:Total South and East City$466,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 15 ENG-1904 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Alley Improvements$669,000 Improvements other than Buildings $669,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Alley Reconstruction Account Code: JUSTIFICATION: Project includes reconstructing approximately alleys between Minnesota Street and Ash Street and 1st Avenue NW and 3rd Avenue NW that are currently gravel. The project also includes an alternate for lining the clay tile sanitary sewer. It is anticipated the alley would be reconstructed to a width of 20 feet and similar in structure to the previous alley improvements (3.5 - 4 inches of bituminous and 8 inches of aggregate base). The alley behind the funeral home is heavily used and also a candidate to improve. The cost estimate for the funderal home alley is not included below. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Levy $497,000$497,000 Debt Levy - Storm $59,000$59,000 Debt Levy - Sewer $42,000$42,000 Debt Levy - Water $71,000$71,000 Priority Score PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2020 Land Acquisition Construction PROJECT COMPLETION DATE: 2021$669,000 Equipment and Other NEIGHBORHOOD:Total $669,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 16 ENG-1505 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Millstream Parking lot Improvements$912,000 Regional Trails $912,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Parking lot and Storm Sewer Improvements Account Code: 200-45203-530 JUSTIFICATION: This plan provides grading and paving the existing bituminous and gravel parking lots with all new asphalt. The street section is estimated for 6" gravel, 2" non-wear bituminous, and 2" wear course bituminous. Storm sewer planned to collect the site drainage and storm water runoff. A storm water pond at the northeast end of the site is proposed through land acquistion, and a second pond is anticipated at the southeast end of the parking lot near the field on park property. Along the Northwest side of the entrance drive, retaining wall construction is anticipated to manage drainage and erosion issues. A storm sewer line running West to East is proposed to be reconstructed from the old County Road 3 ditch to the Watab River. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Debt Levy $912,000$912,000 Debt Levy - Storm Priority Score37.1 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2020 Land Acquisition Construction PROJECT COMPLETION DATE: 2021$912,000 Equipment and Other Total NEIGHBORHOOD: Northwest City$912,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 17 ENG-1543 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Welcome Monument Signs$102,000 Improvements other than Buildings $102,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Welcome to St. Joseph Signs Account Code: New-45202-530/490-43120-530 JUSTIFICATION: The Welcome to St. Joseph sign on the western entrance to the City is located near 6th Ave NW on Minnesota Street. Staff budgeted funds for a new welcome to St. Joseph sign to be constructed when the Co Rd 2 bypass is installed if the Council decides this would be beneficial to the City. The new sign would be located further west close to the new Co Rd 2 alignment. The current sign is made out of brick and mortar that is not able to be relocated without damaging the structure. The current welcome sign may be impacted by the phase II trail extension if the extension is placed on the south side of Minnesota St. The total cost of the sign may go up substantially if the sign is made from different materials and adds a digital feature. The current budgeted cost is carried forward from previous years. The other Welcome to St. Joseph sign on the western entrance to the City was located at County Road 75 and Old Highway 52. The sign needed to be relocated per the request of the property owner the original sign was located on and to accommodate the Xcel Energy substation. The original sign was made of brick and mortor. Due to the type of material, the sign could not simply be moved. The total cost is an estimate to reconstruct a similar sign along the western city limits and CSAH 75. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Service Relief $102,000$102,000 Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score16.5 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2020 Land Acquisition Construction PROJECT COMPLETION DATE: 2021$102,000 Equipment and Other Total NEIGHBORHOOD: Northwest City$102,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 18 ENG-1526 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Wobegon Welcome Center - S. Parking LotTBD Regional Trails 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construct South Parking lot for the Wobegon Welcome Center Account Code: E200-45202-530 JUSTIFICATION: The south parking lot is one of two lots designed to serve the Wobegon Welcome Center. The north parking lot, which was designed to handle automobile traffic only, was completed in 2004. The south lot is designed to handle automobiles and vehicles with snowmobile trailers. An easement will be required to access the lot from the intersection of Elm Street East and First Avenue Northeast. A cost for right-of-way was not included due to pending negotiations with both property owners. Cost figures will change if the existing parking lot is incorporated into the site. This project is eligible to use 1/2¢ sales tax revenue, but not planned to use local option sales tax. It is anticipated the parking lot would be paved with other resurfacing projects to provide a better economy of scale for this parking lot. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Levy Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score34.8 PROJECT COSTS Preliminaries PROJECT STARTING DATE: TBD Land Acquisition PROJECT COMPLETION DATE:Construction Equipment and Other Total NEIGHBORHOOD: Northwest City Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 19 PTR-03 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Klinefelter Park Utilities$277,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Restroom and Utility Addition to Klinefelter Park Account Code: JUSTIFICATION: See the Park Board CIP for description of this project. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Levy $187,000$187,000 Park Dedication $40,000$40,000 Debt Levy - Sewer $25,000$25,000 Debt Levy - Water $25,000 $25,000 Priority Score34.8 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2022 Land Acquisition Construction PROJECT COMPLETION DATE: 2023$277,000 Equipment and Other Total NEIGHBORHOOD: Northwest City$277,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 20 ENG-1520 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: CSAH 75 Pedestrian Crossing$4,326,000 Regional Trails 2020 Budget:PROJECT CATEGORY: DESCRIPTION: CSAH 75 Pedestrian Crossing Account Code: E200-45202-303 JUSTIFICATION: Study completed in 2017 to determine location/type of pedestrian crossing to safely connect the north and south of CSAH75 St. Joseph community. The preferred crossing option includes an underpasse at 4th Avenue/Northland Dr. Other intersections may receive other options for longer count-down clocks, colored crosswalks, etc. A State bonding request was submitted for the 2018 State Legislation session. Council approved lobbyist funding for the 2019 MN Legislative session. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total 1/2 Cent Sales Tax $2,826,000$2,826,000 State Bonding $1,500,000$1,500,000 APO Debt Levy Priority Score37.3 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2024 Land Acquisition Construction PROJECT COMPLETION DATE: 2025$4,326,000 Equipment and Other Total NEIGHBORHOOD: CSAH 75/4th Avenue$4,326,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 21 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Baseball Parking Lot Improvement$103,000 $103,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Reconstruct and Expand Existing Parking Lot Account Code: 200-45203-530 JUSTIFICATION: This plan provides removal of existing bituminous parking lot and reconstruction of an expanded lot with new asphalt to the south of the bleacher and shelter area. The typical section is estimated for 6" gravel, 2" non-wear bituminous, and 1 1/2" wear course bituminous without curb and gutter. Staff recommends this project be completed with other resurfacing improvements for economies of scale in project costs. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Levy $103,000$103,000 Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score39.9 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2020 Land Acquisition Construction PROJECT COMPLETION DATE: 2021$103,000 Equipment and Other Total NEIGHBORHOOD: Northwest City$103,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 22 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Trail Maintenance$21,000 $21,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Trail Maintenance Account Code: JUSTIFICATION: This project consists of trail pavement rehabilitation intended to improve the serviceability and ride quality of paved trails. The trail segments have surface deficiencies such as surface cracking and pavement raveling. Trail maintenance is necessary to preserve the pavement. Fog seal preserves the fine aggregate at the top of the pavement to help prevent oxidation and pop outs/divets and cracks. The seal in placed to extend the quality and life of the pavement. Slurry seal is another option that smooths the top surface by filling in voids. Trails identified for slury seal are Dale Street & Jefferson Lane, and north of the Foot Golf Park. Fog seal is planned for MN street and County Road 2 to the Wobegon Trail, Hollow Park, Water tower, and the 2015 Foot Golf Park area. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Levy $21,000$21,000 Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2020 Land Acquisition Construction PROJECT COMPLETION DATE: 2021$21,000 Equipment and Other Total NEIGHBORHOOD: Northwest City$21,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 23 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Northland Park Trail Improvements$309,000 $309,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construct Multiuse Trail Account Code: JUSTIFICATION: The Park and Trail system plan completed in 2008 identified a lack of internal and external trail connections at Northland Park. An opportunity was identified to construct a multi user trail around the perimeter of the Park. The plan includes grading, construction, and restoration of an 8' wide bituminous trail. The structural section of the trail is to be constructed with 6" gravel, 2 1/2" bituminous pavement. This trail will provide one of the internal connections to the citywide pathway and trail system. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Levy $309,000$309,000 Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2020 Land Acquisition Construction PROJECT COMPLETION DATE: 2021$309,000 Equipment and Other Total NEIGHBORHOOD: Northwest City$309,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 24 ENG-1544 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Field Street (7th Avenue to 16th Avenue)$6,313,000 Streets 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construction and Right of Way Acquisition - 7th Ave to 16th Avenue Account Code: New-43120-530 JUSTIFICATION: Right of Way acquistion and construction of Southern East-West Corridor from 7th Avenue to 16th Avenue with a new connection on 12th Avenue. The road will provide the southern access for the Graceview and Pond View developments. The road is envisioned to be constructed as two lane parkway with a center boulevard. The APO has a request in for federal transportion funds, but the project did not get included in the transportation bill. Since the street has regional significance as the southern loop around the city sales tax revenue can be used to construct this road. Deferred assessments to the south of the road are also considered for this project. In the future, the street is anticipated to connect to 20th Avenue to the east and the proposed Gateway Commons area near I-94. The projected costs include debt levy and 1/2¢ sales tax funds. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Developer Assessments $3,787,800$3,787,800 Debt Levy $1,525,200$1,525,200 MSAS $500,000$500,000 1/2 Cent Sales Tax $500,000$500,000 Priority Score16 PROJECT COSTS PROJECT STARTING DATE:Preliminaries 2023 Land Acquisition PROJECT COMPLETION DATE:Construction 2024$6,313,000 Equipment and Other NEIGHBORHOOD:Total South City$6,313,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 25 ENG-1528 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: North Corridor ROW & Construction \[73rd Ave to TBD Streets 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construction and Right of Way Acquisition - 73rd Av to CR 133 Account Code: New-43120-530 JUSTIFICATION: Right of Way acquistion and construction of the North Corridor from 73rd Avenue to CR 133. - based on the APOs 2010-2013 Transportation Improvement Program (TIP). Project not included in the 2010 federal appropriations bill. The Council opted to release the federal funding for this project. The Council felt the need for construction was not as urgent. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Debt Levy Federal/State/County Priority Score16 PROJECT COSTS PROJECT STARTING DATE:Preliminaries TBD Land Acquisition PROJECT COMPLETION DATE:Construction Equipment and Other NEIGHBORHOOD:Total North East-West City Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 26 ENG-1513 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: North Corridor EISTBD Streets 2020 Budget:PROJECT CATEGORY: DESCRIPTION: EIS for North Corridor Account Code: New-43120-530 JUSTIFICATION: Tier I Environmental documentation CR 133 to CSAH 3 - based on APO 2010-2013 Transportation Improvement Program (TIP). The scoping document was going to completed in 2012, but has been suspended since federal funding is not included in the 2010 transportation bond for the EIS document. The project is not a "financially constrained" project in the APO's 2035 Transportation Plan, therefore the Federal Highway Administration will not consider the environmental document. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Debt Levy (20%) Federal/State/County (80%) Priority Score16 PROJECT COSTS PROJECT STARTING DATE:Preliminaries TBD Land Acquisition PROJECT COMPLETION DATE:Construction Equipment and Other NEIGHBORHOOD:Total North East-West City Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 27 ENG-1523 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Jade Road ExtensionTBD Streets 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Street Construction - CR 121 (Jade Road) to 20th Avenue Corridor Account Code: New-43120-530 JUSTIFICATION: The plan proposes an east-west connection from County Road 121 to the proposed 20th Avenue Corridor. It provides a 4200 lineal foot three lane road, curb & gutter construction with storm sewer, a sidewalk or trail behind the back of curb, and turn lanes off of County Road 121. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Developer Assessments Debt Levy Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score16 PROJECT COSTS PROJECT STARTING DATE:Preliminaries TBD Land Acquisition PROJECT COMPLETION DATE:Construction #VALUE! Equipment and Other NEIGHBORHOOD:Total South City Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 28 ENG-1532 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: 20th Avenue SE Improvements (North)$2,161,000 Streets $2,161,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Corridor CSAH 75 to N Line of Rassier Property Account Code: New-43120-530 JUSTIFICATION: This plan provides for future transportation corridor in the area of 20th Avenue E. The corridor is an estimated 3-4 lane undivided roadway from CSAH 75 to the North line of the Rassier Property. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Developer Assessments (70%) $1,512,700$1,512,700 Federal/State/County $648,300$648,300 Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score16 PROJECT COSTS PROJECT STARTING DATE:Preliminaries 2020 Land Acquisition PROJECT COMPLETION DATE:Construction 2021$2,161,000 Equipment and Other NEIGHBORHOOD:Total South and East City$2,161,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 29 ENG-1547 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: 20th Avenue SE Construction (South)TBD Streets 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Corridor Construction - Rassier property to 290th Street Account Code: New-43120-530 JUSTIFICATION: The plan provides for an extension of 20th Avenue for future transportation corridor. The estimate is based on constructing 5300 lineal feed of 44' roadway from the Rassier property to 290th Street. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Levy Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score16 PROJECT COSTS Preliminaries PROJECT STARTING DATE: TBD Land Acquisition PROJECT COMPLETION DATE:Construction Equipment and Other Total NEIGHBORHOOD: South and East City Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 30 ENG-1529 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: North Corridor ROW & Construction \[CR133 to C TBD Streets 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construction and Right of Way Acquisition - CR133 to CSAH 3 Account Code: New-43120-530 JUSTIFICATION: Right of Way acquistion and construction of the North Corridor from CR 133 to CSAH 3 - based on the APOs 2010- 2013 Transportation Improvement Program (TIP). Project not included in the 2010 federal appropriations bill. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Debt Levy Federal/State/County Priority Score16 PROJECT COSTS Preliminaries PROJECT STARTING DATE: TBD Land Acquisition PROJECT COMPLETION DATE:Construction Equipment and Other Total NEIGHBORHOOD: North East-West City Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 31 ENG-1529 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: CR133 & Elm Street Improvements$4,073,000 Streets 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construction and Right of Way Acquisition - CR133 and Elm Street Intersection Account Code: JUSTIFICATION: This plan provides for right of way acquistion and reconstruction of County Road 133 from Elm Street to CSAH 75. The right of way acqusition is planned to add a median and one additional lane on County Road 133 from Elm Street to CSAH 75. At the intersection of Elm Street, a roundabout is planned to accomodate better traffic flow patterns for the anticipated Elm Street East West connection. Stearns County will have a cost share in the project for the County Road construction. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Debt Levy $4,073,000$4,073,000 Federal/State/County Priority Score PROJECT COSTS Preliminaries PROJECT STARTING DATE: TBD Land Acquisition PROJECT COMPLETION DATE:Construction $4,073,000 Equipment and Other Total NEIGHBORHOOD: North East-West City$4,073,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 32 ENG-1515 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Southwest Trunk Water$1,757,000 Water Main System 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construct a trunk water main - CSAH 2 to CSAH 75 Account Code: E601-49430-530 JUSTIFICATION: This plan provides for 4,800 feet of 16" trunk water main between CSAH 2 and CSAH 75 and 12" trunk watermain along CSAH 75 to 1st Ave NW. It does not include cost for the lateral connections to the adjacent developments. City Council may consider the option to update the comprehensive water study to include future development needs along CSAH 2/3. It is anticipated this project may be developer/development driven. No easement or land acquisition costs are included. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Developer $768,150$768,150 Assessments (45%) Trunk Water (55%) $938,850$938,850 Water Revenue $50,000$50,000 Priority Score31.5 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2022$50,000 Land Acquisition Construction PROJECT COMPLETION DATE: 2023$1,707,000 Equipment and Other Total NEIGHBORHOOD: Southwest City$1,757,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 33 ENG-1908 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: CSAH 2 Water Extension$1,463,000 Water Main System 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construct a trunk water main to serve development Account Code: E601-49440-530 JUSTIFICATION: This plan provides for extending a watermain to serve development property on both the East and West sides of the CSAH 2 corridor. It is anticipated this project may be developer/development driven. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Developer $1,413,000$1,413,000 Assessments (45%) Water Revenue $50,000$50,000 Priority Score31.5 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2022$50,000 Land Acquisition Construction PROJECT COMPLETION DATE: 2023$1,413,000 Equipment and Other Total NEIGHBORHOOD: Southwest City$1,463,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 34 ENG-1510 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: New Water Tower$3,839,000 Water System Storage 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construct a 750,000 gallon water tower Account Code: E601-49436-303/E601-49436-530 JUSTIFICATION: The 2006 water system comprehensive study indicated a shortage of 40,000 gallons per day for recommended storage capacity. The additional capacity would allow for better fire flow sustainability and provide redundancy to perform necessary repairs and maintenance on water tower 1. The construction of three new wells with the water treatment plant in 2007 provided additional supply and has afforded the City time to plan for additional storage capacity. The city's current storage capacity is 500,000 gallons. The City Council approved Design of the second tower in 2008, but has delayed bidding, construction, and construction administration due to stabilization in water demands and development activity. Council determined the second water tower will be added as development occurs and the storage capacity is needed. Staff is estimating the second tower will be needed in approximately 2022. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total WAC $950,000$950,000 Water Revenue $2,889,000$2,889,000 Priority Score31.5 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2024$75,000 Land Acquisition Construction PROJECT COMPLETION DATE: 2025$3,764,000 Equipment and Other Total NEIGHBORHOOD: Citywide$3,839,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 35 ENG-1527 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Upgrade Old Water Main$2,930,000 Water System - Trunk 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Upgrade old water main 1st Ave NW, College Ave, Cedar St Account Code: E601-49430-530 JUSTIFICATION: This plan includes upgrading the old water main (installed between 1949 and 1950) with new pipe on 1st Avenue NW from CSAH 75 to Date, College Avenue from Ash to Elm, Cedar Street from 1st Avenue to Ace Hardware. This estimate includes the addition of a water main on Elm Street from 1st Avenue NW to College Avenue. In 2013, it was determined that the pipes were still functioning ok. The pipe replacement is anticipated when the streets are reconstructed (appx. 15-20 years). PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments $2,430,000 $2,430,000 Debt Levy Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water $500,000$500,000 Priority Score25.15 PROJECT COSTS Preliminaries PROJECT STARTING DATE: 2023 Land Acquisition Construction PROJECT COMPLETION DATE: 2024$2,930,000 Equipment and Other Total NEIGHBORHOOD: North Side CSAH 75$2,930,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 36 ENG-1542 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: St. Wendel Trunk WaterTBD Water System - Trunk 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construct a 16" water main to serve St. Wendel Township Account Code: E601-49440-530 JUSTIFICATION: This plan provides for 6,250 feet of 16" water main to serve St. Wendel Township. The funding schedule assumes the entire length of water main will be assessed at a rate equivalent to the probable cost of constructing an 8" water main plus the probable cost of the utility easements. The balance of the funding is scheduled to come from bonding covered by future water main trunk fees. The plan accounts for 65' of construction width, including 15' within the right of way, 10' (1.4 acres) within perpetual utility easements and 40' (5.7 acres) within temporary construction easements. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments Debt Levy Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score12.35 PROJECT COSTS Preliminaries PROJECT STARTING DATE: TBD Land Acquisition PROJECT COMPLETION DATE:Construction Equipment and Other Total NEIGHBORHOOD: St. Wendel Township - North City Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 37 ENG-1514 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: Southwest Trunk Sewer$5,275,000 Sanitary Sewer System - Trunk 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construct a trunk sewer to serve the SW area Account Code: E602-49480-530/E602-49480-510 JUSTIFICATION: This plan provides for 6,000 feet of 24"- 42" trunk sanitary sewer to be constructed along the south fork of the Watab River, from the existing Main Pump Station to I-94. The pipe will be sized to serve growth to the west from the current city limits to I-94, and along CSAH 2 southwest to I-94. The plan accounts for a 50' of acquired perpetual utility easements and 50' of acquired temporary construction easements, or approximately 7.5 acres for each. It is anticipated that actual construction will depend on potential development tied to CR2/3 realignment construction. In 2008/2009 the City updated the comprehensive sewer study to include the area to be served by the SW trunk sewer to analyze the future capacity needs. Easements are estimated to cost $73,000 in 2012. Council requested staff to research alternative options of providing sewer to the Gateway Commons Area as an isolated short-term alternative to service the area south of Minnesota Street, north of I-94 and east of CSAH 2. The short- term alternative is funded for a 2014 project in coordination with the Park Terrace improvements. The sewer capacity in Park Terrace would allow for some development to the south of the City. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Developer $3,165,000$3,165,000 Assessments Trunk Sewer Debt - $2,030,000$2,030,000 Main Trunk Sewer Debt - Land $80,000$80,000 Priority Score31.5 PROJECT COSTS PROJECT STARTING DATE:Preliminaries 2022$50,000 Land Acquisition $80,000 PROJECT COMPLETION DATE:Construction 2023$5,195,000 Equipment and Other NEIGHBORHOOD:Total Southwest City$5,325,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 38 ENG-1907 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: CSAH 2 Sewer Extension$3,264,000 Sanitary Sewer System 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construct a sewer to serve the SW area Account Code: E602-49450-530 JUSTIFICATION: This plan provides for extending a Sanitary sewer to serve development property on both the East and West sides of the CSAH 2 corridor. It is anticipated this project may be developer/development driven. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Developer Assessments $3,264,000$3,264,000 Priority Score31.5 PROJECT COSTS PROJECT STARTING DATE:Preliminaries 2022$50,000 Land Acquisition PROJECT COMPLETION DATE:Construction 2023$3,264,000 Equipment and Other NEIGHBORHOOD:Total Southwest City$3,314,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 39 ENG-1522 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: CR121 Lift Station Generator$213,000 Sanitary Sewer Pumping 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Purchase a stationary generator to free up the portable generator. Account Code: E602-49473-530 JUSTIFICATION: This plan provides for the purchase of a 100 kW stationary generator with an auto-transfer switch and a sound attenuation and fencing package for the CR 121 lift station. This purchase will free up the portable generator to be used at the other lift stations as needed. The construction of the stationary generator for the CR 121 lift station should coincide with the construction of the lift station designed to serve the Rivers Bend development. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total $213,000$213,000 Trunk Sewer - CR 121 Priority Score31.4 PROJECT COSTS PROJECT STARTING DATE:Preliminaries 2024 Land Acquisition PROJECT COMPLETION DATE:Construction 2025$213,000 Equipment and Other NEIGHBORHOOD:Total CR 121 - South$213,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 40 ENG-1535 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: CIPP Improvements 1st Ave NE$111,000 Sanitary Sewer System - Trunk $111,000 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Sanitary Sewer Lining Account Code: 602-49450-530 JUSTIFICATION: This plan provides for 375 lineal feet of sanitary sewer to be lined with a cured in-place pipe (CIPP) liner on 1st Avenue NE from Date Street to Elm Street. Televising reports from the line indicate deficiences in the pipe such as offset joints, roots, sags in the pipe, and logitudinaland service tee cracks. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Sewer Revenue $111,000 $111,000 Priority Score40.6 PROJECT COSTS PROJECT STARTING DATE:Preliminaries 2020 Land Acquisition PROJECT COMPLETION DATE:Construction 2021$111,000 Equipment and Other NEIGHBORHOOD:Total Northeast City$111,000 Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 41 ENG-1541 CITY OF ST. JOSEPH CAPITAL IMPROVEMENT PLAN 2020-2024 PROJECT TITLE:TOTAL COST: St. Wendel Trunk SewerTBD Sewer System - Trunk 2020 Budget:PROJECT CATEGORY: DESCRIPTION: Construct the trunk sewer to serve St. Wendel Township Account Code: E602-49480-530 JUSTIFICATION: This plan provides for 6,000 feet of trunk sanitary sewer to serve St. Wendel Township. The funding schedule assumes that approximately 66% of the entire length of trunk sewer will be assessed at a rate equivalent to the probable cost of an 8" sanitary sewer of the same length, plus the probable acquisition costs of the associated utility and construction easements. The balance of the funding is scheduled to come from bonding covered by future sewer trunk fees. The plan assumes a construction width of 100', including 50' (6.9 acres) of acquired perpetual utility easements and 50' (6.9 acres) of acquired temporary construction easements. PROJECT COSTS AND FUNDING SOURCES BY YEARS: Project FundingPrior SourceYears20202021202220232024Total Special Assessments TBD Debt Levy Debt Levy - Storm Debt Levy - Sewer Debt Levy - Water Priority Score12.35 PROJECT COSTS Preliminaries PROJECT STARTING DATE: TBD Land Acquisition PROJECT COMPLETION DATE:Construction Equipment and Other Total NEIGHBORHOOD: St. Wendel Township - North City Presented to the City Council on ________________Approved_________ Denied _________ Tabled _________ Comments Approval to Purchase Date_________________________Authorizing InitialsDate ENG- 42